S02 - ATTACHMENT L - FREDERICKSBURG VA Construction Schedule.pdf
PDF 204 KB Posted
- Attached to
- Q702--Fredericksburg Health Care Clinic IOT&A
- Solicitation number
- 36C77622Q0212
About this file
This document contains a construction schedule and related federal solicitation for interior buildout work at a new Department of Veterans Affairs health care clinic in Fredericksburg, Virginia. The schedule outlines over 150 construction activities from pricing proposal development through punchlist completion, spanning from November 2021 through July 2024. Major milestones include awarding tenant interior work in March 2022, installing wall framing and mechanical, electrical and plumbing rough-ins through mid-2024, and obtaining substantial completion and certificate of occupancy in April 2024. The related solicitation is for information technology and audiovisual design, installation, testing and acceptance services at the new clinic, issued under solicitation number 36C77622Q0212 by the VA Office of Information and Technology. The response due date is not specified.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name OD RD % Complete Start Finish TF
DESIGN.450 TI PRICING PROPOSAL DEVELOPMENT 20 10 50% 22-Nov-21 A 14-Jan-22 -177
DESIGN.490 TI PRICING PROPOSAL REVIEW/NEGOTIATION/APPROVAL 50 50 0% 07-Jan-22 21-Mar-22 -177
DESIGN.510 *TI CONSTRUCTION NTP (PERMIT RECEIVED) 0 0 0% 21-Mar-22 -177
PR.800 AWARD TENANT INTERIOR 60 60 0% 22-Mar-22 14-Jun-22 -177
PR.810 S/F/A INTERIOR FINISHES 30 30 0% 27-May-22 11-Jul-22 -177
PR.820 R/A INTERIOR FINISHES 20 20 0% 12-Jul-22 08-Aug-22 -177
RF.L2.120 INSTALL HMF (C.L. 13.4 TO 15) - MED SPACE - L2 6 6 0% 31-Aug-22 08-Sep-22 -177
RF.L2.190 INSTALL HMF (C.L. 15 TO 17) - MED SPACE - L2 6 6 0% 09-Sep-22 16-Sep-22 -177
RF.L2.280 INSTALL HMF (C.L. 17 TO 20) - MED SPACE - L2 6 6 0% 19-Sep-22 26-Sep-22 -177
RF.L2.390 WALL FRAMING (C.L. 17 TO 20) - MED SPACE - L2 10 10 0% 27-Sep-22 11-Oct-22 -177
RF.L2.1240 WALL FRAMING (C.L. 10 TO 13.4) - AUDIOLOGY - L2 10 10 0% 12-Oct-22 25-Oct-22 -177
PR.830 FAB/DEL INTERIOR FINISHES 60 60 0% 09-Aug-22 02-Nov-22 -177
RF.L2.1450 WALL FRAMING (C.L. 10 TO 13.4) - CARDIOLOGY - L2 10 10 0% 26-Oct-22 08-Nov-22 -177
RF.L2.1790 WALL FRAMING (C.L. 6 TO 8) - PHYS. MED / REHAB - L2 10 10 0% 09-Nov-22 23-Nov-22 -177
RF.L2.1880 WALL FRAMING (C.L. 8 TO 10) - PHYS. MED / REHAB - L2 10 10 0% 14-Nov-22 28-Nov-22 -177
RF.L2.2350 WALL FRAMING (C.L. 10 TO 13.4) - TELEHEALTH - L2 10 10 0% 29-Nov-22 12-Dec-22 -177
RF.L2.2840 WALL FRAMING (C.L. 9 TO 11) - PACT - L2 10 10 0% 13-Dec-22 27-Dec-22 -177
RF.L2.2970 WALL FRAMING (C.L. 11 TO 13) - PACT - L2 10 10 0% 15-Dec-22 29-Dec-22 -177
RF.L2.3090 WALL FRAMING (C.L. 13 TO 14) - PACT - L2 10 10 0% 19-Dec-22 03-Jan-23 -177
RF.L2.3590 WALL FRAMING (C.L. 1 TO 3) - MENTAL HEALTH - L2 10 10 0% 04-Jan-23 18-Jan-23 -177
RF.L2.3670 WALL FRAMING (C.L. 3 TO 6) - MENTAL HEALTH - L2 10 10 0% 06-Jan-23 20-Jan-23 -177
RF.L2.3780 WALL FRAMING (C.L. 6 TO 9) - MENTAL HEALTH - L2 10 10 0% 10-Jan-23 24-Jan-23 -177
RF.L2.4260 WALL FRAMING (C.L. 1 TO 4) - SUB ABUSE - L2 10 10 0% 25-Jan-23 07-Feb-23 -177
RF.L2.4760 WALL FRAMING (C.L. 3 TO 7) - PROSTHETICS - L2 10 10 0% 08-Feb-23 22-Feb-23 -177
RF.L3.600 WALL FRAMING (C.L. 6 TO 9) - SPS - L3 10 10 0% 23-Feb-23 08-Mar-23 -177
RF.L3.670 WALL FRAMING (C.L. 9 TO 11) - GI - L3 10 10 0% 09-Mar-23 22-Mar-23 -177
RF.L3.700 WALL FRAMING (C.L. 11 TO 14) - GI - L3 10 10 0% 13-Mar-23 24-Mar-23 -177
RF.L3.800 WALL FRAMING (C.L. 1 TO 3) - AMBULANCE / EMERGENCY - L3 10 10 0% 27-Mar-23 07-Apr-23 -177
RF.L3.840 WALL FRAMING (C.L. 3 TO 5) - AMBULANCE / EMERGENCY - L3 10 10 0% 29-Mar-23 11-Apr-23 -177
RF.L3.890 WALL FRAMING (C.L. 5 TO 8) - AMBULANCE / EMERGENCY - L3 10 10 0% 31-Mar-23 13-Apr-23 -177
RF.L3.930 WALL FRAMING (C.L. 8 TO 12) - AMBULANCE / EMERGENCY - L3 10 10 0% 04-Apr-23 17-Apr-23 -177
RF.L4.390 WALL FRAMING (C.L. 6 TO 9) - DENTAL - L4 10 10 0% 18-Apr-23 01-May-23 -177
RF.L4.460 WALL FRAMING (C.L. 9 TO 11) - EYE - L4 10 10 0% 02-May-23 15-May-23 -177
RF.L4.560 INSTALL ELECTRICAL INWALL ROUGH-INS (C.L. 9 TO 11) - EYE - L4 5 5 0% 16-May-23 22-May-23 -177
RF.L4.580 INSTALL PLUMBING INWALL ROUGH-INS (C.L. 9 TO 11) - EYE - L4 5 5 0% 18-May-23 24-May-23 -177
RF.L4.620 INSTALL LOW VOLT INWALL ROUGH-INS (C.L. 9 TO 11) - EYE - L4 5 5 0% 22-May-23 26-May-23 -177
RF.L4.640 INSTALL ELECTRICAL INWALL ROUGH-INS (C.L. 11 TO 13) - EYE - L4 5 5 0% 23-May-23 30-May-23 -177
RF.L4.670 INSTALL PLUMBING INWALL ROUGH-INS (C.L. 11 TO 13) - EYE - L4 5 5 0% 25-May-23 01-Jun-23 -177
RF.L4.700 INSTALL BLOCKING (C.L. 9 TO 11) - EYE - L4 3 3 0% 30-May-23 01-Jun-23 -177
RF.L4.710 INSTALL LOW VOLT INWALL ROUGH-INS (C.L. 11 TO 13) - EYE - L4 5 5 0% 30-May-23 05-Jun-23 -177
RF.L4.750 ONE SIDE DRYWALL (C.L. 9 TO 11) - EYE - L4 3 3 0% 02-Jun-23 06-Jun-23 -177
RF.L4.830 INWALL ROUGH-IN INSPECTION (C.L. 9 TO 11) - EYE - L4 1 1 0% 07-Jun-23 07-Jun-23 -177
RF.L4.780 INSTALL BLOCKING (C.L. 11 TO 13) - EYE - L4 3 3 0% 06-Jun-23 08-Jun-23 -177
RF.L4.840 INWALL INSULATION (C.L. 9 TO 11) - EYE - L4 2 2 0% 08-Jun-23 09-Jun-23 -177
RF.L4.870 ONE SIDE DRYWALL (C.L. 11 TO 13) - EYE - L4 3 3 0% 09-Jun-23 13-Jun-23 -177
RF.L4.900 HANG SECOND SIDE DRYWALL (C.L. 9 TO 11) - EYE - L4 3 3 0% 12-Jun-23 14-Jun-23 -177
RF.L4.950 INWALL ROUGH-IN INSPECTION (C.L. 11 TO 13) - EYE - L4 1 1 0% 14-Jun-23 14-Jun-23 -177
RF.L4.980 INWALL INSULATION (C.L. 11 TO 13) - EYE - L4 2 2 0% 15-Jun-23 16-Jun-23 -177
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
2022 2023 2024 2025 2026
TI PRICING PROPOSAL DEVELOPMENT
TI PRICING PROPOSAL REVIEW/NEGOTIATION/APPROVAL
*TI CONSTRUCTION NTP (PERMIT RECEIVED)
AWARD TENANT INTERIOR
S/F/A INTERIOR FINISHES
R/A INTERIOR FINISHES
INSTALL HMF (C.L. 13.4 TO 15) - MED SPACE - L2
INSTALL HMF (C.L. 15 TO 17) - MED SPACE - L2
INSTALL HMF (C.L. 17 TO 20) - MED SPACE - L2
WALL FRAMING (C.L. 17 TO 20) - MED SPACE - L2
WALL FRAMING (C.L. 10 TO 13.4) - AUDIOLOGY - L2
FAB/DEL INTERIOR FINISHES
WALL FRAMING (C.L. 10 TO 13.4) - CARDIOLOGY - L2
WALL FRAMING (C.L. 6 TO 8) - PHYS. MED / REHAB - L2
WALL FRAMING (C.L. 8 TO 10) - PHYS. MED / REHAB - L2
WALL FRAMING (C.L. 10 TO 13.4) - TELEHEALTH - L2
WALL FRAMING (C.L. 9 TO 11) - PACT - L2
WALL FRAMING (C.L. 11 TO 13) - PACT - L2
WALL FRAMING (C.L. 13 TO 14) - PACT - L2
WALL FRAMING (C.L. 1 TO 3) - MENTAL HEALTH - L2
WALL FRAMING (C.L. 3 TO 6) - MENTAL HEALTH - L2
WALL FRAMING (C.L. 6 TO 9) - MENTAL HEALTH - L2
WALL FRAMING (C.L. 1 TO 4) - SUB ABUSE - L2
WALL FRAMING (C.L. 3 TO 7) - PROSTHETICS - L2
WALL FRAMING (C.L. 6 TO 9) - SPS - L3
WALL FRAMING (C.L. 9 TO 11) - GI - L3
WALL FRAMING (C.L. 11 TO 14) - GI - L3
WALL FRAMING (C.L. 1 TO 3) - AMBULANCE / EMERGENCY - L3
WALL FRAMING (C.L. 3 TO 5) - AMBULANCE / EMERGENCY - L3
WALL FRAMING (C.L. 5 TO 8) - AMBULANCE / EMERGENCY - L3
WALL FRAMING (C.L. 8 TO 12) - AMBULANCE / EMERGENCY - L3
WALL FRAMING (C.L. 6 TO 9) - DENTAL - L4
WALL FRAMING (C.L. 9 TO 11) - EYE - L4
INSTALL ELECTRICAL INWALL ROUGH-INS (C.L. 9 TO 11) - EYE - L4
INSTALL PLUMBING INWALL ROUGH-INS (C.L. 9 TO 11) - EYE - L4
INSTALL LOW VOLT INWALL ROUGH-INS (C.L. 9 TO 11) - EYE - L4
INSTALL ELECTRICAL INWALL ROUGH-INS (C.L. 11 TO 13) - EYE - L4
INSTALL PLUMBING INWALL ROUGH-INS (C.L. 11 TO 13) - EYE - L4
INSTALL BLOCKING (C.L. 9 TO 11) - EYE - L4
INSTALL LOW VOLT INWALL ROUGH-INS (C.L. 11 TO 13) - EYE - L4
ONE SIDE DRYWALL (C.L. 9 TO 11) - EYE - L4
INWALL ROUGH-IN INSPECTION (C.L. 9 TO 11) - EYE - L4
INSTALL BLOCKING (C.L. 11 TO 13) - EYE - L4
INWALL INSULATION (C.L. 9 TO 11) - EYE - L4
ONE SIDE DRYWALL (C.L. 11 TO 13) - EYE - L4
HANG SECOND SIDE DRYWALL (C.L. 9 TO 11) - EYE - L4
INWALL ROUGH-IN INSPECTION (C.L. 11 TO 13) - EYE - L4
INWALL INSULATION (C.L. 11 TO 13) - EYE - L4
3833-08-R0 - FREDERICKSBURG, VA - UPDATE 08 - ISSUED 01 LONGEST PATH Print Date: 10-Jan-22
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
FREDERICKSBURG, VA - UPDATE 08 - ISSUED
Data Date: 03-Jan-22
TASK filter: 01 LONGEST PATH.
Activity ID Activity Name OD RD % Complete Start Finish TF
RF.L4.970 TAPE & FLOAT (C.L. 9 TO 11) - EYE - L4 5 5 0% 15-Jun-23 21-Jun-23 -177
RF.L4.1070 HANG SECOND SIDE DRYWALL (C.L. 11 TO 13) - EYE - L4 3 3 0% 19-Jun-23 21-Jun-23 -177
RF.L4.1140 TAPE & FLOAT (C.L. 11 TO 13) - EYE - L4 5 5 0% 22-Jun-23 28-Jun-23 -177
RF.L4.1390 F/R/P TRANSFORMER PAD - EYE - L4 5 5 0% 29-Jun-23 06-Jul-23 -177
RF.L4.1620 INSTALL TRANSFORMERS - EYE - L4 5 5 0% 07-Jul-23 13-Jul-23 -177
RF.L4.1800 FINAL PAINT WALLS - EYE - L4 5 5 0% 14-Jul-23 20-Jul-23 -177
RF.L4.1960 INSTALL ELECTRICAL PANELS - EYE - L4 10 10 0% 21-Jul-23 03-Aug-23 -177
RF.L4.2230 PULL WIRING - EYE - L4 20 20 0% 04-Aug-23 31-Aug-23 -177
RF.L4.2480 MAKE FINAL CONNECTIONS & TEST - EYE - L4 10 10 0% 01-Sep-23 15-Sep-23 -177
MS.170 PERMANENT POWER AVAILABLE IN ALL FLOORS (COMPLETION OF ALL ELECTRICAL ROOMS)0 0 0% 15-Sep-23 -254
CX.100 START-UP MEP EQUIPMENT 75 75 0% 18-Sep-23 05-Jan-24 -177
CX.120 FINAL TRADE INSPECTIONS 30 30 0% 18-Dec-23 31-Jan-24 -177
CX.140 LIFE SAFETY INSPECTIONS 25 25 0% 01-Feb-24 07-Mar-24 -177
CX.130 GC PUNCH 26 26 0% 01-Feb-24 08-Mar-24 -176
CX.110 TEST AND BALANCE 75 75 0% 18-Dec-23 04-Apr-24 -177
CX.160 CONTROLS AND COMMISSIONING (PRELIMINARY) 30 30 0% 04-Mar-24 12-Apr-24 -177
CX.170 CERTIFICATE OF OCCUPANCY 26 26 0% 08-Mar-24 12-Apr-24 -177
MS.210 CMDC SUBSTANTIAL COMPLETION 0 0 0% 12-Apr-24* -259
CX.150 OWNER PUNCH 26 26 0% 11-Mar-24 15-Apr-24 -176
CX.190 VA PUNCH 41 41 0% 16-Apr-24 12-Jun-24 -176
CX.180 SYSTEMS TRAINING AND COMMISSIONING 61 61 0% 15-Apr-24 10-Jul-24 -175
CX.200 COMPLETE VA PUNCHLIST 40 40 0% 14-May-24 10-Jul-24 -175
MS.230 PUNCHLIST COMPLETION 0 0 0% 10-Jul-24* -257
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA
2022 2023 2024 2025 2026
TAPE & FLOAT (C.L. 9 TO 11) - EYE - L4
HANG SECOND SIDE DRYWALL (C.L. 11 TO 13) - EYE - L4
TAPE & FLOAT (C.L. 11 TO 13) - EYE - L4
F/R/P TRANSFORMER PAD - EYE - L4
INSTALL TRANSFORMERS - EYE - L4
FINAL PAINT WALLS - EYE - L4
INSTALL ELECTRICAL PANELS - EYE - L4
PULL WIRING - EYE - L4
MAKE FINAL CONNECTIONS & TEST - EYE - L4
PERMANENT POWER AVAILABLE IN ALL FLOORS (COMPLETION OF ALL ELECTRICAL ROOMS)
START-UP MEP EQUIPMENT
FINAL TRADE INSPECTIONS
LIFE SAFETY INSPECTIONS
GC PUNCH
TEST AND BALANCE
CONTROLS AND COMMISSIONING (PRELIMINARY)
CERTIFICATE OF OCCUPANCY
CMDC SUBSTANTIAL COMPLETION
OWNER PUNCH
VA PUNCH
SYSTEMS TRAINING AND COMMISSIONING
COMPLETE VA PUNCHLIST
PUNCHLIST COMPLETION
3833-08-R0 - FREDERICKSBURG, VA - UPDATE 08 - ISSUED 01 LONGEST PATH Print Date: 10-Jan-22
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
FREDERICKSBURG, VA - UPDATE 08 - ISSUED
Data Date: 03-Jan-22
TASK filter: 01 LONGEST PATH.