Project Summary: Improve Sub-Basement Plumbing and Air Quality

This is a Statement of Work for a construction project (Project Number 541-24-103, dated 01-07-26) at a medical center's sub-basement facility. The primary scope involves replacing lift pumps, sump pumps, collection pits, and addressing plumbing deficiencies, while also resolving air quality issues caused by building expansion that has restricted fresh air flow to the sub-basement. The contractor must field-verify all existing conditions and develop a comprehensive phasing plan to minimize disruption to ongoing medical center operations.

The project schedule requires completion within 251 calendar days from the notice to proceed. The contractor must produce detailed phasing plans for all disciplines showing work to be completed per phase on separate drawings, required temporary partitions, temporary and final MEP (mechanical, electrical, plumbing) connections needed for fully functioning spaces at phase completion, and life safety travel distances at each phase endpoint. Each phase must include scope description and timing sequence. The sub-basement is classified as a non-permit-required confined space, allowing general site investigation and inspection without additional safety measures such as air monitoring or alternative entry procedures.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project: Improve Sub-Basement Plumbing and Air Quality Project Number: 541-24-103

Improve Sub-Basement Plumbing and Air Quality 541-24-103

01-07-26

TABLE OF CONTENTS

SECTION TITLE

1.0 SCOPE OF WORK

1.0 SCOPE OF WORK

1. This project replaces lift pumps, sump pumps, pits and other plumbing deficiencies in the sub-basement of the main medical center. Project also addresses air quality issues resulting from building expansion that has limited fresh air flow through the sub-basement. Ongoing projects have impeded egress, lighting and ventilation of the area.

2. Develop project phases as necessary to minimize disruption to the continued operation of the Medical Center. Phasing plans for all disciplines are to be produced to show all of the work that is being completed in a specific phase on separate plan drawings; temporary partitions that will be needed for the phase; temporary and final MEP connections that will need to be made for a fully functioning space at the end of a phase; and life safety travel distances at the end of each phase. The phasing plan shall include the scope and timing sequence of each identifiable phase or major activity. Each phase shall be described in terms of the work involved.

3. Project Schedule is 251 Calendar days from date of notice to proceed to complete Construction

4. As a part of this contract, contractor shall field verify all existing conditions. The sub-basement is a non-permit required confined space. General site investigation and inspection is allowed without additional measures such as air monitoring, alternative entry procedures, etc.