A0002 - ATTACHMENT 7 - Fredericksburg HCC Constructin Progress Report.pdf
PDF 450 KB Posted
- Attached to
- Q702--Fredericksburg Health Care Clinic IOT&A
- Solicitation number
- 36C77622Q0212
About this file
This document provides a lease design and construction progress report for the Fredericksburg Community Based Outpatient Clinic project being undertaken by the Department of Veterans Affairs. Key details include an awarded lease date of September 28, 2020 to Carnegie Management and Development Company with Little Diversified Architectural Consulting and Harvey Clearly Builders on the project team. Construction started on March 4, 2021 and is ongoing with steel erection and stormwater/sewer work currently in progress. Critical milestones include a certificate of occupancy anticipated for June 12, 2024 and final inspection/space acceptance/first use slated for June 12, 2024, October 2, 2024 and October 2, 2024 respectively. The projected lump sum cost is $77,351,165 compared to obligated funds of $91,572,000, resulting in projected excess funds of $14,220,835.
The related federal contract opportunity is a solicitation numbered 36C77622Q0212 for the Fredericksburg Health Care Clinic IOT&A issued by the Department of Veterans Affairs Office of Information Service Center.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lease Design and Construction Progress Report Date:
1/27/2022
Project: Fredericksburg CBOC
Lease Number: 36C10F20L0020
Senior Resident Engineer: Hall, Harvey H.
Project Team
CFM Hall, Harvey H. Gill, Garland
Lessor Canegie Management and Development Co... Little Diversified Architectural Consulting Harvey Clearly Builders
Project Status Photo Milestone Schedule
Lease Award Date 9/28/2020
Kickoff Meeting 10/13/2020
DID 1 Submission 5/21/2021
DID 2 (If required)
Site Permit 3/3/2021
CD Submission 10/22/2021
TI Negotiation (NTP) 3/21/2022
Construction Start 3/4/2021
Budget Building Permit 10/15/2021
Category Planned Projected/Actual C of O 6/12/2024
TI Allowance Cost $76,809,960.00 $76,809,960.00 Final Inspection 6/12/2024
Modifications Issued $0.00 Space Acceptance 2/2/2024
Pending Modifications $0.00 First Use 10/2/2024
REA/Claims $541,205.00 Ribbon Cutting 10/2/2024
Projected Lump Sum $77,351,165.00 Project Performance
Obligated Funds $91,572,000.00 Projected Cost Growth GREEN
Funds Required/Excess $14,220,835.00 Projected Schedule Growth GREEN
Critical Issues:
Title Due Date Response By Description Days Late
Additional Comments:
Lessor submitted TICS to SRE/RE on 01/07/22 and submission is currently under review by SRE/REs. Steel erection/Stormwater/Sewer Manhole install currently ongoing. ASIs to be sent to SRE/RE on 1 Feb