About this file
This document is a procedure guide issued by the Central Florida Tourism Oversight District (CFTOD) Construction Management Division of Public Works, effective May 2026, establishing mandatory storm preparation protocols for all construction and roadway contractors performing active work on CFTOD properties and public rights-of-way. The procedure outlines escalating safeguarding requirements triggered by three weather alert levels: Tropical Storm Warning, Hurricane Watch, and Hurricane Warning. Upon issuance of a Tropical Storm Warning, contractors must remove obstructions from storm drainage and sanitary systems and backfill open trenches within 24 hours. Upon Hurricane Watch issuance, all right-of-way construction operations and material deliveries suspend immediately, with additional requirements to schedule trash collection and remove roll-off containers, to be completed within 24 hours. Upon Hurricane Warning issuance, contractors must remove all equipment and materials from public rights-of-way or consolidate them in secured areas with safety markings, restore normal traffic operations, remove construction debris and portable facilities, lower crane booms, and provide CFTOD with designated emergency response personnel contact information, with all tasks completed within 12 hours of warning issuance or 12 hours prior to projected landfall, whichever occurs first.
Compliance with storm preparation procedures is mandatory regardless of time of day, day of week, or holiday status, with no exemptions from prescribed completion timeframes. Following a storm event, contractors are prohibited from resuming work or entering public rights-of-way without prior written authorization from the Public Works Department, which will be determined on a case-by-case basis. The Construction Management Department will assess post-storm damage, communicate required corrective actions to project stakeholders, and coordinate remediation efforts. Contractors' designated emergency response personnel must promptly assess assigned worksites to identify, address, and mitigate damage or safety hazards and verify utility operations. The procedure emphasizes that contractors should monitor public storm advisories, take proactive measures to secure work sites, and document site conditions with pre-storm video and photographs containing date and time subtitles.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OversightDistrict.org 1
CONSTRUCTION MANAGEMENT
REQUIRED STORM PREPARATION PROCEDURES
FOR PUBLIC RIGHT-OF-WAY AND PUBLIC PROPERTY
PROCEDURE NUMBER: XXXX Version: May 2026
CATEGORY: 04 – Construction Pages: 6
DEVELOPED BY: Construction Management Division of Public Works
Effective: May 2026
Exemptions: No Exemptions Minimum Procedure Review Period: Annually
Revision Revision Date Description Effective Date
1 June 2017 Original Revision June 2017 2 May 2026 Revision May 2026
Purpose The purpose of the procedure is to outline the steps that need to be taken in order to secure construction and roadway sites in advance of an expected hurricane or other severe storm event.
Contractors I Permit holders are encouraged to take proactive measures in securing their work site and the public rights-of-way to ensure public safety and the protection of completed work in the event of tropical cyclone activity. Contractors I Permit holders should monitor public storm advisories and individual storm progress.
Scope This procedure applies to all construction and roadway contractors performing active work under contract with the Central Florida Tourism Oversight District (CFTOD) on any of the CFTOD properties and roadways and is administered by the Construction Management & Planning and Engineering Divisions of the Public Works Department.
Definitions Not applicable.
pwheatley Text Box
SA-03
OversightDistrict.org 2
TROPICAL STORM WARNING ISSUED
Upon the issuance of a Tropical Storm Warning for CFTOD property, all contractors I permit holders performing work on public property or in the public right-of-way shall immediately safeguard the work and property within and adjacent to the project work area as follows:
• Remove obstructions from the public storm drainage system and make all necessary repairs to allow for the collection and discharge of storm water runoff.
• Remove obstructions from the public sanitary gravity and force main sewage system and complete all necessary repairs to allow for collection and conveyance of sanitary sewage.
• Remove all construction debris and backfill all open trenches to provide a temporary surface suitable for vehicular and pedestrian traffic. Steel plating will not be permitted.
Tropical storm warning preparation tasks should be completed within 24 hours of issued warning.
PROCEDURES
OversightDistrict.org 3
HURRICANE WATCH ISSUED
Upon the issuance of a Hurricane Watch for CFTOD property, all contractors I permit holders performing work on public property or in the public right-of-way shall immediately safeguard the work and property within and adjacent to the project work area as follows:
• All right-of-way construction operations shall be suspended immediately. Construction activity on CFTOD projects or within the public rights-of-way, not directly related to the safeguarding of public property or public rights-of-way, will not be permitted.
• All right-of-way construction permits will be suspended immediately.
• Delivery of material or equipment to CFTOD projects or projects within the public rights-of-way will be suspended immediately.
• Remove all obstructions from the public storm drainage system and make all necessary repairs to allow for the collection and discharge of storm water runoff.
• Remove obstructions from the public sanitary gravity and force main sewage system and complete all necessary repairs to allow for collection and conveyance of sanitary sewage.
• Backfill open trenches and provide a temporary surface suitable for vehicular and pedestrian traffic. Steel plating will not be permitted.
• Schedule roll-off trash collection and remove roll-off container(s) from the public right-of-way.
• CFTOD personnel will evaluate site conditions and may identify construction equipment that contractors and permit holders must remove from the site upon issuance of a hurricane warning.
Hurricane watch preparation tasks should be completed within 24 hours of issued watch.
OversightDistrict.org 4
HURRICANE WARNING ISSUED
Upon the issuance of a Hurricane Warning for the CFTOD, all contractors I permit holders performing work on public property or in the public right-of-way shall immediately safeguard the work and property within and adjacent to the project work area as follows:
• Remove all equipment and material from the public right-of-way. Equipment and material that cannot be removed must be condensed into a single area out of the public roadway.
Equipment that cannot be removed out of the public right of way shall be supplemented with appropriate safety markings, to the satisfaction of District personnel, to increase visibility in heavy rain or flooding situations.
• In accordance with traffic modification standards, remove all MOT and restore normal vehicular traffic operation. In cases where MOT may not be safely removed, the District Construction Project Manager/Traffic Engineer must be notified immediately. Barricades and signage must be secured with direct burial or sand bagging. If deemed necessary by CFTOD personnel, the placement of concrete barriers may be required. The District Construction Project Manager/Traffic Engineer may impose additional site securing requirements, as deemed necessary.
• Remove all construction debris, unused barricades, construction materials, permit boards, portable toilets, and similar material. Material may be stored in a secured building on site.
• Crane booms shall be lowered in a safe position.
• Contractors may be advised to take additional measures, at the discretion of CFTOD personnel, which are deemed necessary to secure the public right-of-way and ensure public safety.
• Contractor I Permit holders are advised to record pre-storm video I photos with date/time subtitles.
• Contractors shall provide CFTOD with the names and contact information of designated emergency response personnel who will be available to respond following the official “all clear” issued by the CFTOD Emergency Management Team.
Hurricane warning preparation tasks must be completed within 12 hours of issued warning or 12 hours prior to projected landfall, whichever is first.
OversightDistrict.org 5
Contractors I permit holders shall immediately commence storm preparation procedures upon the issuance of a hurricane watch I warning, regardless of time or day.
Regular work hours, time of day, weekends, or holidays will not be considered as providing any exemption from compliance with required completion time.
All preparations in accordance with these procedures shall be completed within the prescribed timeframe.
OversightDistrict.org 6
POST-STORM EVENT PROCEDURES
• Contractors and Permit Holders shall not resume work or enter the public rights-of-way without prior authorization from the Public Works Department. Authorization to resume operations will be determined on a case-by-case basis, based on the condition of the work and the surrounding area.
• Construction Management will assess and promptly communicate post-storm damage and required corrective actions to project stakeholders.
• The Contractor’s emergency response personnel shall promptly assess all assigned worksites and take appropriate actions to identify, address, and mitigate any damage or safety hazards, including verification of utility operations. Coordinate all necessary remediation efforts with the Construction Management Department.
DO NOT COMMENCE SUSPENDED CONSTRUCTION ACTIVITIES
PRIOR TO RECEIVING AUTHORIZATION OR DIRECTION FROM
THE CENTRAL FLORIDA TOURISM OVERSIGHT DISTRICT.