This statement of work outlines requirements for construction services to fully renovate approximately 17,230 square feet of an existing clinical lab and pathology department at the Jennifer Moreno VA Medical Center in San Diego, California. The project includes demolition, asbestos abatement, new construction of interior partitions and finishes, and mechanical, plumbing and electrical systems work. The contractor must provide all labor, materials and equipment to complete the project in accordance with construction documents and specifications. Work is to be performed over a 360 calendar day period for a total contract value of $5,000,000. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration VISN 22.

View the file

Other files

File Type Posted
Contract Award Notice_36C26223C0282.pdf PDF
Amendment 0003 - Attachment 9. 1XA.pdf PDF
Amendment 0003 - Attachment 21. DWGFINALSUBMITTAL.pdf PDF
Amendment 0003 - Attachment 16. Structural Drawings.pdf PDF
Amendment 0003 - Attachment 7. 1CEXM.pdf PDF
Amendment 0003 - Attachment 12. MCC.pdf PDF
Amendment 0003 - Attachment 22. Building 1 Fire Spinkler Valves 8.5x11.pdf PDF
Amendment 0003 - Attachment 3. 1CEXC Rev1.pdf PDF
Amendment 0003 - Attachment 20. MH-6.03 Rev01.pdf PDF
Amendment 0003 - Attachment 1. 1A Rev1.pdf PDF
Amendment 0003 - Attachment 2. 1CEXB Rev1.pdf PDF
Amendment 0003 - RFI Notice.pdf PDF
Amendment 0003 - Attachment 5. 1CEXG Rev1.pdf PDF
Amendment 0003 - Attachment 19. VA SD Master Finish Legend.pdf PDF
Amendment 0003 - Attachment 4. 1CEXF Rev1.pdf PDF
Amendment 0003 - Attachment 18. Grating and Fall Protection Railing Criteria.pdf PDF
Amendment 0003 - Attachment 14. Comprehensive Hazardous Materials Survey.pdf PDF
Amendment 0003 - Attachment 10. 1XAA Rev1.pdf PDF
Amendment 0003 - Attachment 11. 1XR Rev1.pdf PDF
Amendment 0003 - Attachment 13. Panel Photos.pdf PDF
Solicitation Amendment 0003 (SF30)_36C26223B0016 0003.pdf PDF
Amendment 0003 - Attachment 17. Record Drawings.pdf PDF
Amendment 0003 - Attachment 6. 1CEXGA Rev1.pdf PDF
Amendment 0003 - Attachment 15. 1st Floor PA.pdf PDF
Amendment 0003 - Attachment 8. 1CEXN.pdf PDF
S06 - Amendment 0002_ Att J. Pre-Bid Conference Site Visit Sign-in Sheet.pdf PDF
S06 - Solicitation Amendment 0002 (SF30)_36C26223B0016 0002.pdf PDF
S06 - Solicitation Amendment (SF30)_36C26223B0016 0001.pdf PDF
S02 - Att F. IFC Drawings 3.pdf PDF
S02 - Att H. Site Visit Map.pdf PDF
S02 - Att C. Specifications - VASD Modernize Pathology Project Manual_Vol 2.pdf PDF
S02 - Att E. IFC Drawings 2.pdf PDF
S02 - Att G. DB Wage Rates_GDN CA20230001 06.09.2023.pdf PDF
S02 - Att D. IFC Drawings 1.pdf PDF
S02 - Solicitation (SF1442)_36C26223B0016.pdf PDF
S02 - Att B. Specifications - VASD Modernize Pathology Project Manual_Vol 1.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Modernize Pathology Dept., Bldg. 1 July 11, 2023 Jennifer Moreno VA Medical Center (664) San Diego, California

664-18-333

B.1 INTRODUCTION:

This requirement is to provide all necessary labor, materials, tools, equipment, engineering, supervision, and services to construct all applicable demolition, asbestos abatement, walls, partitions, interior finishes, fire suppression systems, mechanical, plumbing, electrical, and telecom work and other services necessary for Project 664-18-333 Modernize Pathology Dept., Bldg. 1, Jennifer Moreno VA Medical Center San Diego (JMVAMCSD), 3350 La Jolla Village Drive, San Diego, CA 92161. This requirement is classified under construction as it calls for the alteration of real property.

B.2 BACKGROUND / DESCRIPTION OF WORK:

The Veterans Affairs Healthcare System located in San Diego, California (664) requires construction services to construct in accordance to contract drawings and specifications to fully renovate approximately 17,230 sf of the existing Clinical Lab / Pathology dept. to allow the Clinical Lab to operate efficiently, correct FCA deficiencies, Life Safety and to support all of VASD clinics / departments and support current laboratory service function. The Clinical Lab will only be renovated within the allocated space which will modernize the anatomical pathology area, microbiology gross room and Clinical Lab administration. The project will be phased to allow Clinical Lab to remain in service during the modernization. The remodel will have significant space and MEP changes to match the required VHA handbook requirement as well as full asbestos abatement. The project includes all labor, materials, tools and equipment for the modification, renovation and new construction.

INTERIORS

The interior design for this project will be based upon the existing San Diego VA finish standards in order to maintain a consistent appearance with existing adjacent spaces not within the scope of work. All interior design materials and colors shall be coordinated with the VA Interior Designer.

Use of and adherence of Industry and VA standards is required for acceptance of this project.

B.3 CONSTRUCTION DOCUMENT:

Contractor shall furnish all labor, equipment, certification, supervision, and materials necessary to perform all operations in connections with this order. Contractor shall perform work in strict accordance with the General Specifications, Statement of Work, schedule, and all other supporting documents for this contract to include, but not limited to the following documents:

B.4 SPECIFICATIONS

A. The VA Master Construction Specifications contain work procedures and material requirements designed to meet regulatory compliance requirements. Whenever possible, the Master Construction Specifications must be used as the basis for project designs.

B. A complete list of these specifications can be viewed at the following website:

http://www.cfm.va.gov. Specifications which address EOSH requirements include, but are not limited to, the following:

a. SECTION 01 00 00 – General Requirements

b. SECTION 01 57 19 – Temporary Environmental Controls

c. SECTION 01 74 19 – Construction Waste Management

d. SECTION 02 82 11 – Traditional Asbestos Abatement

e. SECTION 02 82 13.13 – Glovebag Asbestos Abatement

f. SECTION 02 82 13.19 – Asbestos Floor Tile and Mastic Abatement

g. SECTION 02 82 13.31 – Asbestos Transite Abatement

h. SECTION 02 83 33.13 – Lead Based Paint Removal and Disposal

B.5 SPECIFIC REQUIREMENTS

A. Scope

a. The Contractor must provide all necessary labor, material, equipment to demolish architectural finishes, plumbing, mechanical, electrical systems, asbestos abatement, and lead abatement supervision and personel necessary to accomplish the project as indicated on the attached contractual documents. Complete containment of area and 100% abatement of existing asbestos and lead paint.

Abatement of hazardous material such as asbestos, lead paint, etc. on structural steel in interstitial, structural support systems, exterior metal panel walls, vinyl floor tile with asbestos mastic, sheet vinyl floors with asbestos mastic, ceramic tile floor/walls, acoustical ceiling grid and tile, gypsum board ceilings. Paint all interstitial metal that is affected by new work. VASD will provide Hazmat Survey Report, dated March 2015 for reference only. Spray fireproofing shall be reapplied to all structural members after removal of asbestos.

b. The project will involve but not limited to trades required for the complete renovation of the Modernize Pathology Dept. and other impacted Services as part of this project to include but not limited to new interior construction of interior partitions, ceilings, flooring, and finishes, associated mechanical, plumbing, and

A E Firm Document Title Document Date Number of

Pages

DAVY

Architecture

Specifications:

IFC-Vol1_VASD Modernize Pathology_Project Manual IFC-Vol2_VASD Modernize Pathology_Project Manual

07/09/2021 2016

DAVY

Architecture

Drawings:

Modernize Pathology Dept., Bldg. 1

07/09/2021 electrical systems required for a fully functional and complete project including but not limited to replacement of air handling units, ventilation, etc. (HVAC) serving the zone including all terminal units, HVAC piping, ductwork, removal of all electrical, signal, and data/communication lines, medical gases, emergency power on the floor level and interstitial level. To the greatest extent possible as allowed by the project budget (CCL), this project will also include all necessary specialty lab equipment/technology or other consultants required to insure a state-of-the-art project.

c. DAVY Architecture is the project Architect/Engineer hired by the VA and has prepared drawings and specifications which are part of this SOW and are to be used for the completion of this project.

d. All employees of the general contractor and subcontractors shall comply with the

VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

e. Prior to commencing work, the general contractor shall provide proof that an

OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.

f. Prior to the commencement of work, the general contractor shall conduct a site walk with the VA COR, VA Safety Manager and VA Infection Control Agent.

1. The general contractor shall establish and maintain a fire protection program in accordance with 29 CFR 1926.

2. The general contractor shall implement the requirements of the VA Infection Control Risk Assessment (ICRA) team, including the establishment and maintenance of a dust control program.

3. Upon completion of the site walk. The general contractor will be issued a Work Permit, ILSM and IC implementation permit.

4. Contractor will provide all documentation per Specifications and validated by the submittal registry to the COR prior to work.

B. General

a. The Contractor is solely responsible to verify by field measurement the size and location of all features.

b. The Contractor is solely responsible to verify by field measurement, and bring out any discrepancies in a timely maner to the VA Construction Project Manager.

c. A complete and thorough site assessment must be performed by the contractor prior of commencement of any work and after issue of NTP.

d. The contractor must develop construction schedule (including critical path), and a phasing plan prior to the NTP and submit it for approval to the VA Construction Project Manager.

e. During the construction Phase the contractor shall submit for approval a schedule of his operations and phasing plan prior to start in any new phase, the project is to be phased so as not to interrupt the campus health care, or supply services. Phasing will be developed by the contractor and approved by the VA Project Manager to either avoid service interruptions or keep interruptions to an absolute minimum.

f. The Contractor shall develop a schedule of construction which includes the necessary actions to maintain the operation of the adjacent function (including one floor above) during the construction process.

g. Contractor must verify breakers and perform proper lock-out procedures.

h. Contractor must implement all requirements of VA Infection Control Risk Assessment

(ICRA) Category 4.

i. Contractor must complete the proper request forms, if necessary for after-hour request, badge request, Cutting and Welding request, and any other forms required to perform work safely and per the facility policies.

j. Detailed project implementation plan and safety plan is required to be submitted to VA Project Manager before commencement of construction.

k. Contractor will execute measures to ensure least amount of disruption to operation of the facility and visitors’ safety.

l. The Contractor must coordinate work with VA Construction Project Manager and unit’s staff to minimize disruption of their daily operations.

m. Contractor must provide dumpsters and construction waste management. The Contractor must remove and dispose of all trash/debris from the work area to a location designated by the Contractor. This location must not be on the facility grounds.

Contractor must ensure all trash is sealed to prevent dissemination of contaminant across the facility.

n. Contractor must use industry standard STP file sharing system. Refer to Specs.

C. SETUP

a. The Contractor must coordinate all work with the VA Construction Project Manager.

b. The Contractor will not interfere with the operation of the Facility.

c. The contractor shall keep a thoughtful daily schedule in coordination with the VA

Construction Project Manager, as this project requires touching every space in the Facility.

d. The Contractor must coordinate with VA Construction Project Manager, and use Impact Notification Memos, and provide daily e-mail updates to keep informed VA Leadership and Staff.

e. The contractor must coordinate dumpster locations, portables toilets, storage units, and staging areas with VA Construction Project Managers.

D. General Requirements

i. Refer to plans and specs.

E. Existing Conditions

j. Refer to plans and specs, refer to B.5-B-b of this document.

B.6 CONFORMANCE STANDARDS:

A. All design and construction accomplished pursuant to this contract shall comply with the latest edition of the following documents unless the contractor is directed otherwise by the Contracting Officer. Any exceptions must be approved in writing by the Contracting Officer prior to construction startup.

a. VA Master Construction Specifications https://www.cfm.va.gov/til/spec.asp#01

b. VA Construction Standards

c. VA Seismic Design Handbook

d. VA Space Planning Criteria

e. VA Design Manuals https://www.cfm.va.gov/til/dManual.asp

f. VA Design Alerts https://www.cfm.va.gov/til/alert.asp

g. VA CADD Standards

h. NFPA 101, Life Safety Code

i. NFPA 241, Standard for Safegarding Const., Alteration & Demolition

Operations

j. NFPA 70, National Electric Code

k. NFPA 99, Health Care Facilities

l. NFPA 12, Installation of Sprinkler Systems

m. Accessibility Standards (ADAAG, ABAAS, Barrier Free Design Guide)

n. AIA Guidelines for Construction and Equipment of Hospital and Medical

Facilities

o. International Building Codes

p. State and Local codes and guidelines (as applicable)

B.7 HOURS OF COVERAGE:

A. Normal hours of operation are Monday through Friday from 7:00 am to 4:30 pm California time (no daylight savings). All work is expected to be performed generally during normal hours of coverage unless requested or approved by the COR or his/her designee.

B. The Contractor will determine in coordination with the VA Construction Project Manager the option of a 24/7 schedule or longer shifts to fullfill the project schedule, and to prevent as much as possible any disruption in the operation of the Facility.

C. The contractor must coordinate with the VA Construction Project Manager the best hours of operation for every impacted area, to avoid any disruption in the operation of the Facility.

a. All loud construction activities including but not limited to concrete saw cutting, hammer drilling, shot pin anchoring shall be performed outside of normal business working hours which is M-F 7:00am-4:30pm. Contractor to coordinate all loud construction work to minimize impact to the facility.

D. Before commencement of work, the Contractor shall confer with the VA COR and Contracting

Office to agree on a sequence of procedures; means of access to premises and building. All work performed, to include delivery of materials and equipment, shall be made with minimal interference to Government operations and personnel.

E. Work performed outside the normal hours of coverage must be approved by the COR or his/her designee.

F. Federal Holidays observed by VASDHCS are:

New Years' Day Labor Day Martin Luther King Day Columbus Day Presidents' Day Veterans' Day Memorial Day Juneteenth Day Thanksgiving Day Independence Day Christmas Day

B.8 IDENTIFICATION, PARKING, NO SMOKING POLICY, & VA REGULATIONS:

A. The Contractor's FSEs shall wear visible identification issued by VAHCS Police Section at all times while on the premises of VAHCS. It is the responsibility of the Contractor to park in the appropriate designated parking areas. Information on parking is available from the VA Police

Section. VAHCS will not invalidate or make reimbursement for parking violations of the Contractor under any conditions. Smoking is strictly prohibited anywhere on the Veterans Affairs Health Care Facilities, to include main facility, and any other buildings at on the premises. Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States (Federal) District Court, not a local district, state, or municipal court.

B.9 INFORMATION SECURITY:

A. In accordance with Appendix A, Handbook 6500.6 Checklist blocks 7, the C&A requirements do not apply to this requirement, and Security Accreditation Package is not required. The nature of this requirement is technical; however, there is no information to be protected.

B.10 POINTS OF CONTACT AND PHYSICAL LOCATION:

A. Access to worksite shall be coordinated through the Engineering Services Department located at:

Point of Contact – COR Wilson Rowley (858) 518-2705

Jennifer Moreno VA Medical Ctr., San Diego Engineering Service (664) 3350 La Jolla Village Drive, San Diego, CA 92161

B.11 PERIOD OF PERFORMANCE:

A. Commencement of work shall begin within 10 days after receipt of written Notice to

Proceed (NTP) and should last no longer than a duration of 360 Calendar days after date NTP is issued.

B.12 SUBMITTALS:

B. Contractor shall submit all required material/shop drawing submittals to the Contracting

Officer within 10 calendar days of award, or as agreed to by the Contracting Officer for approval. No materials shall be installed prior to approval.

C. All material submittals and shop drawings shall contain, and have the Project Title, Project Number, and Contract number clearly indicated.

D. Material submittals and shop drawings shall be checked and signed by the Contractors Quality Control Manager prior to submission to the Government.

E. Submittals shall be legible and shall include all technical data needed to verify that the item meets requirements of listed specifications, and applicable codes.

B.13 COMMENCEMENT, COMPLETION, AND PAYMENT FOR WORK:

A. The Contractor shall be required to commence work required at the time specified on the Notice to Proceed (NTP), execute the work, and complete the entire work not later than the completion time specified on the NTP. The time stated for completion shall include final cleanup of the premises. At the government’s option, it may choose to specify a two-stage performance period.

For example, separating material lead-time from construction days can considerably decrease the length of time occupied buildings are inconvenienced by construction.

B. Before commencement of work, the Contractor shall confer with the VA COR and Contracting

Office to agree on a sequence of procedures; means of access to premises and building; space for storage of materials and equipment; delivery of materials and use of approaches; use of corridors, stairways, elevators, and similar means of communications; location of partitions, eating spaces, and restrooms for the Contractor employees; and the like. Delivery of materials and equipment shall be made with minimal interference to Government operations and personnel.

C. The Contractor will be paid monthly upon submission of proper invoices for work completed.

If the performance period exceeds 30 days and a progress schedule (approved by the Government) has been submitted, partial payment(s) may be authorized. Final payment will be withheld until all discrepancies are corrected and as-built drawings are approved by the Government.

D. The contractor shall attend weekly progress meetings with the COR and/or Contracting Officer to discuss at a minimum; progression of work, projected progress versus actual progress, action items due from the contractor, action items due from the government, and any other significant issues that require attention. The contractor also shall document the meeting minutes and forward a signed copy to the COR for concurrence of the documentation. Copies of all minutes will be forwarded to the Contracting Officer. In the event of any discrepancies the Contracting Officer will be notified immediately for clarification.

B.14 MODIFICATIONS:

A. Modifications for this project must be submitted to the assigned COR who will then submit a formal request to the Contracting Officer (CO). New work is not allowed to commence prior to Contracting Officer’s signed and written approval via fully executed Standard Form (SF) 30 modification.