A0002 - ATTACHMENT 6 - Fredericksburg HCC.pdf

PDF 448 KB Posted

Attached to
Q702--Fredericksburg Health Care Clinic IOT&A
Solicitation number
36C77622Q0212
Issued by

About this file

This document provides a lease design and construction progress report for the Fredericksburg Community Based Outpatient Clinic project. The Department of Veterans Affairs has awarded a lease to Carnegie Management and Development to design and construct the new clinic with an anticipated completion date of June 2024. Little Diversified Architectural Consulting is the architect and Harvey Clearly Builders is the general contractor. As of April 2022, steel erection is 90% complete, floor decking is installed, and concrete pours for floors will begin within the next 1-2 weeks. Exterior stud framing is scheduled to start in mid to late April. The site work and utility installations are ongoing. The total projected project cost is $120,541,205 which exceeds the obligated funds by $28,969,205.

The related federal contract opportunity is a solicitation issued by the Department of Veterans Affairs Office of Information Service Center for information technology and audiovisual acquisition and technical assistance for the Fredericksburg Health Care Clinic project. Responses were due by the date specified in the RFQ.

View the file

Other files

File Type Posted
36C77622Q0212 0003.docx DOCX document
Vendor Questions - Fredericksburg - Updated.pdf PDF
36C77622Q0212 0002.docx DOCX document
S05 - Vendor Questions - Fredericksburg.pdf PDF
A0002 - ATTACHMENT 3 - Key Plan Template.docx DOCX document
36C77622Q0212 - Revised.pdf PDF
A0002 - ATTACHMENT 2 - EQUIP LIST UPDATED 3-25-22.pdf PDF
A0002 - ATTACHMENT 1 - Fredericksburg Revised PWS.pdf PDF
A0002 - ATTACHMENT 7 - Fredericksburg HCC Constructin Progress Report.pdf PDF
A0002 - ATTACHMENT 5 - Program For Design.pdf PDF
A0002 - ATTACHMENT 4 - Room Contents List - updated.pdf PDF
A0002 - ATTACHMENT 8 - Conceptual Layout - Fburg - 9.2020.pdf PDF
36C77622Q0212 0001.docx DOCX document
S02 - ATTACHMENT G - QASP.pdf PDF
S02 - ATTACHMENT D - Procurement Package Template 2021.pdf PDF
S02 - ATTACHMENT M - Wage Rate Determination.pdf PDF
S02 - ATTACHMENT U - Room Contents and Acq. Plan Template.xlsx XLSX spreadsheet
S02 - ATTACHMENT T - Re-use Disposal Plan Template.xlsx XLSX spreadsheet
S02 - ATTACHMENT Q - Move Plan Template.xlsx XLSX spreadsheet
S02 - ATTACHMENT O - Pricing Worksheet - Fredericksburg.xlsx XLSX spreadsheet
S02 - ATTACHMENT R - Change Management Plan Log Template.xlsx XLSX spreadsheet
S02 - ATTACHMENT K - JSN Responsibility Matrix.xlsx XLSX spreadsheet
S02 - ATTACHMENT A - Fredericksburg IOTA PWS.pdf PDF
S02 - ATTACHMENT E - Meeting Minutes template.pdf PDF
S02 - ATTACHMENT C - ProjectContentsList_BAILEE FREDERICKSBURG PFD 1-9.xlsx XLSX spreadsheet
S02 - ATTACHMENT H - Contract Staff Roster.pdf PDF
S02 - ATTACHMENT F - 6500.6 Appendix A.pdf PDF
S02 - ATTACHMENT B - Travel Authorization Request.pdf PDF
S02 - ATTACHMENT V - Fredericksburg Drawings.pdf PDF
S02 - ATTACHMENT I - VSC Security Request Forms.pdf PDF
S02 - ATTACHMENT P - Risk Register Template.xlsx XLSX spreadsheet
S02 - ATTACHMENT S - WBS template.pdf PDF
36C77622Q0212.docx DOCX document
S02 - ATTACHMENT L - FREDERICKSBURG VA Construction Schedule.pdf PDF
S02 - ATTACHMENT J - PDAT Summary.pdf PDF
S02 - ATTACHMENT N - Furniture IDIQ Templates.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lease Design and Construction Progress Report Date:

4/4/2022

Project: Fredericksburg CBOC AKA:

Lease Number: 36C10F20L0020

Senior RE: Hall, Harvey H.

Project Team

CFM Hall, Harvey H. Adams, Charles E. Gill, Garland

Lessor Carnegie Management and Development C... Little Diversified Architectural Consulting Harvey Clearly Builders

Project Status Photo Milestone Schedule

Lease Award Date 9/28/2020

Kickoff Meeting 10/13/2020

DID 1 Submission 5/21/2021

DID 2 (If required)

Site Permit 3/3/2021

CD Submission 10/22/2021

TI Negotiation (NTP) 3/21/2022

Construction Start 3/4/2021

Budget Building Permit 10/15/2021

Category Planned Projected/Actual C of O 6/12/2024

TI Allowance Cost $76,809,960.00 $120,000,000.00 Final Inspection 6/12/2024

Modifications Issued $0.00 Space Acceptance 2/2/2024

Pending Modifications $0.00 First Use 10/2/2024

REA/Claims $541,205.00 Ribbon Cutting 10/2/2024

Projected Lump Sum $120,541,205.00 Project Performance

Obligated Funds $91,572,000.00 Projected Cost Growth RED

Funds Required/Excess $28,969,205.00 Projected Schedule Growth GREEN

Critical Issues:

Title Due Date Response By Description Days Late

Additional Comments:

The steel erection is roughly 90% complete and floor decking is installed and concrete pours for the floors will commence in 1-2 weeks. Exterior stud framing to start possibly mid to late April. Site work is ongoing and the storm water/sewer piping is being installed and the water main installation is currently underway.