This is a Self-Performed and Subcontracted Work worksheet template for offerors responding to federal construction contracts. The document requires General Construction contractors (NAICS code 236220) to demonstrate that at least 15 percent of contract performance costs for personnel will be spent on the concern's own employees or employees of eligible service-disabled veteran-owned small business (SDVOSB) concerns, with specialty trade contractors required to meet a 25 percent threshold. Offerors must provide a detailed breakdown of material and personnel costs organized by specification division, with clear identification of self-performed work versus subcontracted work, particularly distinguishing SDVOSB vendor participation. Home office overhead, profit/fee, and bond costs are calculated separately after subtotals for personnel and material/equipment costs.

The worksheet includes a four-step calculation methodology to determine the percentage of self-performed work, requiring offerors to subtract all non-SDVOSB subcontractor personnel costs from total personnel costs and divide the remainder by total personnel costs. Personnel costs are defined to include laborers, mechanics, tradesmen, and directly charged office personnel such as project managers, job superintendents, administrative staff, and estimators. The document requires certification by an authorized representative with signature, typed name, title, and date, confirming the accuracy of representations provided.

View the file

Other files

File Type Posted
Site Visit Meeting Doc.docx DOCX document
36C25926Q0255 0002.docx DOCX document
Meeting Attendance.pdf PDF
36C25926Q0255 0001.docx DOCX document
S04 - Site Visit Meeting Doc 4th Floor Nurse Call Systems.docx DOCX document
Nurse Call System Location.pdf PDF
PCRA.pdf PDF
P03 Determination - Nurse Call System_Redacted.pdf PDF
ICRA.pdf PDF
S22 LOS Certification 852.219-75 JAN 2023 DEVIATION.docx DOCX document
36C25926Q0255.docx DOCX document
SPECS Nurse Combined.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CALCULATION OF SELF-PERFORMED/SUBCONTRACTED WORK

Offerors for General Construction (NAICS code 236220) must provide at least 15 percent (25% for specialty trade NAICS codes) of the cost of the contract performance incurred for personnel will be spent on the concern's employees or the employees of other eligible service-disabled veteran-owned small business concerns. Provide a breakdown of material and personnel costs, by specification division listed for the project. Home Office overhead, profit/fee and bond costs shall be added after a subtotal of personnel and material/Equipment costs has been calculated. Clearly identify the personnel costs you will be performing, and the personnel costs of other eligible service disabled veteran-owned small business concerns. Below is a suggested format.

Specification Division and name
SDVOSB Vendor (Y or N)
Personnel Cost
Material/Equipment Costs

Division 01

$
$

Division 02

$
$

Division 03

$
$

(Add additional lines as necessary for each Division applicable to this project)

$
$
$
$
Sub Total (Personnel Costs, Material/Equipment Costs)
$
Profit
$
Home Office Overhead
$
Bond
$
Grand Total
$

Calculation of self-performed personnel costs:

1. Total personnel costs * both prime and all subcontractors: $_________________

2. Subtract all subcontractor personnel costs* that are not SDVOSB companies that will perform work on this contract: $__________________

3. Remainder is ‘Total amount of work to be self-performed under the

Contract’:$__________________
4. Self-performed work = Line 3/Line 1 x 100 =________________%

*personnel costs include labors, mechanics, other tradesmen, and office personnel directly charged to the project (includes project manager, job superintendent, administrative, estimators, etc.)

I certify the above representations are true and correct to the best of my knowledge.

___________________________________________________________
(Signature and Typed Name of Authorized Representative)Date