The document is a proposed schedule for a project by the City of Fort Myers, with a contract number NR254209XXXXC010. The project timeline spans from April 28, 2025, to April 10, 2026, and includes multiple key stages such as a PreDesign Conference, document preparation, NRCS review, purchasing, council approval, construction, and final inspection. The schedule outlines a comprehensive workflow beginning with contract execution and progressing through coordination, document submission, reviews, approvals, and construction, with the construction phase scheduled to last 210 days from August 11, 2025, to March 9, 2026.
The agreement expires on April 10, 2026, with critical milestones including a 16-day coordination period for the PreDesign Conference, 14-day document submission to NRCS, 30-day purchasing phase, 24-day council approval period, and a 7-day notice to proceed. The final stages involve a 14-day final inspection and punchlist period, followed by a 14-day submittal of as-built documents. No specific pricing, funding sources, or financial details are provided in this scheduling document.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NR254209XXXXC010
Proposed Schedule
City of Fort Myers
Task Start Date Duration End Date Executed Contract 04/28/2025 1
Coordinate for PreDesign Conference 04/28/2025 16 05/14/2025
PreDesign Conference 05/14/2025 0 05/14/2025 Prepare requested documents 05/14/2025 0 05/14/2025
Sent Document to NRCS 05/14/2025 14 05/28/2025 Prepare Responses 05/28/2025 2 05/30/2025
NRCS Review 05/30/2025 12 06/11/2025 Purchasing 06/11/2025 30 07/11/2025
Council Approval 07/11/2025 24 08/04/2025 Notice to Proceed 08/04/2025 7 08/11/2025
Construction 08/11/2025 210 03/09/2026 Final Inspection /
Punchlist 03/09/2026 14 03/23/2026
Submittal of As-Builts 03/23/2026 14 04/06/2026
Agreement Expiration Date 04/10/2025 04/10/2026
Agreement Expiration Date: April 10, 2026