Schedule of Submittals.xlsx

XLSX spreadsheet 34 KB Posted

Attached to
RENOVATE RUNWAY CONTROL STRUCTURE B1776
Solicitation number
FA309926Q0021
Issued by

About this file

This is a Schedule of Submittals for a design-build construction project (Project #22-1006) to renovate Runway Control Structure Building 1776 at Laughlin Air Force Base. The schedule outlines all required contractor submissions across three Notice-to-Proceed (NTP) phases: design, pre-construction, and construction.

During the Design phase (NTP 1), the contractor must submit security clearance documentation and training certifications two weeks prior to base access, a site investigation agenda at NTP 1, and design packages at 65%, 95%, and 100% completion levels at 56, 49, and 35-day intervals respectively, with two paper copies of drawings required. The Pre-Construction phase (NTP 2) requires submission of Entry Access Lists, AF Form 103 Work Clearance Requests, contractor safety plans and qualifications, quality control plans, construction site plans, hazardous material documentation, asbestos/lead abatement plans, traffic control plans, and records of existing conditions, all due within 30 days of NTP 2 unless otherwise specified. The Construction phase (NTP 3) mandates ongoing submissions including waste disposal manifests, hazmat usage logs, quality control daily inspection reports, weekly progress schedules, biweekly meeting minutes, materials testing results, operation and maintenance data, as-built drawings within two weeks of final inspection, and a construction warranty management plan. Additional project-specific requirements include FAA Determination Form 7460-1 prior to the end of NTP 2 and DD Form 1354 completion prior to and at final inspection.

View the file

Other files

File Type Posted
RCS B1776 Site Visit Attendees List.pdf PDF
Exterior Image 1.jpg JPG image
Site Visit Questions and Answers.docx DOCX document
Exterior Image 3.jpg JPG image
Exterior Image 5.jpg JPG image
Exterior Image 6.jpg JPG image
Exterior Image 8.jpg JPG image
Exterior Image 2.jpg JPG image
Exterior Image 4.jpg JPG image
Exterior Image 7.jpg JPG image
Solicitation Amendment FA309926Q00210001 .pdf PDF
SOW- Renovate RSU 1776 _revised 9.15.pdf PDF
SOW- Renovate RSU 1776 .pdf PDF
2026-CEMIRT Report of Visit.pdf PDF
B. Division 01 Specification Guidelines.docx DOCX document
Solicitation - FA309926Q0021.pdf PDF
SOW- Renovate RCS 1776 .docx DOCX document
F. B1700 Hazardous Material Test Report.pdf PDF
C. EQ Contractor Tech Specs FY26.pdf PDF
H. LeadReport Bldg 1700_1995.pdf PDF
D. Laughlin AFB Installation Facilities Standards.pdf PDF
E. Laughlin AFB Short-Term Contractor Hazmat Usage Log.pdf PDF
Progress Schedule and Progress Report.xlsx XLSX spreadsheet
Wage Determination TX20260186.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # 22-1006 PROJECT TITLE Renovate RCS B1776 SOLICITATION / CONTRACT NO.

(To be completed by Project Engineer)(To be completed by Contract Administrator)
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALLAUGHLIN DIV 01 SPECIFICATIONSENVIRONMENTAL QUALITY CONSTRUCTION SPECIFICATIONS LAFBSTATEMENT OF WORK OR OBJECTIVESNUMBER OF PAPER COPIES REQUIRED. DIGITAL COPIES ARE REQUIRED FOR ALL SUBMITTALSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS

APPR

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

DIS

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

NTP 1 - Design
Entry Access List (EAL)1.8.22 Weeks prior to base access
Proof of OPSEC Training2.42 Weeks prior to base access
Antiterrorism Level I Awareness Training2.42 Weeks prior to base access
Site investigation agenda5.2at NTP 1
Summary of site investigation5.3NLT 14 Days after NTP 1
65% Design Package3.1.12 (drawings only)NLT 56 Days after NTP 1
95% Design Package3.1.22 (drawings only)NLT 49 Days after approved 65%
100% Design Package3.1.32 (drawings only)NLT 35 Days after approved 100%
Material Submittal Register3.1.3.5with 100% design
Progress Schedule Form and Contract Progress Report6.1.1Biweekly
Meeting Minutes6.2.1NLT 3 Days after meeting
NTP 2 - Pre Construction
Entry Access List (EAL)1.8.22 Weeks prior to base access
AF Form 103, Work Clearance Request2.23.3.1NLT 30 days after NTP 2
Proof of OPSEC Training2.42 weeks prior to base access
Contractor Safety Plan3.2.23.4.2.2NLT 30 days after NTP 2
Certificate of Contractor Safety Compliance3.2.3NLT 7 days after NTP 2
QC Manager Qualifications4.2.33.1.2NLT 7 days after NTP 2
QC Plan4.2.4NLT 30 days after NTP 2
Construction Site Plan12.1NLT 30 days after NTP 2
Hazardous Material Approval (Safety Data Sheets)3.2.1NLT 30 days after NTP 2 (as required)
Hazardous Waste Training Certificate3.2.2Prior to NTP 3

(as required) Hazardous Waste / Material Procedures 3.2.2 Prior to NTP 3 (as required)

Asbestos/Lead Hazard Abatement Plan3.5.2.1NLT 10 days prior to construction start
Copy of notification to Department of State Health Services3.5.2.1NLT 10 days prior to construction start
Worker/Area Protection Plan3.5.2.2Prior to NTP 3

(as required) FOD Plan 14.10 Prior to NTP 3 (as required) Laydown Yard 2.5.7.3 Prior to NTP 3 (as required)

Phase Plan6.1.2NLT 30 Days after NTP 2
Traffic Control Plan12.25.3, 5.5NLT 30 Days after NTP 2
Records of Existing Conditions1.5, 7.1.14.2, 4.4, 5.5NLT 30 Days after NTP 2
Submittals per Contractor's Design10.4.4 through 10.4.11TBD
NTP 3 - Construction
Non-Hazardous Waste Disposal Manifest and/or Waste Shipment Record5.1 / 6.2NLT 45 days from the date of signature of receiving facility
Hazardous Waste Disposal Manifests5.2 / 6.2As required, prior to removal from Government property
Hazmat Usage Log6.1End of each month during construction
QC Daily Inspection Reports4.2.6Weekly
Progress Schedule Form and Contract Progress Report6.1Biweekly
Meeting Minutes6.2.1NLT 3 Days after meeting
Records of Existing Conditions7.1.1NLT 14 days after NTP 2
Materials Testing7.1.3As required, within 7 days of test
Submittals per Contractor's Design SOW10.4.4 through 10.4.11TBD
Operation and Maintenance Data10.4.12NLT 2 weeks after Final Inspection
As Built Drawings/CAD Files10.4.132 (D size)NLT 2 weeks after Final Inspection
Completion Inspection (QC Manager Punchlist)13.4NLT 3 days after Pre-Final Inspection
Draft DD Form 135413.3Prior to Pre-Final Inspection
Final DD Form 135413.3At Final Inspection
Other Material and sample submittals per Contractor's DesignTBD
Construction Warranty Management Plan13.2NLT 2 weeks after Final Inspection
Project Specific Submittals
FAA Determination 7460-12.5.2prior to end of NTP 2
Schedule of Submittals Template, Feb 05 (SAF/AQCP)

Task Order # FA3099-16-D-0002-0002 SOW Atch 2

&"Times New Roman,Regular"&12Page &P of &N