This is a Capitalization Authorization and Expense Form template used by the Department of Veterans Affairs National Cemetery Administration (NCA) to process and document the capitalization of construction projects at cemetery facilities.

The form requires project managers to classify assets generated from construction projects into three categories: new assets, betterments to existing assets, and asset removals. For each asset, project managers must complete designated yellow-highlighted fields including the cemetery station, asset description, Budget Object Code (BOC), total cost, building number (if applicable), gross square feet for buildings, budget fiscal year, and completion date. The form provides specific BOC codes for different asset types, ranging from land and land rights (3210-3213) to buildings and improvements (3220-3223) and other structures and facilities (3240-3241), with distinctions between capitalized and non-capitalized items. The form includes separate sections for new assets, betterments, asset removals, and hazardous waste or historical asset repair costs. NCA Finance personnel complete additional columns including assigned fixed asset (FA) numbers and names, accounting codes, fund information, and estimated asset life. Project managers must submit completed capitalization authorizations to NCAConstructionFinance@va.gov and NCA42B1@va.gov. The form also includes a detail section reconciling work-in-progress (WIP) amounts and project summary information sourced from financial reports (F876, FA01, F700) and the FA07 Fixed Assets report.

View the file

Other files

File Type Posted
S02_Attachment - Solicitation Sections B_L_M (amended).pdf PDF
S05_Attachment - RFIs and Answers.xlsx XLSX spreadsheet
S02_Attachment - Construction Specifications (amended).pdf PDF
S06_36C78626R0008 Amend 0003.pdf PDF
S02_Attachment - Construction Drawings (amended).pdf PDF
S06_36C78626R0008 Amend. 0002.pdf PDF
S02_Attachment - Site Visit Attendance Roster.pdf PDF
S06_36C78626R0008 Amend. 0001.pdf PDF
S02_Construction Drawings bk 1.pdf PDF
S02_Wage Determination Building Construction.pdf PDF
S02_Construction Drawings bk 12.pdf PDF
S02_Wage Determination Heavy Construction.pdf PDF
S02_Price Proposal Breakdown.docx DOCX document
S02_Construction Drawings bk 7.pdf PDF
S02_Attachment - Limitations on Subcontracting Cert.docx DOCX document
S02_Construction Specifications.pdf PDF
S02_Construction Drawings bk 6.pdf PDF
S02_Construction Drawings bk 3.pdf PDF
S02_Construction Drawings bk 13.pdf PDF
S02_Construction Drawings bk 2.pdf PDF
S02_Attachment - Davis-Bacon Act Poster.pdf PDF
S02_Construction Drawings bk 5.pdf PDF
S02_Attachment - Standard Form 1413.pdf PDF
S02_Construction Drawings bk 4.pdf PDF
S02_Construction Drawings bk 11.pdf PDF
S02_Construction Drawings bk 9.pdf PDF
S02_Construction Drawings bk 8.pdf PDF
S02_Attachment - Past Performance Questionnaire.docx DOCX document
S02_Attachment - RFI Form.pdf PDF
S02_36C78626R0008.pdf PDF
S02_Attachment - DOL Certified Payroll Form.pdf PDF
S02_Attachment - Project Sample Template.docx DOCX document
S02_Construction Drawings bk 10.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions The attached spreadsheet is used for capitalization of construction projects. The program manager only completes the columns highlighted in yellow.

First step is to classify generated asset in the three categories it should belong to (new assets, betterments, asset removal), majority of the asset generated are categorized as new assets. One you've determine the classification of asset. Complete the spreadsheet highlighted in YELLOW.
STATION: enter cemetery station
DESCRIPTION of ASSET: Itemize all assets that were generated from the project such as committal shelter, site excavation, columbarium etc.
BOC (Budget Object Codes for Real Property): enter the BOC that applies to the asset:
3210 Land (capitalized before 10/1/25)Land (expensed after 10/1/25)3211 Land Acquisition & Permanent Land Rights3212 Temporary Land Rights CAP3213 Temporary Land Rights NON-CAP
3215 Improvements to LandUnder $1M---->3216 Non-Capitalized Improvements to Land
3220 Buildings and ImprovementsUnder $1M---->3223 Non-Capitalized Buildings and Improvements
3240 Other Structures & FacilitiesUnder $1M---->3241 Non-Capitalized Other Structures & Facilities
3270 Historical Assets (not capitalized per policy)
TOTAL COST: enter total cost per asset (refer to detail tab in worksheet for obligations regarding project)
BLDG NUMBER: enter the building number for all new buildings and structures.
GSF (for Buildings) enter the the Gross Square Feet for all new buildings.
BFY (Budget Fiscal Year): enter budget fiscal year (refer to detail tab)
DATE COMPLETE: Enter date when construction project was completed

AN EXAMPLE:

NEW ASSETSTo be completed by Project Manager
StationDESCRIPTION OF ASSETBOCTOTAL COSTBLDG NUMBERG S F
(for Buildings)DATE COMPLETE
839Committal Shelter3240$100,000.008/19/04
839Site excavation3215$108,638.008/19/04
839Grading3215$125,000.008/19/04
839Furnishing & installing water & electrical service & sanitary sewer3215$618,061.428/19/04
839Relocation of over-head electric line3240$150,000.008/19/04
839New burial monuments3240$250,000.008/19/04
839Restroom3220$200,000.008/19/04
839Maint Building3220$931,923.008/19/04

Total New Assets $2,483,622.42

If the project is for a betterment or removal, verify that the asset was already capitalized by checking the FA04 report (Fixed Assets report) and then enter the FA (Fixed asset) name and number in the spreadsheet
Please include the Building Number for all buildings and structures and the new Gross Square Feet for a building betterment. Include the Building Number for all buildings and structures and the old Gross Square Feet for a Building Removal.

Please send all capitalization authroizations to NCAConstructionFinance@va.gov & NCA42B1@va.gov

FINANCIAL POLICY
https://department.va.gov/financial-policy-documents/financial-document/chapter-07-general-property-plant-and-equipment/

https://department.va.gov/financial-policy-documents/financial-document/chapter-07-general-property-plant-and-equipment/ CAP - from PM

Capitalization Authorization:Project Manager:
Cemetery:Date sent to PM:
Project Name:Date recevied the CAP from PM :
Project Number:Custody Receipt (CR) Date :
1st, 2nd or final capitalization:Date recevied the CR from PM :
Developed Acres: èDate capitalized the project :
Gravesite Count:PPC: êCasket: êIGC: êNiches:êCapitlization status:ON TIME
NEW ASSETSTo be completed by Project ManagerTo be completed by NCA Finance
StationDESCRIPTION OF ASSET

cemvicenrp: List all assets generated from the project such as: Columbarium, Maintenance Building, Roadway System, site furnishings, Grading Drainage & Planting, Utility System, Irrigation System, Memorial Walkway etc.

BUILDING

NUMBER

(for buildings and structures)G S F
(for Buildings)BOC

cemvicenrp: BOC (Budget Object Class) 3210 Land & Land Rights 3215 Improvements to Land 3220 Buildings & Improvements 3240 Other Structures & Facilities TOTAL COST TO CAP/EXP TOTAL CONTRACT AMOUNT FOR ASSET + HOLDBACK Completion Date cemvicenrp: Enter Completion Date

Assigned FA NUMBERAssigned FA NAMEAOBFYFUNDFunding ProjectASSET CODEFA GroupFA LOCCOST CTRESTIMATED LIFE
40See Below
Total New Assets$0.00$0.00
BETTERMENTS to EXISTING ASSETS:To be completed by Project ManagerTo be completed by NCA Finance
StationDESCRIPTION OF ASSETBUILDING

NUMBER

(for buildings and structures)G S F
(for Buildings)BOC

cemvicenrp: BOC (Budget Object Class) 3210 Land & Land Rights 3215 Improvements to Land 3220 Buildings & Improvements 3240 Other Structures & Facilities TOTAL COST TO CAP/EXP TOTAL CONTRACT AMOUNT FOR ASSET + HOLDBACK Completion Date cemvicenrp: Enter Completion Date

FA NUMBER of Existing Asset from FA07 ReportFA NAME from FA07 ReportAOBFYFUNDFunding ProjectASSET CODEFA GroupFA LOCCOST CTRESTIMATED LIFE
40
Total Cost of Betterments$0.00$0.00
ASSETS TO BE REMOVED: (Assets that were demolished or rebuilt to the point where they no longer are the same asset - i.e. a former storage buiding that is now a computer lab)
To be completed by Project ManagerTo be completed by NCA Finance
StationDESCRIPTION OF ASSETBUILDING

NUMBER

(for buildings and structures)G S F
(for Buildings)BOC

cemvicenrp: BOC (Budget Object Class) 3210 Land & Land Rights 3215 Improvements to Land 3220 Buildings & Improvements 3240 Other Structures & Facilities TOTAL COST TO CAP/EXP TOTAL CONTRACT AMOUNT FOR ASSET Completion Date cemvicenrp: Enter Completion Date cemvicenrp: BOC (Budget Object Class) 3210 Land & Land Rights 3215 Improvements to Land 3220 Buildings & Improvements 3240 Other Structures & Facilities

FA NUMBER of Existing Asset from FA07 ReportFA NAME from FA07 ReportAOBFYFUNDFunding ProjectASSET CODEFA GroupFA LOCCOST CTRESTIMATED LIFE
40
$0.00$0.00
HAZARDOUS WASTE and HISTORICAL ASSET REPAIR: Clean up cost for Hazardous Waste AND any costs associated with work on Historical Assets
To be completed by Project ManagerTo be completed by NCA Finance
StationDESCRIPTION OF ASSETBOC

cemvicenrp: BOC (Budget Object Class) 3210 Land & Land Rights 3215 Improvements to Land 3220 Buildings & Improvements 3240 Other Structures & Facilities cemvicenrp: List all assets generated from the project such as: Columbarium, Maintenance Building, Roadway System, site furnishings, Grading Drainage & Planting, Utility System, Irrigation System, Memorial Walkway etc.

cemvicenrp: Enter Completion Date cemvicenrp: BOC (Budget Object Class) 3210 Land & Land Rights 3215 Improvements to Land 3220 Buildings & Improvements 3240 Other Structures & Facilities TOTAL COST DATE Expensed BFY FUND Funding Project ASSET CODE FA Group FA LOC COST CTR ESTIMATED LIFE

$0.00
Notes And Reconciliation with WIP to be completed by NCA Finance
WIPProjectBFYFUNDAmount

WIP Total $0.00

DETAIL - from Finance

FundBFYSPOLineStaBOCACCOBLIGATEDPAIDOUTSTANDINGHOLDBACKTCodeJobdescrip
$0.00$0.00
$0.00$0.00
$0.00$0.00
$0.00$0.00
$0.00$0.00$0.00
PROJECT SUMMARY
POVENDOROBLIGATEDPAIDOUTSTANDINGHOLDBACKPOP
$0.000
$0.000
$0.000
TOTAL$0.00$0.00$0.00

WIP - from Finance Run F876 Report

FA01 - from Finance

INTEREST - from Finance Run F700 Report

JV - from Finance S:Drive > Construction > FMS to iFAMS Asset Transactions > JV Tab

FMS

File details come from the government source that posted it. Updated .