ROHS Window Replacement Addendum #2.pdf

PDF 252 KB Posted

Attached to
Window Replacement
Solicitation number
RFP ROY 210000000392 3
Issued by
Macomb County, Michigan

About this file

This is an addendum to a window replacement project for Royal Oak High School managed by Royal Oak Schools in Michigan. The project involves replacing windows at the school facility, with a bid due date of Thursday, December 17, 2020 at 11:00 AM local time. Prospective bidders may schedule site visits by contacting Mark Paulus at mark.paulus@royaloakschools.org or (248) 880-6791; appointments are mandatory and unscheduled building visits are not permitted. Questions regarding the project should also be directed to Mark Paulus through the same contact information.

The addendum addresses several clarifications requested by bidders. Specification section 122400 requires providers to include a fascia rather than a ceiling pocket. The bond warranty period is eighteen months, and the additional insured parties are identified as TMP Architecture and Lecole Planners. Payment and performance bonds are structured as single obligee rather than dual obligee arrangements.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM 2

Project: Royal Oak High School – Window Replacement

Bid Due date: Thursday, December 17, 2020 at 11:00 AM Local Time (unchanged)

I. General Information

1. For questions contact Mark Paulus at mark.paulus@royaloakschools.org or (248) 880-

6791.

2. Any bidder wanting to visit the site, contact Mark Paulus at mark.paulus@royalschools.org or (248) 880-6791 to schedule a time. Bidders are not allowed to visit the building without an appointment.

II. Questions and Answers

1Q. In specification section 122400, article 2.02B.6a calls for a fascia and in article 2.02B.6c calls for a ceiling pocket. Please advise which is correct.

1A. Please provide a fascia.

2Q. Can you provide confirm the bond warranty time period?

2A. Eighteen months.

3Q. Are there are any additional insured?

3A. The additional insured is TMP Architecture and Lecole Planners.

4Q. Are the payment and performance bonds dual oblige?

4A No.

END