This is a Pre-Bid Request for Information (RFI) form for the Alabama National Cemetery GSE Phase 3 project administered by the National Cemetery Administration's Southeast District (Project Number 927CM3003).
The form serves as a template for contractors to submit clarification questions and requests for information regarding project specifications, drawings, and requirements prior to bidding. It includes fields for contractors to identify the date of submission, RFI number, reference subject, specification section number and title, drawing number, plan/detail/schedule reference, and a detailed explanation of the request. The form requires submission of the contractor's company name and contact person's name. The National Cemetery Administration responds to each inquiry by completing the NCA Response section, which includes the date received, responding party, response date, and authorized signature. This standardized form facilitates organized communication between the government agency and potential bidders during the pre-bid phase, ensuring all clarifications are documented and tracked systematically.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
927CM3003
Project: Alabama National Cemetery GSE Phase 3
National Cemetery Administration – Southeast District
PRE-BID REQUEST FOR INFORMATION
Date Submitted: ______________ RFI _________
Reference/Subject: ____________________________
Spec. Section No. / Title ________________________ Page / Art. / Para. ____________________
Drawing No.: _________________________________ Plan/Detail/Schedule: _________________
Request (Explain your request in detail here):
Submitted by (Company Name): _________________________(Person Name): ______________________________
NCA Response:
Date Received by NCA: __________________
Response by: ___________________________________ Date: __________________________________________
NCA Signature
| RFI: |
| ReferenceSubject: |
| Page Art Para: |
| Spec Section No Title 1: |
| Drawing No: |
| PlanDetailSchedule: |
| Submitted by Company Name 1: |
| Person Name: |
| Response by: |
| Text2: |
| Date3_af_date: |
| Date4_af_date: |
| Date5_af_date: |
| Text1: |
File details come from the government source that posted it. Updated .