RFQ_CDS250307_HVAC_Replacement_-_Robeson_1405_NW_19th_Ct_-_Exhibit_C_-__Work_Write-up.pdf
PDF 227 KB Posted
- Attached to
- HVAC Replacement - Robeson (1405 NW 19th Ct)
- Solicitation number
- RFQ# CDS/250307
- Issued by
- Marion County, Orlando City, Florida
About this file
The document is a Work Write-Up (Exhibit C) for a residential HVAC replacement project issued by the City of Ocala, Florida, under contract number CDS/250307 for a property located at 1405 NW 19th Ct. The project involves a comprehensive rehabilitation of the home's HVAC system, electrical infrastructure, and interior repairs, with a mandatory completion timeline of 60 days. The scope of work includes removing the existing HVAC system, installing a new 16 SEER2 electric heat pump system, upgrading the electrical meter and panel to 200-amp service, replacing smoke and CO alarms, and conducting necessary interior repairs and painting.
The estimated permit cost for the project is $200.00, and the contractor is required to submit a 3-ring binder at project closeout containing contractor information, warranties, owner manuals, and other documentation. The project will be awarded to the lowest bidder meeting all requirements, with the bid to be submitted on a lump sum basis that includes all direct and indirect costs. The work must comply with the current Florida Building Code, National Electrical Code (NEC), and Ocala Electric Utility standards, with all necessary permits to be obtained by the contractor and inspections to be coordinated with the City of Ocala Building Department.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit C – WORK WRITE-UP CONTRACT# CDS/250307
C - 1
Rehabilitation Specification: GRNT 23-0041
CRA:
Applicant: Gloria Robeson
Address: 1405 NW 19th Ct
Parcel #: 2196-002-010
Phone: 352-895-4057
Work must comply with the current Florida Building Code.
TYPES OF PERMITS REQUIRED:
Building Roofing Plumbing Electrical Mechanical Gas
CONTRACTORS REQUIRED:
General/Builder/Residential Roofing Plumbing Electrical HVAC Gas Specialty
The project must be fully completed in 60 days.
GENERAL CONDITIONS
1. It is the responsibility of the contractor and/or sub-contractors to obtain all required permits necessary to perform the work described above and to properly post/display them clearly at the job site.
2. It is also the responsibility of the contractors and sub-contractors to ensure all required inspections are requested and passed, up to and including the final inspections from the City of Ocala Building Department and the Community Development Services Department.
3. Due to this being an owner-occupied residence, the contractor MUST coordinate with the Owner and City of Ocala Building Department/Inspectors when requesting the necessary inspections for this project. (Owner may move out during construction.)
4. All references to equivalent imply the substituted goods/materials must meet or exceed the specifications of the brand requested.
Exhibit C – WORK WRITE-UP CONTRACT# CDS/250307
C - 2
23-
Item 1 – HVAC
1. Remove and properly dispose of existing HVAC system, Air Handler, Condenser Unit, Copper Lines and Condensate Pipe and pump, etc.
2. Drywall walls/ceiling in furnace closet. Or build closet in most suitable location. Line return air box with duct board. Closet in living room can be used, modify as needed.
3. Provide and install completely new, properly sized to home, electric Heat Pump Style HVAC System HVAC System, including ALL new copper Lines and Condensate pipes and condensate pump (if needed), pipe insulation and any other related components.
4. Install fresh air and return air as required by code.
5. Ensure that new condensate line empties a minimum of 12” away from the side walls of the home and is secured per code.
6. Provide and install new Thermostat wires for ALL new equipment. If electrical supplies and disconnects are sized properly to handle new system, they may be re-used, otherwise it will be the contractor’s responsibility to provide and install new electrical wiring and disconnects required for new HVAC Equipment.
7. Provide and install NEW Circuit Breakers for Air Handler, Heat Strips and Compressor where necessary.
8. New HVAC Unit MUST be a Minimum of 16 SEER2 and MUST be Energy Star Certified in Florida. Install emergency drain pan with float switch if needed (observed rust, mold, algae, etc.).
9. Replace all flex ducts and register boxes. All joint connections to be sealed with mastic (fiber reinforced, water-based, high-velocity duct sealant).
10. Check clean and sanitize existing metal ductwork. Repair/replace insulation as needed. All joint connections to be sealed with mastic (fiber reinforced, water-based, high-velocity duct sealant).
11. Provide and install a Secondary “wet” switch as a safety backup to the gravity condensate.
12. If existing Plenum Base is damaged, rotted or in any way deteriorated, provide and install ALL necessary materials to properly repair or rebuild the plenum with duct board or (if metal, then replace with metal).
13. Provide and install new standard filter box (if needed) and install new filter(s), minimum of MERV-5 Rating or better, in a readily accessible manner. Filter size should be common and readily available at any chain retail store such as Walmart. Install return air filter grille for filter.
14. Provide and install a new digital, Programable Thermostat, matched/compatible to new system. Owners’ thermostat can be used if functional. Ensure that new thermostat (if used) is designed to utilize the maximum functionality of the new HVAC systems’ capabilities (temperature and humidity control and programing) and Energy Efficiency.
15. Install new properly sized registers and returns as needed, throughout home and make all necessary repairs to home in all locations a component is removed or replaced.
16. If required by code or for permit, obtain and provide Energy Calculations and Manual D & J and AHRI Reports.
Exhibit C – WORK WRITE-UP CONTRACT# CDS/250307
C - 3
17. Copies of all documents, including Signed Energy Calculations, Manual D & J and AHRI Reports, Warranty Information, and ALL Paperwork required for any Energy Rebates that the owner may be eligible for must be made and provided to the Owner and Rehab Inspector at Rehab Final Inspection.
18. Provide the Owner with basic instructions on how to operate the new HVAC System / Thermostat, filter change schedule, and instruction on suggested service intervals.
19. Contractor shall repair/paint any areas damaged due to replacement.
20. Air handler shall be installed in the hall closet.
Item 2 – Interior Repairs
1) Repair all areas affected due to the HVAC/Electrical repairs back to original condition as necessary.
2) Provide and apply “Kilz” (equal or better) stain-resistant primer to all repaired areas and new and/or unpainted drywall as needed throughout.
3) Provide and apply 2 or more (if necessary), full-coverage coats of Sherwin-Williams ProMar 200 Zero VOC Interior Latex, equal or better. Match existing colors.
Item 3 – Electrical
1. Remove and properly dispose of existing Electrical Meter Enclosure.
2. Remove and properly dispose of existing, Main Feeder Wire from meter to interior breaker panel(s).
3. Provide and install new Meter Enclosure, mast, and weather head with separate or integrated
200-Amp Main Panel. Must meet all current NEC requirements as well as be compliant with the most current version of the Ocala Electric Utility’s “Metering Enclosure and Equipment Standards”.
4. Install new Main Disconnect, new Main Breaker(s) for Interior Sub-Distribution Panels (if required) and New Panel must have multiple open slots for exterior/added circuits (minimum 6) and any other current NEC compliant circuits required for the home, unless provided for in existing Interior Distribution Panels.
5. Provide and properly install new correctly sized for loads, Main Feeder Wire from exterior disconnect/breaker, through attic cavity, properly secured/protected per codes, to feed existing interior breaker panels.
6. If any other circuits need to be added/corrected to meet code or for proper function for owner, provide, and install all necessary components to bring into compliance.
7. Interior:
8. Install new interior electrical panel with appropriate GFCI/AFCI breakers.
9. Label panel as specific as possible to identify location for receptacles, lights, equipment, rooms, etc.
10. If Bathroom, Kitchen, or laundry outlets are not currently GFCI protected outlets/switches, provide and install all needed materials to change to GFCI/AFCI, outlets or breakers per code.
Exhibit C – WORK WRITE-UP CONTRACT# CDS/250307
C - 4
11. Exterior:
12. Install new HVAC disconnect and exterior GFCI outlet at condenser location, front and rear (if not installed).
13. Install general LED lighting/switch in laundry area.
14. Smoke/CO Alarms:
15. Remove and properly dispose of all old smoke alarms and mounting plates throughout the home.
16. Provide and install new CO/Smoke Combo Alarms, throughout home. Minimum, one Smoke
Alarm in each sleeping space and one Combo CO/Smoke Alarm in each common-area immediately adjacent to sleeping space(s), must have 10-year non-serviceable battery.
17. Existing locations where smoke alarms were previously located should be used, if possible, otherwise the old locations must be repaired and painted to “best match” of surrounding walls, texture and color.
18. Any devices requiring new wiring circuits/switches shall be included in the total price.
19. Any sub panels not needed can be removed.
20. Install necessary electrical circuits for a 16-seer2 electric heat pump HVAC system.
21. Contractor may be required to coordinate with other contractors during repairs.
Item P – Permits
This amount of __200.00________ is the estimated permit cost/allowance for this project.
At project closeout and before final payment, Contractor shall submit to homeowner, a 3-ring binder to include:
Prime Contractors information w/warranty
Sub-contractor information
Registered roof warranty and claim information
All owner manuals/instructions
Provide a list of the manufacturer, type, sheen/finish and color of all coatings used and the respective locations where they were applied, to the owner.
Color choices (all color/product choices and/or changes to previously agreed upon choices shall be done in writing)
Also, to project manager:
Final Payment Affidavit
Owner final acceptance of the work
Material and/or contractor lien releases