This is a VHA Pre-Construction Risk Assessment (PCRA) template and completed permit for facility construction, renovation, and maintenance activities. The document provides minimum requirements for categorizing activity types and safety risks to determine appropriate precautions for Construction, Renovation, and Maintenance work affecting patients, employees, and contractors.

The template defines three activity types with corresponding control measures: Inspection/Upkeep (work completed in a single shift not exceeding 10 hours with minimal dust, debris, vapors, or fumes); Small-scale Construction (prolonged work up to six months with selective demolition, plumbing, electrical, and HVAC work); and Large-scale Construction (work exceeding six months involving excavation, heavy equipment, confined spaces, crane work, elevated work, welding, demolition, and significant building component installation). Control measures escalate by activity type and include site-specific safety plans, task hazard analyses, hazard communication, weekly site visits, daily inspections, Hot Work permits, LOTO procedures, and specialized plans for excavation, dust control, pollution prevention, dig-safe documentation, crane lifts, fall protection, and confined entry. The completed permit for Project 523-25-003 Bulk Oxygen Correction at Jamaica Plain designates this as a Large-scale activity with multiple coordination requirements across adjacent areas including the Bulk O2 Storage Area, Building 4 SARRPT, Building 5 Boiler Plant, Transportation, and Prosthetics departments. An Infection Control Risk Assessment (ICRA) has been determined as required, with signatures from Infection Prevention and Control, Project Manager, and Safety Officer dated June 24-25, 2025.

View the file

Other files

File Type Posted
36C24126Q0398 0003.docx DOCX document
Site Utility Plan.pdf PDF
AUL Maps - JP.pdf PDF
VA Med AUL 2007.pdf PDF
36C24126Q0398 0002 6-16-26.docx DOCX document
S06 36C24126Q0398 0001.pdf PDF
523-25-003.CD.VABOS-O2-V1-Br-Dwg-Stamped.pdf PDF
523-25-003.CD.VABOS-O2-V3-WR-Spec.pdf PDF
523-25-003 Bulk Oxygen Corrections_Site Visit Sign-in JP WX.pdf PDF
523-25-003 Bulk Oxygen Corrections_Site Visit Sign-in BK.pdf PDF
523-25-003.CD.VABOS-O2-V2-JP-Dwg-Stamped.pdf PDF
523-25-003.CD.VABOS-O2-V1-Br-Spec.pdf PDF
523-25-003.CD.VABOS-O2-V3-WR-Dwg-Stamped.pdf PDF
523-25-003.CD.VABOS-O2-V2-JP-Spec.pdf PDF
S02-S02-523-25-003 CD VABOS O2 V1 Br Spec .pdf PDF
S02-S02-523-25-003 SOW Bulk Oxygen Correction Construction.docx DOCX document
S02-S02 ICRA JP Bulk O2 523-25-003 .pdf PDF
S02-S02-26_0303 New O2 VAMC Brockton B8 Proposed Location - Copy.pdf PDF
S02-S02-PCRA WRX Bulk O2 523-25-003 June 25 sign .pdf PDF
S02-S02- Wage Determination Brockton.pdf PDF
S02-S02-523-25-003 CD VABOS O2 V2 JP Spec .pdf PDF
S02-S02-523-25-003 CD VABOS O2 V3 WR-Spec .pdf PDF
S02-S02 West Roxbury Base Offer Breakdown.xlsx XLSX spreadsheet
S02-S02 36C24126Q0398 Karla review.docx DOCX document
S02-S02 Brockton Base Offer Breakdown.xlsx XLSX spreadsheet
S02-S02 ICRA WRX Bulk O2 523-25-003 .pdf PDF
S02-S02-BK Bulk O2 PCRA Signed By PM .pdf PDF
S02-S02-523-25-003 VABOS O2 Dwg All .pdf PDF
S02-S02- Wage Determination West Roxbury_Jamaica Plains.pdf PDF
S02-S02 Jamaica Plains Base Offer Breakdown.xlsx XLSX spreadsheet
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VHA Pre-Construction Risk Assessment (PCRA)

VHA-PCRA-2024-1.1 (May 21, 2024) Page 1 of 5

PCRA Introductory Information and Instructions

Use this template as a baseline for performing facility Pre-Construction Risk Assessments (PCRA) for Construction, Renovation, and Maintenance work (referred to as the “activity” in this document). The template provides minimum requirements for categorizing activity type(s) and safety risk to determine the level of precautions needed to prevent impact related to Construction, Renovation and Maintenance on patients, employees, and contractors.

Ensure that the activity statement of work and any drawings available are used for the PCRA assessment and included in the project file with the completed PCRA.

Communication and coordination of all types of activity with affected areas are to be included among the control measures. The development of communication and coordination plans must begin during the activity planning phase.

Facilities may customize this template to incorporate site-specific information and requirements.

NOTE: This VHA PCRA template pertains specifically to non-infection-related safety for Construction, Renovation, and Maintenance activities. It must be used in conjunction with the VHA Infection Control Risk Assessment (ICRA) for the activity, if required, which specifically addresses infection risks outside the scope of this PCRA.

PERMIT: See the last page of this document for a fillable permit form to be used for posting at the activity site.

Activity Location:

Activity Name, Number, and/or Brief Description:

Table 1 - Construction, Renovation, and/or Maintenance Activity Type and Control Measures NOTE: If any of the bulleted criteria in a higher activity type pertains to the work that will be done (even if the other criteria are in a lower type), use the higher activity type for the VHA PCRA.

Controls defined in Table 1 for the activity must be in place before the activity begins and maintained until work is completed and the area is activated. Control measures for each activity must also include the control measures in the preceding row(s).

As the activity progresses, a full re-evaluation of remaining activity type and risk is required prior to changing the level of control measures.

Activity Type determined from Table 1:

Activity Type and Description Control Measures Inspection/upkeep generally defined as follows:

• Work can be completed in a single shift, not to exceed 10 hours.

• Patients, employees and/or visitors may be in the area depending on the activity.

• Work that does not create dust or debris.

• Work that does not create vapors or fumes.

• Removal of ceiling tile or access to mechanical or electrical chase for visual inspection that will not impair fire safety systems and are limited to 1 tile per 50 square feet with limited

1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.

2. Site visits of construction area are required weekly by member of multi-disciplinary team.

Site visits will be documented on standard checklist.

3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved where a contact is in place. For internal work the

VHA-PCRA-2024-1.1 (May 21, 2024) Page 2 of 5 exposure time (not to exceed an hour for each tile) within the shift.

• Minor interior updates (e.g., replacing floor or ceiling tiles, carpentry work to include hanging signage, and painting with hand tools) that do not create vibration or noise.

• Limited building system maintenance that does not require Lock Out Tag Out (LOTO) such as plumbing on potable systems limited to faucet replacement, steam trap replacement etc. and electrical work such as replacement of bulbs, receptacles, or switches.

shop involved must work with Safety to ensure proper precautions are in place.

4. Must address identified hazards and controls that will be implemented to ensure minimal impact to patients, employees, contractors and facility.

5. Communication and coordination plan for all affected areas

Small scale Construction, Renovation and general maintenance/repair work, generally defined as follows:

• Prolonged work that may take longer than a single shift but not exceeding six months.

• Patients and employees are not to be in the area until activity is completed.

• Work that creates some noise and vibration due to power tool use.

• Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural elements that may o disturb asbestos, lead or silica o create the potential for falling objects o create vibration and/or noise in excess of 80 dB(A) in surrounding areas.

o cause penetrations in fire or smoke barrier

• Plumbing work such as the installation of new sinks, showers and toilets and associated plumbing that requires utility outages or work on the steam system that may require:

o LOTO o The use of compressed gas cylinders

• Electrical work such as installation of conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. Electrical work such as installation of cabling/wiring/conduit for a single device, installation of new device such as a light fixture that require LOTO.

• Air Handler and/or fan shutdown/startup and HVAC work such as replacement of a single diffuser, single terminal unit, a single device and the installation of ductwork, diffusers, and terminal units for an area that may require:

o Work on ladders o Rigging, hoisting or lifting of equipment or materials overhead

• Modification of existing fire alarm and suppression systems requiring system outages and ILSMs or obstruction of exits and or impact on corridors.

• Architectural, structural, or any other work that may cause vapors or fumes such as:

o Roofing work o Flooring work o Painting or other large-scale use of such substances.

All control measures in the row above and the following:

1. Hazard communication chemical inventory required to be provided by the contractor and approved.

2. Where construction, Renovation and maintenance are done in an accredited facility, and ILSM assessment is required to be done and ILSMs put into place in accordance with TJC LS.01.02.01 and the local facility policy including Fire watch if necessary. Staff is trained and the ILSM is verified regularly

3. Hot Work or burn permits in place and staff trained

4. LOTO procedures in place and staff trained on their use

5. Site visits will be reviewed using the criteria in standardized guide.

6. Daily inspections of the site are to be conducted by the General Contractor or shop supervisor and documented on their daily log.

Large-scale construction, renovation, or maintenance generally defined as follows:

• Work exceeding 6 months in duration.

• Patients and employees are not to be in the area until activity is completed.

All control measures in the two rows above and the following Activity Hazard Analyses and Control Plans (check all that apply):

1. Excavation safety plan in place ☐

2. Dust control plan in place ☐

VHA-PCRA-2024-1.1 (May 21, 2024) Page 3 of 5

• Excavation or heavy equipment use taking place o Dig safe required utility location o Trench safety o Dust control plan o Equipment exhaust, Noise, Vibration

• Confined space entry required (permit required or not)

• Requires crane work o General crane work o Lift over buildings

• Includes elevated work o Roof work, fall protection o Window work, scaffolding and fall protection o Odor control

• Welding, cutting or use of torches requiring burn permits

• Demolition of building components and infrastructure including removal of multiple doors, walls, framing, ceilings, flooring, piping, electrical and HVAC that may o require asbestos, lead or silica abatement o create the potential for falling objects o create vibration and/or noise in excess of 90 dB(A) in surrounding areas.

o cause breaches to fire or smoke barrier

• The installation building components such as new walls, ceilings and doors including framing, drywall and associated plaster work that requires transport of significant materials through building and up elevators i.e., weight limits of floors and elevators

• Plumbing work requiring LOTO and system shutdown and startup such as the installation of:

o new medical gas systems, o steam/heating hot water, condensate systems, o Potable water and sanitary drainage, multiple sinks, showers and toilets including associated plumbing.

• Electrical work such as installation of electrical feeders, distribution panels, conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. requiring LOTO and system isolation.

• Installation of fire alarm and suppression systems requiring outages of those systems and ILSMs or closure of exits/corridors

• Mechanical work such as the installation of air handling equipment, associated ductwork, diffusers, heat exchangers, terminal units and controls requiring lifting and support of equipment and systems.

3. Pollution prevention plan in place ☐

4. Dig safe paper work in place ☐

5. Crane lift plan in place ☐

a. Crane placement

b. Crane swing

c. Crane load evaluation

6. Fall protection plan in place and staff trained ☐

7. Confined entry plan in place and staff trained ☐

Table 2. Affected Adjacent Area Assessment In addition to the minimum precautions noted above for the Activity Type, it is critical that the activity be coordinated with the areas adjacent to the activity to ensure operations in those areas are not disrupted or impacted. List the adjacent areas in Table 2 below and develop activity-specific coordination plans and associated communication plans with each area to address activity work that could impact or disrupt the operation of the areas, in general as follows:

• If adjacent area is vacant (e.g., work outside, construction of new building, etc.):

o Coordination is typically not necessary other than potentially traffic flow and pedestrian access.

VHA-PCRA-2024-1.1 (May 21, 2024) Page 4 of 5

• If adjacent area is non-continuously occupied (e.g., areas where outpatient care is provided, employee health, etc.):

o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., conduct work after hours).

• If adjacent area is occupied continuously (e.g., areas where inpatient care is provided, residential areas such as Community Living Centers, etc.):

o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., move affected party temporarily).

Area Service(s)/Type(s) of Area(s)

(e.g., OR, Unit/Ward, Sterile Processing, Administrative, etc)*

Point of Contact

(POC)

POC Contact Information

Construction plan communicated to POC?

Activity Area**

Area Above

Area Below

Adjacent Area 1

Adjacent Area 2

Adjacent Area 3

Adjacent Area 4

* There may be more than one Service/type of area for each row. List all. The information entered on this table must be used in the ICRA if required.

** List the area(s) in which the construction/renovation/maintenance activity will occur.

Infection Control Risk Assessment (ICRA)

Consult with Infection Prevention and Control regarding the assessment of potential patient infection risks associated with the activity and the need for control measures. For example, activities such as a boiler plant project and/or facility steam shutdown, if properly planned, should have minimal to no patient infection risk impacts and likely not to require an ICRA. See VHA Directive 7715 and the VHA ICRA Template for more information.

Is an ICRA required for the Activity? Yes ☐ No ☐ vhabhsnelsoc3 Highlight

Pre-Construction Risk Assessment (PCRA) Permit This page must be posted at the entrance to the project area, or other designated area

Unique permit number:

Location and brief description of construction/renovation/maintenance Project manager Project start date Contact phone number Completion date Contractor or lead shop Permit expiration date

Activity Type Inspection/Upkeep, Small-scale, or Large-scale)

Activity Type Control measures to be in place for the duration of the activity (Check the box for the Activity Type to indicate the Control Measures)

Inspection/Upkeep

1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.

2. Site visits of construction area are required weekly by member of multi-disciplinary team. Site visits will be documented on standard checklist.

3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved.

4. Must address identified hazards and controls that will be implemented to ensure minimal impact patients, employees, contractors and facility.

5. Communication and coordination plan for all affected areas

Small-scale

All control measures in the row above and the following:

1. Hazard communication chemical inventory required to be provided by the contractor and approved.

2. ILSMs in place and staff trained on situation

3. Hot Work or burn permits in place and staff trained

4. LOTO procedures in place and staff trained on their use

5. Site visits will be reviewed using the criteria in standardized guide.

6. Daily inspections of the site are to be conducted by the General Contractor and documented on their daily log.

Large-scale

All control measures in both rows above and the following Activity Hazard Analyses and Control Plans as applicable (check all that apply):

1. Excavation safety plan in place ☐

2. Dust control plan in place ☐

3. Pollution prevention plan in place ☐

4. Dig safe paperwork in place ☐

5. Crane lift plan in place ☐

a. Crane placement

b. Crane swing

c. Crane load evaluation

6. Fall protection plan in place and staff trained ☐

7. Confined entry plan in place and staff trained ☐

*The location of all Activity Hazard Analyses and Control Plans (excavation, dust, pollution, etc.) as applicable shall be identified on this permit and shall be made available to all workers on the job.

VHA-PCRA-2024-1.1 (May 21, 2024)

Additional requirements:

Is an Infection Control Risk Assessment (ICRA) required for the Activity? Yes ☐ No ☐ Infection Prevention and Control signature:

Date:

Project Manager signature Date

Safety Officer signature Date

Chair, Construction Safety Committee signature

Date

PERMIT See the last page of this document for a fillable permit form to be used for posting at the activity site: Jamaica Plain - Outside by Building 4
andor Brief Description: 523-25-003 Bulk Oxygen Correction: Construction work upgrades Bulk Oxygen Storage areas to comply with NFPA.
As the activity progresses a full reevaluation of remaining activity type and risk is required prior to changing: Large-scale
Excavation safety plan in place: Off
Dust control plan in place: Off
Dig safe paper work in place: Off
Crane lift plan in place: Off
Fall protection plan in place and staff trained: Off
undefined: Off
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcActivity Area: Bulk O2 Storage Area
Point of Contact POCActivity Area: William Shattuck
POC Contact InformationActivity Area: (857) 203-6432
Construction plan communicated to POCActivity Area: Yes
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcArea Above: N/A
Point of Contact POCArea Above: N/A
POC Contact InformationArea Above: N/A
Construction plan communicated to POCArea Above: N/A
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcArea Below: N/A
Point of Contact POCArea Below: N/A
POC Contact InformationArea Below: N/A
Construction plan communicated to POCArea Below: N/A
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 1: Bldg. 4 - SARRPT
Point of Contact POCAdjacent Area 1: Monica Roy
POC Contact InformationAdjacent Area 1: (857) 364-5969
Construction plan communicated to POCAdjacent Area 1: Yes
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 2: Bldg. 5 - Boiler Plant
Point of Contact POCAdjacent Area 2: Dan Beaty
POC Contact InformationAdjacent Area 2: (857) 203-6633
Construction plan communicated to POCAdjacent Area 2: Yes
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 3: Transportation
Point of Contact POCAdjacent Area 3: Miguel Preciado
POC Contact InformationAdjacent Area 3: (857) 364-5425
Construction plan communicated to POCAdjacent Area 3: Yes
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 4: Prosthetics
Point of Contact POCAdjacent Area 4: David Gray
POC Contact InformationAdjacent Area 4: (617) 435-9450
Construction plan communicated to POCAdjacent Area 4: Yes
Is an ICRA required for the Activity: Yes
Activity Type InspectionUpkeep Smallscale or Largescale: Large-scale
1 Excavation safety plan in place: Off
2 Dust control plan in place: Off
3 Pollution prevention plan in place: Off
4 Dig safe paperwork in place: Off
5 Crane lift plan in place: Off
6 Fall protection plan in place and staff trained: Off
7 Confined entry plan in place and staff trained: Off
Additional requirements: Coordination of work should have minimal impact on Medical Center operation or note off hours work.
Is an Infection Control Risk Assessment ICRA required for the Activity: Yes_2
Pollution prevention plan in place: Off
Unique permit number: 523-25-003
Project manager: Naweed Azad
Contact phone number: 617 - 359 - 8589
Project Start Date_af_date:
Completion Date_af_date:
Permit Expiration Date_af_date:
Contractor or lead shop: TBD
Location and brief description of Construction/Renovation/Maintenance: Bulk Oxygen Correction: Jamaica Plain

Construction work upgrades Bulk Oxygen Storage area to comply with NFPA.

Check Box6: Yes
Check Box7: Yes
Check Box8: Yes
Date10_af_date: 06/25/2025
2025-06-24T15:51:46-0400
NAWEED AZAD
2025-06-25T13:49:41-0400
CARLA NELSON
Project Manager Date Signed_af_date: 06/24/2025
Safety Officer Date Signed_af_date: 06/25/2025
CCS Date Signed_af_date:
2025-06-25T08:12:45-0400
JENNIFER MCMILLAN