S02. 01 00 00 - General Requirements.pdf
PDF 528 KB Posted
- Solicitation number
- 36C25026B0014_1Solicitation
About this file
This document is a General Requirements specification (Section 01 00 00) for the Columbus VAMC Parking Garage Tendon Repair Design project, VA Project 757-24-204, located in Columbus, OH. The project involves repairing damaged beam tendons and re-stressing them post-construction, with work to be performed at the Columbus VA Medical Center. Key requirements include strict security protocols, with contractors required to obtain badges, comply with VA security management programs, and adhere to specific site access and documentation control procedures.
The specification outlines comprehensive guidelines for construction operations, including protecting existing structures and utilities, maintaining medical center functionality, and managing temporary facilities. Contractors must coordinate closely with the Contracting Officer's Representative (COR), provide detailed photographic documentation using professional-grade digital cameras, and maintain extensive online documentation with interactive navigation. The project emphasizes minimizing disruption to medical center operations, with specific requirements for utility services, temporary toilets, and site access. Warranty management is also a critical component, with contractors required to develop a detailed warranty plan and respond to potential issues within specified timeframes.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 00 00 -1
Columbus VAMC Specification VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the Columbus VAMC – Parking Garage Tendon Repair project as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the Medical Center Engineering Officer.
C. Offices of West Point Engineers, LLC., as
Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by the Contracting Officer or his duly authorized representative.
D. All employees of the general contractors and subcontractors shall comply with the VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
01 00 00 -2
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Work includes the repair of the damaged beam tendons, and the restressing of these tendons post-construction.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
01 00 00 -3
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The
General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Guards: Not applicable. Project site access will not require guard presence.
D. Key Control: Not applicable; contractor will not require access to keyed facilities at this time. Should conditions change upon contract award the contractor will coordinate with the COR accordingly.
E. Document Control:
1. Before starting any work, the General
Contractor/Subcontractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information.”
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or
“Sensitive Unclassified.” Secure such information in separate containers and limit access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
01 00 00 -4
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
4. These security documents shall not be removed or transmitted from the project site without the written approval of the Contracting Officer.
5. All paper waste or electronic media such as CDs shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of
“sensitive information.”
7. All electronic information shall be stored as appropriate in a specific location following VA standards and procedures using an Engineering Document Management
Software (EDMS).
Security, access, and maintenance of all project drawings, both scanned and electronic, shall be performed and tracked through the EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access.
Access shall be restricted to picking up and dropping off materials and supplies, and those contractor vehicles actively involved in the landscaping work.
2. A limited number of permits shall be issued for General
Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical
Center Facility Manager.
01 00 00 -5
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The
Contractor shall hold and save the Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices):
not applicable at this time.
C. The Contractor shall, under regulations prescribed by the
Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to the rules of the Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, 01 00 00 -6
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025 including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction areas within the areas in use by Department of Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to
Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of
Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent services to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the
Contractor.
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure
01 00 00 -7
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025 that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
The work to be outlined shall include, but not be limited to:
a. site preparation and mobilization,
b. removal of damaged tendons,
c. repair/replacement of tendons, and
d. re-stressing after construction completion.
2. To ensure such executions, Contractor shall furnish the
COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to
COR and Contractor.
Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Center’s operations will not be hindered.
Contractor shall permit access to Department of Veterans
Affairs personnel and patients through other construction
01 00 00 -8
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025 areas which serve as routes of access to such affected areas and equipment.
J. Construction Fence: Not applicable.
K. When a construction site is turned over to Contractor, Contractor shall accept entire responsibility to include upkeep and maintenance.
L. Utilities Services: Maintain existing utility services for
Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to ensure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems
(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR . Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center
Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK
01 00 00 -9
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of the proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Columbus VA Medical Center. Interruption time approved by Medical Center may occur at other than
Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent services to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the
Contractor.
M. Abandoned Lines: Not applicable – any uncovered abandoned lines will be reported to the COR for further action.
N. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction
01 00 00 -10
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025 materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
O. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS – NOT APPLICABLE
1.8 DISPOSAL AND RETENTION
A. In general, this project does not include major disposal and/or retention activities. However, if any of the items listed below are encountered, the contractor will inform the COR immediately for a recommendation as to the appropriate actions.
B. Materials and equipment accrued from removed work and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the
Government are identified by attached tags or noted on drawings or in specifications as items to be stored.
Items that remain the property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to reinstallation and reuse. Store such items where directed by COR.
01 00 00 -11
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
2. Items not reserved shall become property of the
Contractor and be removed by Contractor from Medical
Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.
When rooms and spaces are vacated by the Department of
Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the
Government in advance of work to avoid interfering with
Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed, and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place.
If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting
Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which
01 00 00 -12
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025 are made known to or should be known by the Contractor. The
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver complete and undamaged work. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by
01 00 00 -13
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 PHYSICAL DATA – SOIL CONDITIONS – NOT APPLICABLE; NO MAJOR
SOIL WORK REQUIRED
1.12 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the
Contractor shall perform services specified herein and in other specification sections if required. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and benchmarks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades
01 00 00 -14
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025 that may be established or indicated by the Contracting
Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full-size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications, and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21
(Warranty of Construction) at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to ensure that the Government receives all warranties to which
01 00 00 -15
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025 it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting
Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn it over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4-month and 9-month warranty inspection will be conducted, measured from time of acceptance, by the
Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the
Contractor, subcontractors, manufacturers, or suppliers involved.
2. Furnish with each warranty the name, address, and telephone number of each of the guarantor’s representatives nearest project location as applicable.
3. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
01 00 00 -16
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and
Maintenance manuals.
k. Organizations, names, and phone numbers of personnel to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
4. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
5. Procedure and status of tagging of all equipment covered by extended warranties.
6. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance & Payment Bonds: The Performance & Payment
Bonds must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work
01 00 00 -17
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025 required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the
Government at the contractor’s expenses, the Contracting
Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the
Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the
Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which
01 00 00 -18
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025 is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the
Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service
Requirements:
E. Following oral or written notification by the Contracting
Officer, the Contractor shall respond to construction warranty service requirements in accordance with the
“Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the period specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within
4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within
8 hours, initiate work within 24 hours and work continuously to completion or relief.
01 00 00 -19
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
3. Third Priority Code 3. All other work to be initiated within 3 workdays and work continuously to completion or relief.
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on
Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.17 RESIDENT ENGINEER'S FIELD OFFICE – NOT APPLICABLE
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT – NOT
APPLICABLE
1.19 TEMPORARY USE OF EXISTING ELEVATORS - NOT APPLICABLE
1.20 TEMPORARY USE OF NEW ELEVATORS – NOT APPLICABLE
1.21 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
01 00 00 -20
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
1. Contractors may have for use of Contractor's workers such toilet accommodations as may be assigned to Contractor by
Medical Center. Contractor shall keep such places clean and be responsible for any damage done thereto by
Contractor's workers. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government.
The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in an efficient manner, in compliance with code and as satisfactory to the
Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the Medical Center a monthly record of the
Contractor's usage of electricity as hereinafter specified.
D. Heat: Not applicable
01 00 00 -21
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide a reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the Contractor.
2. Maintain connections, pipes, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at
COR discretion) of use of water from Medical Center's system.
G. Fuel: Not applicable.
1.23 TESTS NOT APPLICABLE
1.24 INSTRUCTIONS – NOT APPLICABLE
1.25 GOVERNMENT-FURNISHED PROPERTY – NOT APPLICABLE
1.26 RELOCATED ITEMS NOT APPLICABLE
01 00 00 -22
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT -
NOT APPLICABLE
1.28 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the COR. All wood members shall be of framing lumber. Cover sign frame with 0.7mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Provide three 100mm by
100mm (4-inch by 4-inch) posts (or equivalent round posts) set 1200mm (4 ft) into ground. Set bottom of sign level at
900mm (three feet) above ground and secure to posts with through bolts. Make posts full height of sign. Brace posts with 50mm x 100mm (2” by 4”) material as directed.
B. Paint all surfaces of sign and post with two coats of white gloss paint. Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the COR.
D. Detail Drawing of construction sign showing required legend and other characteristics of sign is to be determined by the COR.
1.29 SAFETY SIGN – NOT APPLICABLE
1.30 PHOTOGRAPHIC DOCUMENTATION
A. During the construction period through completion, provide photographic documentation of construction progress and selected milestones including electronic indexing, navigation, storage, and remote access to the documentation, as per these specifications.
B. Photographic documentation elements:
01 00 00 -23
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
1. Each digital image shall be taken with a professional grade camera with minimum size of 6 megapixels (MP) capable of producing 200x250mm (8 x 10 inch) prints with a minimum of 2272 x 1704 pixels and 400x500mm (16 x 20 inch) prints with a minimum 2592 x 1944 pixels.
2. Indexing and navigation systems utilize actual AUTOCAD construction drawings, making such drawings interactive on an on-line interface. For all documentation referenced herein, indexing and navigation must be organized by both time (date-stamped) and location throughout the project.
3. Documentation shall combine indexing and navigation systems with inspection-grade digital photography designed to capture actual conditions throughout construction and at critical milestones. Documentation shall be accessible online through the use of an internet connection. Documentation shall allow for secure multiple-user access, simultaneously, online.
4. Before construction, the building pad, adjacent streets, roadways, parkways, driveways, curbs, sidewalks, landscaping, adjacent utilities, and adjacent structures surrounding the building pad and site shall be documented. Overlapping photographic techniques should be used to ensure maximum coverage. Indexing and navigation accomplished through interactive architectural drawings.
If site work or pad preparation is extensive, this documentation may be required immediately before construction and at several pre-determined intervals before building work commences.
5. As-built condition of pre-foundation utilities and site utilities shall be documented prior to pouring footers, placing concrete and/or backfilling. This process shall
01 00 00 -24
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025 include all underground and in-slab utilities within the building(s) envelope(s) and utility runs in the immediate vicinity of the building(s) envelope(s). This may also include utilities enclosed in slab-on-deck in multi-story buildings. Overlapping photographic techniques should be used to ensure maximum coverage. Indexing and navigation accomplished through interactive site utility plans.
6. Miscellaneous events that occur during any Contractor site visit, or events captured by the Department of
Veterans Affairs independently, shall be dated, labeled, and inserted into a Section in the navigation structure entitled “Slideshows,” allowing this information to be stored in the same “place” as the formal scope.
7. Customizable project-specific digital photographic documentation of other details or milestones. Indexing and navigation accomplished through interactive architectural plans.
8. Weekly (21 Max) Site Progressions - Photographic documentation capturing the project at different stages of construction. These progressions shall capture underground utilities, excavation, grading, backfill, landscaping and road construction throughout the duration of the project.
9. In the event a greater or lesser number of images than specified above are required by the COR, adjustment in contract price will be made in accordance with clause entitled "CHANGES" (FAR 52.243-4).
C. Images shall be taken by a commercial photographer and must show distinctly, at as large a scale as possible, all parts of work embraced in the picture.
01 00 00 -25
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025
D. Coordination of photo shoots is accomplished through COR.
Contractor shall also attend construction team meetings, as necessary. Contractor’s operations team shall provide regular updates regarding the status of the documentation, including photo shoots concluded, the availability of new
Progressions or Exact-Builts viewable on-line and anticipated future shoot dates.
E. Contractor shall provide all on-line domain/web hosting, security measures, and redundant server back-up of the documentation.
F. Contractor shall provide technical support related to using the system or service.
G. Upon completion of the project, final copies of the documentation (the “Permanent Record”) with the indexing and navigation system embedded (and active) shall be provided in an electronic media format, typically a DVD or external hard drive. Permanent Record shall have Building
Information Modeling (BIM) interface capabilities. On-line access terminates upon delivery of the Permanent Record.
1.31 FINAL ELEVATION DIGITAL IMAGES
A. A minimum of four (4) images of each elevation shall be taken with a minimum 6 MP camera, by a professional photographer with different settings to allow the COR to select the image to be printed. All images are provided to the COR on a CD.
B. Photographs shall be taken upon completion, including landscaping. They shall be taken on a clear sunny day to obtain sufficient detail to show depth and to provide clear, sharp pictures. Pictures shall be 400mm x 500mm (16” by 20”), printed on regular weight paper, matte finish archival grade photographic paper and produced by a RA4
01 00 00 -26
VA Project 757-24-204 100% Bid Documents Submission Columbus OH Parking Garage Tendon Repair Design 18 Jul 2025 process from the digital image with a minimum 300 PPI.
Identifying data shall be placed on label affixed to back of photograph without damage to photograph and shall be similar to that provided for final construction photographs.
1.32 HISTORIC PRESERVATION
A. Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical, and/or cultural resources, the Contractor shall immediately notify the COR verbally, and then with a written follow up.
1.33 VA TRIRIGA CPMS – NOT APPLICABLE
- - - E N D - - -