This is a sample AIA Document A133-2009 Standard Form of Agreement between Owner and Construction Manager as Constructor for the Waterside Construction Management at Risk (CMAR) Services contract (RFQ-26-3) issued by the Canaveral Port Authority, located in Cape Canaveral, Florida. The Construction Manager will provide both Preconstruction Phase and Construction Phase services for waterside facility projects including berths, piers, fender components, mooring dolphins and bollards, underwater inspections, and other port facilities. The contract is structured as a continuing services agreement with projects to be initiated by the Canaveral Port Authority as needed. The Preconstruction Phase includes preliminary evaluation of program requirements, project scheduling, cost estimating, design consultation, subcontractor selection and bidding, and preparation of a Guaranteed Maximum Price (GMP) proposal. The Construction Phase encompasses full construction management, administration, supervision, scheduling, cost control, and project completion. Contract completion timelines and specific project scopes are to be determined by individual projects. The contract term is five years with no renewal options specified in this sample document, and the Contract Sum for each individual and distinct project scope shall not exceed $2,000,000.
Compensation for Preconstruction Phase services will be determined based on direct personnel expense and other reimbursable costs to be specified in individual project agreements. For Construction Phase services, the Construction Manager will receive the Cost of the Work plus a combined fee not to exceed 15 percent of the Cost of the Work for performance of Construction Phase services and profit and overhead expenses, plus a not-to-exceed General Conditions cost to be determined by project. The Construction Manager's Fee includes no increases for overhead and profit for the five-year contract duration. The Construction Manager must prepare a GMP proposal subject to Owner acceptance, with a construction contingency fund to be established for each project. The Construction Manager is responsible for procuring all materials, labor, and subcontractors at standard market rates; all cash discounts, rebates, and trade discounts accrue to the Owner. Progress payments are due within 25 business days of invoice submission, with retainage not to exceed 10 percent initially, reduced to 5 percent after 50 percent completion. The Construction Manager must maintain a Payment and Performance Bond in an amount equal to the Contract Sum, issued by a Florida-authorized surety, and obtain Builders Risk Insurance. The contract is subject to Florida Statute 287.055 and the Local Government Prompt Payment Act (Florida Statutes 218.70 et seq.), with disputes to be resolved through negotiation, mediation, and litigation in Brevard County, Florida.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOTE: The following contract is provided for reference and planning purposes only. A final contract will be in substantially the same form but remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE CONSTRUCTION MANAGEMENT AT RISK SERVICES for CONTINUING SERVICES CONTRACT
RFQ-26-3
AIA
Document A133TM – 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price
AIA Document A133™ – 2009 (formerly A121™CMc – 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.
WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:47:05 on 04/28/2014 under Order No.1051200823 which expires on 03/20/2015, and is not for resale.
User Notes: (3B9ADA13)
ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.
AGREEMENT made as of the __ day of ________ in the year 2026 (the “Effective Date”) (In words, indicate day, month and year.)
BETWEEN the Owner:
(Name, legal status and address)
Canaveral Port Authority 445 Challenger Road, Suite 301 Cape Canaveral, Florida 32920 and the Construction Manager:
(Name, legal status and address) for the following Project:
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
RFQ-26-3
Cape Canaveral, Florida 32920
The Architect/Engineer:
To be determined by project
The Owner’s Designated Representative:
William E. (Bill) Crowe, P.E.
Vice President, Engineering and Construction 445 Challenger Road, Suite 301 Cape Canaveral, Florida 32920 Telephone: (321) 783-7831
The Construction Manager’s Designated Representative:
(Name, address and other information)
AIA Document A133™ – 2009 (formerly A121™CMc – 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.
WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:47:05 on 04/28/2014 under Order No.1051200823 which expires on 03/20/2015, and
User Notes: (3B9ADA13)
TABLE OF ARTICLES
1 GENERAL PROVISIONS
2 CONSTRUCTION MANAGER’S RESPONSIBILITIES
3 OWNER’S RESPONSIBILITIES
4 COMPENSATION AND PAYMENTS FOR PRECONSTRUCTION PHASE SERVICES
5 COMPENSATION FOR CONSTRUCTION PHASE SERVICES
6 COST OF THE WORK FOR CONSTRUCTION PHASE
7 PAYMENTS FOR CONSTRUCTION PHASE SERVICES
8 INSURANCE AND BONDS
9 DISPUTE RESOLUTION
10 TERMINATION OR SUSPENSION
11 MISCELLANEOUS PROVISIONS
12 SCOPE OF THE AGREEMENT
ARTICLE 1 GENERAL PROVISIONS
§ 1.1 The Contract Documents The Contract Documents form the Contract between the Owner and the Construction Manager for the Project. The Contract Documents consist of:
.1 this Agreement (AIA Document A133–2009, Standard Form of Agreement Between Owner and Construction Manager as Constructor) (the “Agreement”);
.2 General Conditions of the Contract (AIA Document A201–2007, Modified General Conditions of the Contract for Construction) [Exhibit “A”];
.3 Supplemental Conditions of the Construction Management Agreement [Exhibit “B”];
.4 Drawings, Specifications, Details, Addenda, and other documents prepared by the Architect/Engineer and accepted by the Owner prior to the execution of this Agreement;
.5 Insurance Addendum [Exhibit “C”];
.6 Construction Management Staff Addendum [Exhibit “D”];
.7 Owner Direct Purchase Program Addendum [Exhibit “E”];
.8 Payment and Performance Bond [Exhibit “F”];
.9 General Conditions Addendum [Exhibit “G”];
.10 Guaranteed Maximum Price Amendment;
.11 Public Entity Crime Affidavit [Exhibit “H”];
.12 Non-Collusion Affidavit [Exhibit “I”];
.13 FEMA Terms and Conditions
.14 the latest revision of all applicable local, state and national building codes and related codes, including, but not limited to, the Florida Building Code, Florida Fire Prevention Code, Florida Plumbing Code, Florida Mechanical Code, and National Building Code;
.15 Contract Forms, including Substantial Completion Form, Certificate of Final Payment, Application for Payment, Contingency Use Request, and Sales Tax Savings Use Request;
.16 all other documents listed in this Agreement;
.17 Request for Qualifications number RFQ-26-3;
.18 Construction Manager’s Qualifications Proposal;
AIA Document A133™ – 2009 (formerly A121™CMc – 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.
WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:47:05 on 04/28/2014 under Order No.1051200823 which expires on 03/20/2015, and
User Notes: (3B9ADA13)
.19 the following items delivered, prepared, or issued after the Effective Date of this Agreement: Notice to Proceed with Preconstruction Phase Services, Notice to Proceed with Construction Phase Services; and
.20 all written Modifications issued after execution of this Agreement.
Upon the Owner’s acceptance of the Construction Manager’s Guaranteed Maximum Price proposal, the Contract Documents will also include the documents described in Section 2.2.3 and identified in the Guaranteed Maximum Price Amendment and revisions prepared by the Architect/Engineer and furnished by the Owner as described in Section 2.2.8. All of the foregoing documents and items form the Contract and are as fully a part of the Contract as if attached to this Agreement or repeated herein. Unless otherwise agreed by the Owner and Construction Manager in writing, documents not included or expressly contemplated in this Section do not form any part of the Contract Documents. Without limiting the generality of the foregoing, shop drawings and other submittals from the Construction Manager or its Subcontractors or Suppliers of any tier do not constitute part of the Contract Documents.
If anything in the other Contract Documents, other than a Modification, is inconsistent with this Agreement, this Agreement shall govern.
§ 1.1.1 The Contract Documents are to be interpreted to include all items necessary for the proper, complete, and timely performance of the Work and construction of the Project. Work that is reasonably inferable from the Contract Documents will be required if it is consistent with the intent of the Contract Documents.
§ 1.2 Relationship of the Parties The Construction Manager accepts the relationship of trust and confidence established by this Agreement and covenants with the Owner to cooperate in all respects with the Owner and Architect/Engineer and exercise the Construction Manager’s best skill, ability, and judgment in furthering the interests and objectives of the Owner and the Project; to furnish efficient construction administration, management services and supervision; to furnish at all times an adequate supply of workers and materials; and to perform the Work in an expeditious and economical manner consistent with the Owner’s interests. The Owner agrees to furnish or approve, in a timely manner, information required by the Construction Manager and to make payments to the Construction Manager in accordance with the requirements of the Contract Documents. The Construction Manager expressly acknowledges that, except as expressly set forth otherwise herein, it is an independent contractor and that it is not the representative or agent of the Owner.
§ 1.3 General Conditions of the Contract Any referenced herein or in the Contract Documents to “AIA Document A201™–2007”, “A201™–2007”, “AIA Document A201–2007”or “A201–2007” shall refer to AIA Document A201™–2007, Modified General Conditions of the Contract for Construction that is part of the Contract Documents. For the Preconstruction Phase, AIA Document A201™–2007, General Conditions of the Contract for Construction, shall apply only as specifically provided in this Agreement. For the Construction Phase, the general conditions of the contract shall be as set forth in A201–2007, which document is incorporated herein by reference. The term “Contractor” as used in A201–2007 shall mean the Construction Manager.
ARTICLE 2 CONSTRUCTION MANAGER’S RESPONSIBILITIES
The Construction Manager has the overall responsibility for and shall furnish to the Owner the complete Pre-Construction Phase and Construction Phase Services necessary for the timely completion of the Work on the Project in strict accordance with the Contract Documents. The Construction Manager shall perform services specifically allocated to it by the Contract Documents, as well as those services reasonably inferable from the Contract Documents. The Construction Manager’s Preconstruction Phase responsibilities are set forth in Sections 2.1 and 2.2.
The Construction Manager’s Construction Phase responsibilities are set forth in Section 2.3. The Owner and Construction Manager may agree, in consultation with the Architect/Engineer, for the Construction Phase to commence prior to completion of the Preconstruction Phase, in which case, both phases will proceed concurrently.
The Construction Manager shall identify a representative authorized to act on behalf of the Construction Manager with respect to the Project.
§ 2.1 Preconstruction Phase § 2.1.1 The Construction Manager shall provide a preliminary evaluation of the Owner’s program, Project schedule and construction budget requirements, each in terms of the other.
AIA Document A133™ – 2009 (formerly A121™CMc – 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.
WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:47:05 on 04/28/2014 under Order No.1051200823 which expires on 03/20/2015, and
User Notes: (3B9ADA13)
§ 2.1.2 Consultation The Construction Manager shall schedule and conduct meetings with the Architect/Engineer and Owner to discuss such matters as planning, procedures, progress, coordination, and scheduling of the Work. The Construction Manager shall advise the Owner and the Architect/Engineer on proposed site use and improvements, conditions in the construction market, selection of materials, building systems and equipment, and identification of Owner Direct Purchase items. The Construction Manager shall also provide information and recommendations consistent with the Project requirements to the Owner and Architect/Engineer on constructability; availability of materials, labor, and equipment; prospective bidders; time requirements for procurement, installation and construction; and factors related to construction cost including, but not limited to, costs of alternative designs or materials, preliminary budgets, life-cycle data, and possible cost reductions. From time to time, as the Architect/Engineer or the Owner may reasonably request, the Construction Manager shall submit to the Architect/Engineer and the Owner a written report detailing the Construction Manager’s knowledge, analysis, recommendations and suggestions concerning the matters referenced within this subsection.
§ 2.1.2.1 The Construction Manager shall review the design, including plans and specifications, and Construction Documents with the Architect/Engineer and make recommendations to the Owner and the Architect/Engineer with respect to dividing the Work in such manner as will permit the Construction Manager to take bids and award separate construction subcontracts. The Construction Manager shall take into consideration such factors as natural and practical lines of severability, sequencing effectiveness, access and availability constraints, total time for completion, construction market conditions, availability of labor and materials, community relations and any other factors pertinent to saving time and cost by overlapping design and construction that are authorized by the Owner.
§ 2.1.3 When Project requirements in Section 3.1.1 have been sufficiently identified, the Construction Manager shall prepare and periodically update a Project Schedule for the Architect/Engineer’s review and the Owner’s acceptance.
The Construction Manager shall obtain the Architect/Engineer’s approval for the portion of the Project Schedule relating to the performance of the Architect/Engineer’s services. The Project Schedule shall coordinate and integrate the Construction Manager’s services, the Architect/Engineer’s services, other Owner consultants’ services, and the Owner’s responsibilities and identify items that could affect the Project’s timely completion. The updated Project Schedule shall include the following: submission of the Guaranteed Maximum Price proposal; components of the Work; times of commencement and completion required of each Subcontractor; ordering and delivery of products, including those that must be ordered well in advance of construction; and the occupancy requirements of the Owner.
§ 2.1.4 Phased Construction The Construction Manager shall provide recommendations with regard to accelerated or fast-track scheduling, procurement, or phased construction. The Construction Manager shall take into consideration cost reductions, cost information, constructability, provisions for temporary facilities and procurement and construction scheduling issues.
§ 2.1.5 Preliminary Cost Estimates § 2.1.5.1 Based on the preliminary design and other design criteria prepared by the Architect/Engineer, the Construction Manager shall prepare preliminary estimates of the Cost of the Work or the cost of program requirements using the unit quantity survey estimating method for the Architect/Engineer’s review and Owner’s approval. If the Architect/Engineer or Construction Manager suggests alternative materials and systems, the Construction Manager shall provide cost evaluations of those alternative materials and systems. The Construction Manager shall reconcile its estimate with any available estimate of the Cost of the Work and/or Project budget prepared by the Architect/Engineer or the Owner. If the Construction Manager’s estimate exceeds the Owner’s construction budget, the Construction Manager shall detail and propose alternatives and scope reductions to reduce the estimate within the Owner’s construction budget.
§ 2.1.5.2 As the Architect/Engineer progresses with the preparation of the Schematic Design, Design Development and Construction Documents, the Construction Manager shall prepare and update, at appropriate intervals agreed to by the Owner, Construction Manager and Architect/Engineer, estimates of the Cost of the Work of increasing detail and refinement and allowing for the further development of the design until such time as the Owner and Construction Manager agree on a Guaranteed Maximum Price for the Work. Such estimates shall be provided for the Architect/Engineer’s review and the Owner’s approval. The Construction Manager shall inform the Owner and Architect/Engineer when estimates of the Cost of the Work exceed the latest approved Project budget and make recommendations for corrective action.
AIA Document A133™ – 2009 (formerly A121™CMc – 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.
WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:47:05 on 04/28/2014 under Order No.1051200823 which expires on 03/20/2015, and
User Notes: (3B9ADA13)
§ 2.1.6 Subcontractors and Suppliers The Construction Manager shall develop bidders’ interest in the Project, identify and encourage bidding competition, familiarize bidders with the requirements of the Project, including, but not necessarily limited to, advertising and conducting and attending meetings with prospective bidders and giving recommendations on the clarification of responsibilities of prospective bidders, and pre-qualify prospective bidders. The Construction Manager shall solicit and enter into all subcontracts as are necessary to ensure that the Work is timely and successfully performed and completed in strict accordance with the Contract Documents.
§ 2.1.6.1 The Construction Manager shall take such measures as are appropriate to provide that all construction requirements will be covered in the separate subcontracts, as necessary, and that the Work of the separate subcontracts and the general conditions Work items are performed without duplication or overlap and sequenced to maintain completion of all Work in accordance with the Project Schedule and the Contract Time.
§ 2.1.7 The Construction Manager shall prepare, for the Architect/Engineer’s review and the Owner’s acceptance, a procurement schedule for items that must be ordered well in advance of construction. The Construction Manager shall expedite and coordinate the ordering and delivery of materials that must be ordered well in advance of construction. If the Owner agrees to procure any items prior to the establishment of the Guaranteed Maximum Price, the Owner shall procure the items on terms and conditions acceptable to the Construction Manager. Upon the establishment of the Guaranteed Maximum Price, the Owner shall assign all contracts for these items to the Construction Manager and the Construction Manager shall thereafter accept responsibility for them.
§ 2.1.8 Extent of Responsibility The Construction Manager shall exercise reasonable care in preparing schedules and estimates. The Construction Manager, however, does not warrant or guarantee estimates and schedules except as may be included as part of the Guaranteed Maximum Price. The Construction Manager is not required to ascertain that the Drawings and Specifications are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the Construction Manager shall promptly report to the Architect/Engineer and Owner any nonconformity discovered by or made known to the Construction Manager as a request for information in such form as the Architect/Engineer may require.
§ 2.1.9 Notices and Compliance with Laws The Construction Manager shall comply with applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public authorities applicable to its performance under the Contract Documents, and with equal employment opportunity programs, and other programs as may be required by governmental and quasi-governmental authorities for inclusion in the Contract Documents.
§ 2.2 Guaranteed Maximum Price Proposal and Contract Time § 2.2.1 At a time to be mutually agreed upon by the Owner and the Construction Manager and in consultation with the Architect/Engineer, the Construction Manager shall prepare a Guaranteed Maximum Price proposal for the Owner’s review and acceptance. The Guaranteed Maximum Price in the proposal shall be the sum of the Construction Manager’s estimate of the Cost of the Work, including contingencies described in Section 2.2.4, and the Construction Manager’s Fee.
§ 2.2.2 To the extent that the Drawings and Specifications are anticipated to require further development by the Architect/Engineer, the Construction Manager shall provide in the Guaranteed Maximum Price for such further development consistent with the Contract Documents and reasonably inferable therefrom. Such further development does not include such things as changes in scope, systems, kinds and quality of materials, finishes or equipment, all of which, if required, shall be incorporated by Change Order.
§ 2.2.3 The Construction Manager shall include with the Guaranteed Maximum Price proposal a written statement of its basis, which shall include the following:
.1 A list of the Drawings and Specifications, including all Addenda thereto, and the Conditions of the Contract;
.2 A list of the clarifications and assumptions made by the Construction Manager in the preparation of the Guaranteed Maximum Price proposal, including assumptions under Section 2.2.2, to supplement the information provided by the Owner and contained in the Drawings and Specifications;
AIA Document A133™ – 2009 (formerly A121™CMc – 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.
WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:47:05 on 04/28/2014 under Order No.1051200823 which expires on 03/20/2015, and
User Notes: (3B9ADA13)
.3 A statement of the proposed Guaranteed Maximum Price, including a statement of the estimated Cost of the Work organized by trade categories or systems, allowances, contingency, and the Construction Manager’s Fee;
.4 The anticipated date of Substantial Completion upon which the proposed Guaranteed Maximum Price is based; and
.5 A date by which the Owner must accept the Guaranteed Maximum Price.
§ 2.2.4 In preparing the Construction Manager’s Guaranteed Maximum Price proposal, the Construction Manager shall include its contingency for the Construction Manager’s exclusive use to cover those costs considered reimbursable as the Cost of the Work but not included in a Change Order.
§ 2.2.5 The Construction Manager shall meet with the Owner and Architect/Engineer to review the Guaranteed Maximum Price proposal. In the event that the Owner and Architect/Engineer discover any inconsistencies or inaccuracies in the information presented, they shall promptly notify the Construction Manager, who shall make appropriate adjustments to the Guaranteed Maximum Price proposal, its basis, or both.
§ 2.2.6 If the Owner notifies the Construction Manager that the Owner has accepted the Guaranteed Maximum Price proposal in writing before the date specified in the Guaranteed Maximum Price proposal, the Guaranteed Maximum Price proposal shall be deemed effective without further acceptance from the Construction Manager. Following acceptance of a Guaranteed Maximum Price, the Owner and Construction Manager shall execute the Guaranteed Maximum Price Amendment amending this Agreement, a copy of which the Owner shall provide to the Architect/Engineer. The Guaranteed Maximum Price Amendment shall set forth the agreed upon Guaranteed Maximum Price with the information and assumptions upon which it is based.
§ 2.2.7 The Construction Manager shall not incur any cost to be reimbursed as part of the Cost of the Work prior to the commencement of the Construction Phase, unless the Owner provides prior written authorization for such costs.
§ 2.2.8 The Owner shall authorize the Architect/Engineer to provide the revisions to the Drawings and Specifications to incorporate the agreed-upon assumptions and clarifications contained in the Guaranteed Maximum Price Amendment. The Owner shall promptly furnish those revised Drawings and Specifications to the Construction Manager as they are revised. The Construction Manager shall notify the Owner and Architect/Engineer of any inconsistencies between the Guaranteed Maximum Price Amendment and the revised Drawings and Specifications.
§ 2.2.9 The Construction Manager shall include in the Guaranteed Maximum Price all sales, consumer, use and similar taxes for the Work provided by the Construction Manager that are legally enacted, whether or not yet effective, at the time the Guaranteed Maximum Price Amendment is executed.
§ 2.3 Construction Phase § 2.3.1 General § 2.3.1.1 For purposes of Section 8.1.2 of A201–2007, the date of commencement of the Work shall mean the date of commencement of the Construction Phase.
§ 2.3.1.2 The Construction Phase shall commence upon the Owner’s acceptance of the Construction Manager’s Guaranteed Maximum Price proposal or the Owner’s issuance of a Notice to Proceed with Construction Phase services, whichever occurs earlier. Upon the commencement of the Construction Phase, the Construction Manager shall promptly and diligently proceed with the performance of the Work to achieve the Contract Time as set forth in the Contract Documents.
§ 2.3.1.3 The Construction Manager shall achieve Substantial Completion of the Work within _____ (to be determined by project) days after the date of commencement of the Construction Phase, or within such further time, if any, as may be allowed for time extensions authorized by a Change Order in accordance with the Contract Documents. The Construction Manager shall achieve Final Completion of the Work within ____ (to be determined by project) days after Substantial Completion, or within such further time, if any, as may be allowed for time extensions authorized by a Change Order in accordance with the Contract Documents.
AIA Document A133™ – 2009 (formerly A121™CMc – 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.
WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:47:05 on 04/28/2014 under Order No.1051200823 which expires on 03/20/2015, and
User Notes: (3B9ADA13)
§ 2.3.2 Administration § 2.3.2.1 Those portions of the Work that the Construction Manager does not customarily perform with the Construction Manager’s own personnel shall be performed under subcontracts or by other appropriate agreements with the Construction Manager. The Owner may designate specific persons from whom, or entities from which, the Construction Manager shall obtain bids. In accordance with section 1.2.2 of the Supplemental Conditions, the Construction Manager shall obtain bids from Subcontractors and from Suppliers of materials or equipment fabricated especially for the Work and shall deliver such bids to the Architect/Engineer.
§ 2.3.2.2 If the Guaranteed Maximum Price has been established and when a specific bidder (1) is recommended to the Owner by the Construction Manager, (2) is qualified to perform that portion of the Work, and (3) has submitted a bid that conforms to the requirements of the Contract Documents without reservations or exceptions, but the Owner requires that another bid be accepted, then the Construction Manager may require that a Change Order be issued to adjust the Contract Time and the Guaranteed Maximum Price by the difference between the bid of the person or entity recommended to the Owner by the Construction Manager and the amount and time requirement of the subcontract or other agreement actually signed with the person or entity designated by the Owner.
§ 2.3.2.3 Subcontracts or other agreements shall conform to the applicable payment provisions of this Agreement, and shall not be awarded on the basis of cost plus a fee without the prior consent of the Owner. If the Subcontract is awarded on a cost-plus a fee basis, the Construction Manager shall provide in the Subcontract for the Owner to receive the same audit rights with regard to the Subcontractor as the Owner receives with regard to the Construction Manager in Section 6.11 below.
§ 2.3.2.4 If the Construction Manager recommends a specific bidder that may be considered a “related party” according to Section 6.10, then the Construction Manager shall promptly notify the Owner in writing of such relationship and notify the Owner of the specific nature of the contemplated transaction, according to Section 6.10.2.
§ 2.3.2.5 The Construction Manager shall schedule and conduct meetings to discuss such matters as procedures, progress, coordination, scheduling, and status of the Work. The Construction Manager shall prepare and promptly distribute minutes to the Owner and Architect/Engineer.
§ 2.3.2.6 Upon the execution of the Guaranteed Maximum Price Amendment, the Construction Manager shall prepare and submit to the Owner and Architect/Engineer a Project Schedule for the Work and submittal schedule in accordance with Section 3.10 of A201–2007 and the Supplemental Conditions.
§ 2.3.2.7 The Construction Manager shall record the progress of the Project. On a monthly basis, or otherwise as agreed to by the Owner, the Construction Manager shall submit written progress reports to the Owner and Architect/Engineer, showing percentages of completion and other information required by the Owner. The Construction Manager shall also keep, and make available to the Owner and Architect/Engineer, a daily log containing a record for each day of weather, portions of the Work in progress, number of workers on the Project site, identification of equipment on the Project site, problems that might affect progress of the work, accidents, injuries, and other information required by the Owner.
§ 2.3.2.8 The Construction Manager shall develop a system of cost control for the Work, including regular monitoring of actual costs for activities in progress and estimates for uncompleted tasks and proposed changes. The Construction Manager shall identify variances between actual and estimated costs and report the variances to the Owner and Architect/Engineer and shall provide this information in its monthly reports to the Owner and Architect/Engineer, in accordance with Section 2.3.2.7 above.
§ 2.4 Professional Services Section 3.12.10 of A201–2007 shall apply to both the Preconstruction and Construction Phases.
§ 2.5 Hazardous Materials Section 10.3 of A201–2007 shall apply to both the Preconstruction and Construction Phases.
AIA Document A133™ – 2009 (formerly A121™CMc – 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.
WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:47:05 on 04/28/2014 under Order No.1051200823 which expires on 03/20/2015, and
User Notes: (3B9ADA13)
ARTICLE 3 OWNER’S RESPONSIBILITIES
§ 3.1 Information and Services Required of the Owner § 3.1.1 The Owner shall provide information with reasonable promptness, regarding requirements for and limitations on the Project, including a written program which shall set forth the Owner’s objectives, constraints, and criteria, including schedule, space requirements and relationships, flexibility and expandability, special equipment, systems, sustainability and site requirements.
§ 3.1.2 Prior to the execution of the Guaranteed Maximum Price Amendment, the Construction Manager may request in writing that the Owner provide reasonable evidence that the Owner has made financial arrangements to fulfill the Owner’s obligations under the Contract. Thereafter, the Construction Manager may only request such evidence if: (1) the Owner fails to make payments to the Construction Manager as the Contract Documents require, (2) a change in the Work materially changes the Contract Sum, or (3) the Construction Manager identifies in writing a reasonable concern regarding the Owner’s ability to make payment when due.
§ 3.1.3 The Owner shall establish and periodically update an overall budget for the Project, based on consultation with the Construction Manager and the Architect/Engineer, which budget shall include (1) Cost of the Work, (2) the Owner’s other costs, and (3) reasonable contingencies related to all of these costs.
§ 3.1.4 Structural and Environmental Tests, Surveys and Reports. During the Preconstruction Phase, the Owner shall furnish the following information or services with reasonable promptness. The Owner shall also furnish any other information or services under the Owner’s control and relevant to the Construction Manager’s performance of the Work with reasonable promptness after receiving the Construction Manager’s written request for such information or services. Except as otherwise specifically provided in the Contract Documents or to the extent the Owner advises the Construction Manager to the contrary in writing, the Construction Manager shall be entitled to rely on the accuracy of information and services furnished by the Owner but shall exercise proper precautions relating to the safe performance of the Work.
§ 3.1.4.1 The Owner shall furnish tests, inspections and reports required by law and as otherwise agreed to by the parties, such as structural, mechanical, and chemical tests, tests for air and water pollution, and tests for hazardous materials.
§ 3.1.4.2 The Owner shall furnish surveys describing physical characteristics, legal limitations and utility locations for the site of the Project, and a legal description of the Project site.
§ 3.1.4.3 The Owner, when such services are requested and necessary, shall furnish services of geotechnical engineers, which may include but are not limited to test borings, test pits, determinations of soil bearing values, percolation tests, evaluations of hazardous materials, seismic evaluation, ground corrosion tests and resistivity tests, including necessary operations for anticipating subsoil conditions, with written reports and appropriate recommendations.
§ 3.1.4.4 During the Construction Phase, the Owner shall furnish information or services required of the Owner by the Contract Documents with reasonable promptness. The Owner shall also furnish any other information or services under the Owner’s control and relevant to the Construction Manager’s performance of the Work with reasonable promptness after receiving the Construction Manager’s written request for such information or services.
§ 3.2 Owner’s Designated Representative The Owner shall identify a representative authorized to act on behalf of the Owner with respect to the Project. The Owner’s representative shall render decisions promptly and furnish information expeditiously, so as to avoid unreasonable delay in the services or Work of the Construction Manager. Except as otherwise provided in Section
4.2.1 of A201–2007, the Architect/Engineer does not have such authority. The term “Owner” means the Owner or the Owner’s authorized representative.
§ 3.2.1 Legal Requirements. The Owner shall furnish all legal and accounting services, including auditing services, that may be reasonably necessary at any time for the Project to meet the Owner’s needs and interests.
§ 3.3 Architect/Engineer The Owner shall retain an Architect/Engineer to provide design services, including the preparation of Drawings and Specifications for the Project. The Architect/Engineer’s services, duties and responsibilities as described in the
AIA Document A133™ – 2009 (formerly A121™CMc – 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.
WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:47:05 on 04/28/2014 under Order No.1051200823 which expires on 03/20/2015, and
User Notes: (3B9ADA13)
Agreement Between Owner and Architect/Engineer, including any additional services requested by the Construction Manager that are necessary for the Preconstruction and Construction Phase services under this Agreement. The Owner shall provide the Construction Manager a copy of the executed agreement between the Owner and the Architect/Engineer, and any further modifications to that agreement.
ARTICLE 4 COMPENSATION AND PAYMENTS FOR PRECONSTRUCTION PHASE SERVICES
§ 4.1 Compensation § 4.1.1 For the Construction Manager’s Preconstruction Phase services, the Owner shall compensate the Construction Manager as follows:
§ 4.1.2 For the Construction Manager’s Preconstruction Phase services described in Sections 2.1 and 2.2:
(Insert amount of, or basis for, compensation and include a list of reimbursable cost items, as applicable.)
§ 4.1.3 If the Preconstruction Phase services covered by this Agreement have not been completed within N/A months of the date of this Agreement, through no fault of the Construction Manager, the Construction Manager’s compensation for Preconstruction Phase services shall be equitably adjusted.
§ 4.1.4 Compensation based on Direct Personnel Expense includes the direct salaries of the Construction Manager’s personnel providing Preconstruction Phase services on the Project and the Construction Manager’s costs for the mandatory and customary contributions and benefits related thereto, such as employment taxes and other statutory employee benefits, insurance, sick leave, holidays, vacations, employee retirement plans and similar contributions.
§ 4.2 Payments § 4.2.1 Unless otherwise agreed, payments for services shall be made monthly in proportion to services performed.
§ 4.2.2 Payments are due and payable upon presentation of the Construction Manager’s invoice to the Architect/Engineer. Amounts unpaid by the twenty-fifth (25th) business day after the Construction Manager’s Application for Payment is received by the Architect/Engineer shall bear interest at the rate entered below, or in the absence thereof at the legal rate prevailing from time to time at the principal place of business of the Construction Manager.
one percent (1%) per month
ARTICLE 5 COMPENSATION FOR CONSTRUCTION PHASE SERVICES
§ 5.1 In consideration of the Construction Manager’s faithful, complete, and timely performance of the Work as described in Section 2.3 and the covenants of this Agreement and all Contract Documents to the full satisfaction and acceptance of the Owner, the Owner shall pay the Construction Manager the Contract Sum in current funds as determined by each project. The Contract Sum is the Cost of the Work as defined in Section 6.1.1 plus the Construction Manager’s Fee, subject to the limitation on the Contract Sum by the Guaranteed Maximum Price. Per Florida Statute 287.055, under no circumstances shall the Contract Sum exceed $2,000.000.00 US for each individual and distinct project scope performed under this contract.
§ 5.1.1 The Construction Manager’s Fee:
A combined fee of not to exceed percent (15%) of the Cost of the Work for the performance of the Construction Phase services and for profit and overhead expenses, plus a not-to-exceed cost of $ TBD (to be determined by project) for the performance of General Conditions Items as set forth in the Exhibit D – Construction Manager’s Staff Addendum.
There shall be no increase allowed for the combined fee percentage for overhead and profit for the duration of the contract, up to five (5) years.
The Construction Manager’s Fee constitutes compensation for the performance of all of the Construction Manager’s obligations for the Project pursuant to the Contract Documents, including, without limitation, all profit, overhead (including principal, branch and home office overhead), and risk and expenses not specifically included in the Cost of the Work. The amount of the Construction Manager’s Fee to be included in the Construction Manager’s monthly Application for Payment and paid by the Owner shall be proportional to the percentage of the Work completed, less
AIA Document A133™ – 2009 (formerly A121™CMc – 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.
WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:47:05 on 04/28/2014 under Order No.1051200823 which expires on 03/20/2015, and
User Notes: (3B9ADA13) payments previously made on account of the Construction Manager’s Fee to be paid upon final completion of the Project in accordance with the Contract Documents
§ 5.1.2 The method of adjustment of the Construction Manager’s Fee for changes in the Work:
The Construction Manager shall not be entitled to any additional Construction Manager’s Fee for changes in the Work that total up to ten percent (10%) of the original Contract Sum. For any changes in the Work in excess of ten percent (10%) of the original Contract Sum that are due to no fault of the Construction Manager or those for whom the Construction Manager is responsible, the Owner shall pay the Construction Manager, as compensation for the performance of all of the Construction Manager’s obligations related to the changed Work, a Construction Manager’s Fee at the rate of seventy-five percent (75%) of the original Construction Manager’s Fee set forth in Section 5.1.1 of this Agreement. Within ten (10) days after Substantial Completion, the Architect/Engineer shall review all Change Orders and Construction Change Directives to compute the net increase or decrease in the Contract Sum resulting from changes in the Work, and the net increase or decrease of the Contract Sum, as determined by the Architect/Engineer, shall be the basis of determining any entitlement to and calculation of any Construction Manager’s Fee for changes in the Work. If the Construction Manager is entitled to any Construction Manager’s Fee for changes in the Work, the Construction Manager shall include a request for such Fee in its final Application for Payment. Any Construction Manager’s Fee for changes in the Work is not retainage.
§ 5.1.3 The limitation on amounts payable by the Owner for the cumulative overhead and profit of Subcontractors and Suppliers of all tiers for increases in the cost of any portion of the Work shall be:
Fifteen percent (15%) of the actual cost of the associated portion of the Work with a maximum total combined fee (overhead and profit) of 25% including the prime Construction Manager’s fee.
§ 5.1.4 Rental rates for Construction Manager-owned equipment shall not exceed the standard rate paid at the place of the Project, unless otherwise stated in the Contract Documents.
§ 5.1.5 Unit prices, if any:
Item Units and Limitations Price per Unit ($0.00)
Applicable Unit Rates are established in Exhibit D – Construction Manager’s Staff Addendum. There shall be no increases allowed for the unit rates for the duration of the base contract of three (3) years. Rate increases, if desired, may be requested by the Construction Manager at the time of contract renewal. Any percentage of rate increase must be commensurate with the current consumer price index (CPI) at the time of the requested increase and is subject to approval by the Canaveral Port Authority’s designated Representative.
§ 5.2 Guaranteed Maximum Price § 5.2.1 The Construction Manager guarantees that the Contract Sum shall not exceed the Guaranteed Maximum Price set forth in the Guaranteed Maximum Price Amendment, as it is amended from time to time. The Guaranteed Maximum Price constitutes a limit on the total amount payable by the Owner to the Construction Manager for the performance of the Construction Manager’s obligations under the Contract Documents. To the extent the Cost of the Work exceeds the Guaranteed Maximum Price, the Construction Manager shall bear such costs in excess of the Guaranteed Maximum Price without reimbursement by or additional compensation from the Owner.
(Insert specific provisions if the Construction Manager is to participate in any savings.)
§ 5.2.1.1 The Construction Manager shall use its best efforts to obtain from Subcontractors and Suppliers bids, proposals, and subcontracts, or other agreements that are less than the amounts budgeted for the corresponding components of the Work in the Guaranteed Maximum Price and which are in furtherance of the Owner’s interests and objectives to complete the Project in the least costly manner in accordance with the Contract Times. If the allowable, final, and verified, audited amount of the actual Cost of the Work and Allowance items is less than the totals for each of those categories in the original Guaranteed Maximum Price, such savings shall be transferred and/or credited to the Contingency Fund described in Section 5.2.5 of this Agreement. Any amounts in the Contingency Fund at the time of Final Completion shall be credited in accordance with Section 5.2.5.1 of this Agreement, and an appropriate, corresponding Change Order shall be executed by the Owner and the Construction Manager.
AIA Document A133™ – 2009 (formerly A121™CMc – 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.
WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:47:05 on 04/28/2014 under Order No.1051200823 which expires on 03/20/2015, and
User Notes: (3B9ADA13)
§ 5.2.2 The Guaranteed Maximum Price is subject to additions and deductions by Change Order as provided in the Contract Documents and the Date of Substantial Completion shall be subject to adjustment as provided in the Contract Documents.
§ 5.2.3 The Construction Manager’s itemized calculation of the Guaranteed Maximum Price and its component parts shall be set forth in the Guaranteed Maximum Price Amendment, and the Construction Manager, by executing the Guaranteed Maximum Price Amendment, represents that the component costs upon which the Guaranteed Maximum Price is based are accurate, complete, and current at the time of the Guaranteed Maximum Price Amendment and that any other costs supporting any additional amounts payable by a Change Order in the future will also be accurate and complete. Payments to the Construction Manager shall be reduced, and the Owner entitled to a deductive Change Order, if it is determined that any component costs included in the calculation of the Guaranteed Maximum Price were materially inaccurate, incomplete, or not current.
§ 5.2.4 Allowances Within the Guaranteed Maximum Price, there may be specific items that the Construction Manager and the Owner have agreed to include as allowances until such time as the actual cost and Project Schedule impact of these items can be more specifically ascertained. The Construction Manager represents that before identifying any material(s) or equipment as an allowance item(s), the Construction Manager has performed or will perform all reasonably necessary research, investigation, and inquiry to confirm that the material(s) or equipment for which an allowance is provided is capable of being procured and that there is a justifiable and demonstrable basis for designating the material(s) or equipment as an allowance item(s) and at the sum(s) for the allowance included in the Guaranteed Maximum Price.
All unused allowance(s) shall be credited to the Owner. Allowances are further governed by Section 3.8 of the General Conditions.
§ 5.2.5 Construction Contingency Fund The Guaranteed Maximum Price shall include a Construction Contingency Fund in the amount of $ to be determined by project to be used to fund increases in the Cost of the Work for the Project identified through the refinement, development and completion of the Construction Documents. The Construction Manager will be permitted to draw from the Contingency Fund and use Contingency Funds as required, with the Owner’s written consent and approval. The Construction Manager shall account for Contingency Funds monthly in its Applications for Payment and Project accounting reports and debit and/or credit accordingly to the Construction Contingency account.
Use of the Construction Contingency Fund shall not increase the Construction Manager’s Fee or the not-to-exceed limit for General Conditions Work.
§ 5.2.5.1 All use of funds being transferred in and/or out of the Contingency Fund shall be approved by the Owner prior to use. Contingency Funds shall not be mixed with allowance categories.
§ 5.3 Changes in the Work § 5.3.1 The Owner may, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions or other revisions that may cause an increase or decrease in the Guaranteed Maximum Price and/or the Contract Time. The Owner shall issue such changes in writing. The Architect/Engineer may make minor changes in the Work as provided in Section 7.4 of AIA Document A201–2007.