This document is an attachment to a Task Order (TO-E) under the 36C25226B0020 IDIQ Abatement contract for the Hines Abatement project covering Buildings 1 and 200. The attachment details six abatement tasks with specific scope, timelines, and location information.
Tasks 1 and 2 involve abatement work in Building 1, Floor 3 (Rooms D333, D335, and D335A) with 8 calendar days, 6 abatement days, and 8 monitoring days allocated. The scope includes abating all lead paint excluding windows (with contractor assumption that all paint is lead-based), abating all asbestos-containing materials (ACM) floor tile, ceiling tile, glue dots, mastic, and pipe insulation/fittings/elbows, and re-insulating all abated piping. Tasks 3, 4, and 5 cover Building 1, Floor 4 (Rooms D405, D407, D407A, D409, and D409A) with identical abatement requirements but requiring 10 calendar days, 8 abatement days, and 10 monitoring days. Task 6 addresses Building 200's stone space with 34 calendar days, 32 abatement days, and 34 monitoring days, focusing solely on ACM pipe insulation, fittings, and elbows abatement with re-insulation. All work is scheduled for Monday-Friday day shift hours, and the document includes floor plan drawings identifying the specific rooms and areas requiring abatement treatment.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tasks 1 and 2 Bldg 1 – Floor 3, Room D333, D335, and D335A
Calendar Days = 8 Abatement Days = 6 Monitoring Days = 8
• Abate all lead paint – excluding all windows – contractor shall assume all paint is lead based paint.
• Abate all ACM floor tile, ceiling tile, glue dots, mastic, pipe insulation, pipe fittings, and pipe elbows
• Re-insulate all abated piping, pipe fittings, and pipe elbows.
• This work can be completed during Monday-Friday day shift hours
36C25226B0020 IDIQ Abatement
ATTACHMENT 7.6
578-26-008 Hines Abatement TO-E Bldgs 1 and 200
Tasks 3, 4, and 5 Bldg 1 – Floor 4, Room D405, D407, D407A, D409 and D409A
• Abate all lead paint – excluding all windows – contractor shall assume all paint is lead based paint.
• Abate all ACM floor tile, ceiling tile, glue dots, mastic, pipe insulation, pipe fittings, and pipe elbows
• Re-insulate all abated piping, pipe fittings, and pipe elbows.
• This work can be completed during Monday-Friday day shift hours
Calendar Days = 10 Abatement Days = 8 Monitoring Days = 10
36C25226B0020 IDIQ Abatement
ATTACHMENT 7.6
578-26-008 Hines Abatement TO-E
Tasks 6 Bldg. 200 Stone space – Example of an existing condition
Calendar Days = 34 Abatement Days = 32 Monitoring Days = 34
• Abate all ACM pipe insulation, pipe fittings, and pipe elbows
• Re-insulate all abated piping, pipe fittings, and pipe elbows.
• This work can be completed during Monday-Friday day shift hours
36C25226B0020 IDIQ Abatement
ATTACHMENT 7.6
578-26-008 Hines Abatement TO-E
| Slide Number 1 |
| Slide Number 2 |
| Slide Number 3 |
File details come from the government source that posted it. Updated .