S02 - 9 Interim Life Safety Measures ILSM.pdf

PDF 330 KB Posted

Attached to
Z1DA--578-18-024 SCI Recreation Area Outdoor Construction
Solicitation number
36C25224B0013
Issued by

About this file

This document is a VA Hospital Policy Memorandum that establishes procedures for implementing interim life safety measures (ILSM) during construction projects at the Hines, IL VA Hospital.

The policy outlines the 11 ILSM actions required to compensate for Life Safety Code deficiencies or construction hazards, including ensuring unobstructed exits, maintaining fire protection systems, and providing additional firefighting equipment and training. It defines the responsibilities of various hospital departments for evaluating projects, implementing ILSMs, conducting inspections, and providing training. The policy also includes several attachments with worksheets and inspection forms for documenting the ILSM assessment and monitoring compliance. Overall, the memorandum provides a comprehensive framework for managing life safety during construction activities at the VA facility.

View the file

Other files

File Type Posted
S02 - Att2 Snip of Physical Therapy Space.png PNG image
36C25224B0013 0005.docx DOCX document
S02 - Att1 CS101 Sheet Plan photos.pdf PDF
S02 - Att5 Insert A BID SCHEDULE.pdf PDF
S02 - Att1 IMG_3364.jpg JPG image
S02 - Att2 IMG_3365.jpg JPG image
S02 - Att3 CS101 Sheet Plan photos.pdf PDF
S02 - Att4 Site Visit Sign-in.pdf PDF
36C25224B0013 0004.docx DOCX document
S02 - Att2 Insert A BID SCHEDULE.pdf PDF
S02 - Att1 SOW Revised RFI Update.pdf PDF
S02 - Att3 Site Visit 1 Sign-in.pdf PDF
36C25224B0013 0003.docx DOCX document
36C25224B0013 0002.docx DOCX document
36C25224B0013 0001.docx DOCX document
S02 - 8 Pre-Construction Risk Assessment PCRA.pdf PDF
36C25224B0013_1.docx DOCX document
S02 - 12 Contractor Parking.pdf PDF
S02 - 14 578-18-024 Specifications.pdf PDF
S02 - Att 19 Final SOW 578-18-024.pdf PDF
S02 - 1 Hines VA Campus Site Plan.pdf PDF
S02 - 10 Infection Control Risk Assessment ICRA.pdf PDF
S02 - 17 Photos Current Conditions.pdf PDF
S02 - 13 OIT Horizontal Cable Requirements 02.pdf PDF
S02 - 15 578-18-024 BOD.pdf PDF
S02 - 7 Above Ceiling Entry and Wall Construction Permits.pdf PDF
S02 - 4 Safety and Health During Construction Activities.pdf PDF
S02 - 16 578-18-024 Bid Documents P1.pdf PDF
S02 - 2 Hines Underground Utility Plan.pdf PDF
S02 - 16 578-18-024 Bid Documents P2.pdf PDF
S02 - Att 18 Wage Rate IL20240009 07.26.2024.pdf PDF
S02 - 5 Cutting Welding and Other Hot Work.pdf PDF
S02 - 3 Pre-Construction Checklist.pdf PDF
S02 - 11 Contractor PIV Instructions and Form.pdf PDF
S02 - 6 Dig Permit SOP Form.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Hospital Policy Memorandum 578-02-001-088(R-3) Hines, IL 60141 November 25, 2014

INTERIM LIFE SAFETY MEASURES

Changes:

3c(1) The Chief, Project/Planning Section, FMS, the Chief, Maintenance Section, FMS, the Chief, Information Resources Management, and all other service/section chiefs who have program responsibility for construction projects and/or activities, including work/projects involving penetrations of walls and/or ceilings are responsible for:

(1) Ensuring the accurate preparation and timely submission of the ILSM Construction Project Evaluation Worksheet (Attachment B).

(2) Ensuring that an amended ILSM Construction Project Evaluation Worksheet for the project is promptly submitted to Safety if changes impacting ILSM occur after the construction phase of a project or construction activities begins, and

(3) Ensuring that the members of their respective staffs assigned project coordination duties know and understand the provisions of this plan, and monitor plan compliance within their respective work groups.

Education /Training: Policy to be review at service/service line staff meetings.

Related forms - Attachments

• Attachment A - Interim Life Safety Measures

• Attachment B - Interim Life Safety Measures Construction Project Evaluation Worksheet

• Attachment C - Interim Life Safety Measures Occupant impact Evaluation Worksheet.

• Attachment D - Interim Life Safety Measures High Hazard Inspection Report

• Attachment E – Fire Watch Decision Grid

VA Hospital Policy Memorandum 578-02-001-088 (R-3) Hines, IL 60141 November 25, 2014

1. PURPOSE: To establish specific procedures for implementing those provisions of the Hospital Fire Safety Management Plan pertaining to the use of interim life safety measures

(ILSM).

2. POLICY:

a. The eleven interim life safety measures, listed on Attachment A, are a series of administrative actions required to temporarily compensate for significant hazards posed by existing Life Safety Code (LSC) deficiencies or construction activities.

b. The ILSM assessment will be completed before any constructions project is initiated.

c. Interim life safety measures will apply to appropriate personnel, including construction workers, will be implemented upon project development, and will be continuously enforced through project completion.

d. A fire watch is implemented on a “case-by-case” basis as determined by the fire watch decision grid. (Attachment E)

3. RESPONSIBILITIES:

a. The Safety Section is assigned overall responsibility for developing, implementing, enforcing and evaluating the effectiveness of the complete Interim Life Safety Measures Policy.

b. The Safety Section is responsible for:

(1) Evaluating specific LSC deficiencies and construction hazards to determine when and to what extent one or more of the listed ILSMs are applicable,

(2) Maintaining required ILSM records and for conducting required ILSM inspections, testing, training, and monitoring as required,

(3) The day-to-day enforcement of the ILSM plan, and

(4) For advising the Chief, FMS, as to the effectiveness of the plan, and recommending plan improvements as necessary.

(5) Provide the appropriate training for all affected personnel if it is determined that ILSM measures are to be implemented, and

(6) If appropriate based on the ILSM to be implemented, conduct addition fire drills in accordance with Hospital Policy 578-02-001-086 Fire Safety.

c. The Chief, Project/Planning Section, FMS, the Chief, Maintenance Section, FMS, the Chief, Office of Information and Technology, and all other service/section chiefs who have program responsibility for construction projects and/or activities, including work/projects involving penetrations of walls and/or ceilings are responsible for:

(1) Ensuring the accurate preparation and timely submission of the ILSM Construction Project Evaluation Worksheet (Attachment B),

(2) Ensuring that an amended ILSM Construction Project Evaluation Worksheet for the project is promptly submitted to Safety if changes impacting ILSM occur after the construction phase of a project or construction activities begins, and

(3) Ensuring that the members of their respective staffs assigned project coordination duties know and understand the provisions of this plan, and monitor plan compliance within their respective work groups.

d. Police Service is responsible for:

(1) Conducting daily inspections of sites under ILSM during weekends and holidays.

(2) Documenting findings of daily inspections on Attachment D.

4. ACTIONS:

a. The chief of a service or section initiating a construction project to be accomplished by a contractor will ensure that requirements for full compliance with all applicable NFPA LSC Codes and Hines Hospital fire and safety policies are communicated to all parties involved.

b. A minimum of two weeks before the start of the construction phase of a project, the chief of the service or section responsible for the project will ensure that an ILSM Construction Project Evaluation Worksheet, describing the project and its potential impact on life safety, is accurately completed and submitted to Safety through the Chief, FMS. After the construction phase of a project begins, the responsible service or section chief will ensure that an amended ILSM Construction Project Evaluation Worksheet for the project is promptly submitted to Safety if changes impacting ILSM occur.

c. Safety staff will review the ILSM Construction Project Evaluation Worksheet submitted for each project, inspect the job site as necessary, obtain additional information as required, and complete an ILSM Occupant Impact Evaluation Worksheet (Attachment C).

d. If it is determined on the basis of the evaluations conducted that ILSMs are not required for a particular project, Safety personnel will advise the responsible service/section chief accordingly.

e. Should it be determined that one or more ILSMs are required to be used during a given project, Safety personnel will explain the actions necessary to the responsible service/section chief and will ensure implementation of the ILSMs as appropriate. ILSMs required for a project will be discussed in detail and noted in the minutes of each pre-construction meeting pertaining to that project.

f. When the construction phase of a project with required ILSMs begins, Safety will initiate daily inspection of the site to ensure that ILSMs are in effect, and for compliance with established safety codes and policies. These inspections will continue through project completion. Findings will be documented on the ILSM High Hazard Inspection Report (Attachment D).

g. Police Service will conduct daily inspections on weekends and holidays.

5. REFERENCES:

a. The Joint Commission (TJC), Environment of Care Standards.

b. Hospital Policy, 578-02-001-086(R3) Fire Safety, dated December 12, 2014.

c. Hospital Policy, 578-03-001-089(R2), Cutting, Welding, and Other Hot Work, dated July 5, 2013.

d. Hospital Policy, 578-12-138A-076(R1), Safety and Health during Construction

Activities, April 11, 2014.

6. RESCISSION: Policy Memorandum 578-02-001-088 (R-2), Interim Life Safety Measures, dated October 3, 2011.

7. RECERTIFICATION: This policy memorandum will be re-certified on or before November 26, 2017.

8. FOLLOW-UP RESPONSIBILITY: Safety Section (001S).

/s/ Daniel S. Zomchek, Ph.D., FACHE Acting Hospital Director

Attachments

Distribution: Hines Intranet Website and Service Chiefs via E-mail

Attachment A Policy Memorandum 578-02-001-088(R-3) November 25, 2014

1. Ensuring free and unobstructed exits. Personnel in affected areas receive additional training when alternative exits are designated. Buildings or areas under construction must always maintain escape routes for construction workers. Means of exiting construction areas are inspected daily.

2. Ensuring free and unobstructed access to emergency services and for fire, police, and other emergency forces.

3. Ensuring fire alarm, detection, and suppression systems are in good working order. A temporary but equivalent system shall be provided when any fire system is impaired. Temporary systems must be inspected and tested monthly.

4. Ensuring temporary construction partitions are smoke-tight and built of noncombustible or limited combustible materials that will not contribute to the development or spread of fire.

5. Providing additional firefighting equipment and training personnel in its use.

6. Prohibiting smoking, according to the Joint Commission Environment of Care standards, throughout all buildings on the station as well as in and adjacent to construction areas.

7. Developing and enforcing storage, housekeeping, and debris removal practices that reduce the building’s flammable and combustible fire load to the lowest feasible level.

8. Conducting a minimum of two fire drills per shift per quarter.

9. Increasing hazard surveillance of buildings, grounds, and equipment with special attention to excavations, construction areas, construction storage, and field offices.

10. Training personnel to compensate for impaired structural or compartmentalization features of fire safety.

11. Conducting organization-wide safety education programs to promote awareness of Life Safety Code deficiencies, construction hazards, and Interim Life Safety Measures.

Attachment B

EDWARD HINES JR. VA HOSPITAL

FACILITIES MANAGEMENT SERVICE

CONSTRUCTION PROJECT EVALUATION WORKSHEET

PROJECT TITLE/NUMBER: _578-18-024 Construct SCI Recreation Activity Area____

BUILDING/ROOM NUMBER: _Field Between B001 and B221______________________

SERVICE/SECTION RESPONSIBLE: _Project Engineering________________________

EFFECTS ON LIFE SAFETY

Provide a brief description of the project and any effects it is likely to have on life safety.

Examples include: closing of an exit; use or storage of flammable materials on-site; installation of a dust barrier; blocking streets, driveways or access roads; impairment of fire detection and/or suppression systems; and removal of doors.

Project will likely impede southeastern most exit of B001 Section A as well as exits that run the connecting corridor to B221. The project will also disrupt normal traffic flow in parking lot adjacent to B001.

SPECIFIC SAFETY CONCERNS

Will any of the work to be performed during this project as currently planned compromise or impair the use of the critical elements of fire protection listed below?

1. FIRE ALARM SYSTEMS: YES ____ NO _X___

If YES is checked above, provide additional details, including number of devices affected and length of time systems will be impaired, on a separate sheet.

2. AUTOMATIC FIRE SPRINKLER SYSTEMS: YES ____ NO _X___

If YES is checked above, provide additional information including the size and occupancy of the area affected, and the anticipated duration of the impairment.

3. EXITS (STAIRWELLS, CORRIDORS & DOORS): YES ____ NO _X___

If YES is checked above, provide additional information including the type, number, and location of exits, which will be obstructed, and the anticipated duration of the impairment.

4. ACCESS TO EMERGENCY VEHICLES & PERSONNEL: YES ____ NO _X___

If YES is checked above, provide additional information including location of blockage, how access will be obstructed, and the anticipated duration of the impairment.

5. INTEGRITY OF SMOKE &/OR FIRE COMPARTMENTS: YES ____ NO _X___

If YES is checked above, provide additional information including size, location, number, and purpose of penetrations, which will be made.

_____________________________ 06/20/2024 Person responsible for construction projects Date And/or activities, including work/projects

________________________________ 06/20/2024 Service/Section Chief Date

Attachment C

OCCUPANT IMPACT EVALUATION WORKSHEET

DESCRIPTION OF LSC DEFICIENCY OR CONSTRUCTION PROJECT:

SIGNAGE

1. Will the above described LSC deficiency or construction project hinder the occupants in the immediate area from effectively implementing RESCUE?

YES ____ NO ____

If YES is checked above, will the condition described exist for more than one working day?

YES ____ NO ____

If the condition will exist for more than one working day, signage must be prepared and posted informing the occupants of the compromise of safety and directing a higher level of awareness of fire hazards.

SIGNS POSTED BY: ______________________________ DATE: __________

2. Will the above described LSC deficiency or construction project hinder the occupants in the immediate area from effectively activating a pull station fire ALARM?

YES ____ NO ____

If YES is checked above after question 2, will the condition described exist for more than one working day?

YES ____ NO ____

If the condition will exist for more than one working day, signage must be prepared and posted informing the occupants that the fire alarm pull station is out of service and instructing the occupants to call the Hines Police Department by telephone at extension 22323 to report a fire.

SIGNS POSTED BY: _____________________________ DATE: __________

3. Will the above described LSC deficiency or construction project hinder the ability of the occupants in the immediate area to CONFINE a fire?

YES ____ NO ____

If YES is checked above, will the condition described exist for more than one working day?

YES ____ NO ____

If the condition will exist for more than one working day, signage must be prepared and posted informing the occupants of the condition and listing alternative actions to be taken until the condition is remediated.

SIGNS POSTED BY: ______________________________ DATE: __________

4. Will the above described LSC deficiency or construction project reduce or hinder the ability of the occupants in the immediate area or the community Fire Department to EXTINGUISH a fire?

YES ____ NO ____

If YES is checked above, will the condition described exist for more than one working day?

YES ____ NO ____

If the condition will exist for more than one working day, signage must be prepared and posted informing the occupants of the condition and listing alternative actions to be taken until the condition is remediated. Additionally, the community Fire Department will develop a contingency firefighting tactical plan for the area. In the case of construction projects, that contingency plan must be approved and in place prior to permitting any work to start at the job site.

SIGNS POSTED BY: _______________________________ DATE: ________

5. Will the above described LSC deficiency or construction project hinder the occupants’ ability to EVACUATE the building or area?

YES ____ NO ____

If YES is checked above, will the condition described exist for more than one working day?

YES ____ NO ____

If the condition will exist for more than one working day, signage must be prepared and posted advising the occupants of the condition and describing alternate routes of egress.

SIGNS POSTED BY: _____________________________ DATE: ________

TRAINING

6. Does the ILSM signage pertaining to RESCUE provide sufficient information and instruction in itself to ensure proper occupant response during an emergency incident?

YES ____ NO ____

If the signage is determined to be inadequate to ensure proper occupant response, Safety will provide the personnel affected with additional instruction and training as necessary. Such training will be documented.

TRAINING CONDUCTED BY: _________________________ DATE: __________

7. Does the ILSM signage pertaining to ALARM provide sufficient information and instruction in itself to ensure proper occupant response during an emergency incident?

YES ____ NO ____

If the signage is determined to be inadequate to ensure proper occupant response, Safety will provide the personnel affected with additional instruction and training as necessary. Such

8. Does the ILSM signage pertaining to CONFINE provide sufficient information and instruction in itself to ensure proper occupant response during an emergency situation?

YES ____ NO ____

If the signage is determined to be inadequate to ensure proper occupant response, Safety will provide the personnel affected with additional instruction and training as necessary. Such

9. Does the ILSM signage pertaining to EVACUATE provide sufficient information and instruction in itself to ensure proper occupant response during an emergency situation?

YES ____ NO ____

If the signage is determined to be inadequate to ensure proper occupant response, Project/Planning will provide the personnel affected with additional instruction and training as necessary. Such training will be documented.

FIRE DRILLS

10. Will the above described LSC deficiency or construction project necessitate altering staff response to RESCUE, ALARM, CONFINEMENT, EXTINGUISHMENT and/or

EVACUATION?

YES ____ NO ____

If YES is checked above, will condition exist for more than sixty days?

YES ____ NO ____

If staff response to Rescue, Alarm, Confinement, Extinguishment and/or Evacuation will be altered for more than sixty days, the Safety Section will increase the frequency of scheduled fire drills in the area affected to two per shift per quarter.

ADDITIONAL FIRE DRILLS SCHEDULED BY: _________________ DATE: _______

INSPECTION

If evaluation indicates that one or more ILSMs must be used for this deficiency or project, daily inspection of the site by Safety personnel will be required. Each inspection must be documented on the ILSM High Hazard Inspection Report.

INSPECTION REQUIRED: YES ____ NO ____

INSPECTION SCHEDULED BY: __________________________ DATE: _______

EVALUATION COMPLETED BY:

SIGNATURE OF SAFETY STAFF DATE

Attachment D

HIGH HAZARD INSPECTION REPORT

LOCATION: ______________________________________________

DESCRIPTION OF DEFICIENCY OR PROJECT: ____________________________________

ILSMs REQUIRED: ___________________________________________________

YES NO

1. Is the ability of the occupants to perform rescue impaired? ____ ____

2. Is the ability of the occupants to activate an alarm impaired? ____ ____

3. Is the ability of the occupants to confine a fire impaired? ____ ____

4. Is the ability of the occupants to extinguish a fire impaired? ____ ____

5. Is the ability of the occupant to perform evacuation impaired? ____ ____

6. Is access to emergency vehicles/personnel impaired? ____ ____

7. Is the automatic fire sprinkler system in operation? ____ ____

8. Are the smoke detectors operating? ____ ____

9. Are flammable or combustible materials stored in the area? ____ ____

10. Is the area clear of storage, trash, waste and debris? ____ ____

REMARKS/CORRECTION ACTION REQUIRED: ___________________________________

SIGNATURE OF INSPECTOR DATE

Attachment E

November 25, 2014

Fire Watch Decision Grid

Service Situation Fire Watch Required?

ILSM Evaluation Required?

A. Putting a shield over one smoke detector to prevent dust/false alarms for more than 4 hours

Rationale: Other features of fire protection are not compromised during the event, such as additional smoke detectors or sprinkler heads in the affected area.

B. Covering all smoke detectors during a controlled event, such as only during the time contractors are working in an affected area, although after hours the entire area is fully operational

Rationale: During a controlled event, the organization would be managing the deficiency. The area would be continually monitored, and ILSM should be implemented as per policy

C. Shutting off a zone valve to the sprinkler system or disabling a fire alarm zone for more than 4 hours

• Scheduled event (that is, working on, servicing, or upgrading fire alarm system or sprinkler system)

Rationale: During a controlled event, the organization would be managing the deficiency. The area would be continually monitored, and ILSM would be implemented as per policy.

• Unscheduled event (that is, shutting off a zone valve to the sprinkler system or disabling a smoke zone for more than 4 hours in response to a system failure)

INTERIM LIFE SAFETY MEASURES

2024-06-20T06:41:53-0500
CHARLES SMITH
2024-06-20T07:29:37-0500
LAWRENCE DOYLE

File details come from the government source that posted it. Updated .