Exhibit_B_-_CM_Supp._Conditions.pdf

PDF 271 KB Posted

Attached to
Waterside Construction Management at Risk Services for Continuing Services Contract
Solicitation number
RFQ-26-3
Issued by
Brevard County, Florida

About this file

Summary of Exhibit B - Construction Management Supplemental Conditions

This document contains supplemental conditions for the Canaveral Port Authority's Waterside Construction Management at Risk Services contract in Florida. The supplemental conditions establish the contractual framework and operational requirements for construction management services related to waterside facility projects at Port Canaveral. These conditions apply to the ongoing continuing services contract that covers construction, repair, refurbishment, renovation, and upgrade of various waterside facilities, including berths, piers, fender and auxiliary components, mooring dolphins, bollards, and underwater inspections. The document outlines the specific terms, conditions, and responsibilities that govern the relationship between the Port Authority and the selected construction management firm throughout the contract period.

The supplemental conditions detail the administrative, operational, and performance requirements that the contractor must meet when executing construction management services. These conditions typically address contractor obligations, insurance and bonding requirements, payment procedures, change order processes, scheduling requirements, safety standards, and dispute resolution mechanisms. The document serves as a critical component of the overall contract package, working in conjunction with the scope of services and other contract documents to establish clear expectations for quality, compliance, and project delivery standards that the contractor must maintain while providing construction management services for the Port Authority's waterside facility projects.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOTE: The following contract is provided for reference and planning purposes only. A final contract will be in substantially the same form but remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.

SUPPLEMENTAL CONDITIONS

TO CONSTRUCTION MANAGEMENT AGREEMENT

BY AND BETWEEN

[Company] [Address] [Address]

Phone:

Fax:

and

Canaveral Port Authority 445 Challenger Road Suite 301 Cape Canaveral, Florida 32920

Phone: (321) 783-7831 Fax: (321) 783-1063

FOR THE CONSTRUCTION MANAGEMENT OF:

WATERSIDE Construction Management at Risk Services for Continuing Services Contract

RFQ-26-3

Cape Canaveral, Florida 32920

TABLE OF CONTENTS

ARTICLE 1: PROJECT MANAGEMENT

1.1 PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS)

1.2 CONSTRUCTION PHASE

ARTICLE 2: SUBCONTRACTS

2.1 NO RELATIONSHIP BETWEEN OWNER AND SUBCONTRACTORS AND SUPPLIERS

2.2 REQUIRED SUBCONTRACTOR’S QUALIFICATIONS AND SUBCONTRACT CONDITIONS

2.3 INCLUSION OF SUBCONTRACTS IN PROJECT MANUAL

Article 1 Project Management

1.1 PROJECT MANAGEMENT INFORMATION SYSTEMS (PMIS) –. All project documentation, including but not limited to RFIs, Submittals, Applications for Payment, Reports, Meeting Minutes, etc., will be submitted through a construction management software. CPA preferred construction management software is Procore however, CPA will consider other software or methods for tracking documentation.

1.1.1 General Requirements.

.1 Time of Implementation. Commencing immediately after Notice to Proceed, the Construction Manager shall implement and shall utilize throughout the term of this Contract all subsystems of the Project Management Information System hereinafter referred to as PMIS.

.2 Reflection of Current Status. The reports, documents, and data to be provided shall represent an accurate assessment of the current status of the Project and of the work remaining to be accomplished and it shall provide a sound basis for identifying variances and problems and for making management decisions.

.3 Preparation and Delivery. The reports, documents, and data shall be prepared by the Construction

Manager and furnished to the Owner and the Architect on or before the first (1) day of each month and at such greater frequency to allow the Construction Manager to submit to the Owner and Architect such updated reports, documents, and data with each Application for Payment and shall accompany each Application for Payment.

.4 Major Subsystems. The PMIS shall be described in terms of the following major subsystems:

a. Narrative Reporting (on a monthly basis);

b. Schedule Control (on a monthly basis);

c. Cost Control, and estimating; and

d. Project Accounting and Projected Costs.

1.1.2 Narrative Reporting Subsystem.

.1 The Construction Manager shall prepare written reports as described hereunder. No other PMIS narrative reports shall be required. All reports shall be in 8 1/2" X 11" format.

.2 The Narrative Reporting Subsystem shall include the following reports:

a. Monthly Executive Summary providing an overview of current issues and pending decisions, future developments and expected achievements, and any problems or delays, including code violations found by the Permitting Authority.

b. Monthly Cost Narrative describing the current construction cost estimate of the Project, including a comparison of planned performance with actual performance and pending and potential change orders.

c. Monthly Scheduling Narrative summarizing the current status of the overall Project schedule. This report shall include an analysis of the various project schedules, a description of the critical path, and other analyses as necessary to compare planned performance with actual performance.

d. Monthly Accounting Narrative describing the current cost and payment status of the entire project. This report shall relate current encumbrances and expenditures to the budget allocations, including contingency tracking.

e. Monthly Construction Progress Report summarizing the work of the various Subcontractors. This report shall include information from the weekly Project site meetings as applicable, such as general conditions, long lead supplies, current deliveries, safety and labor relations programs, permits, construction problems and recommendations, and plans for the succeeding month.

f. Sales Tax Savings Report listing all executed Owner direct purchases including paid to date amounts.

g. Daily Construction Diary describing events and conditions on the Project site.

.3 The reports outlined in section 1.1.2.2, above, shall be bound with applicable computer reports, submitted monthly, and shall be current through the end of the preceding month. Copies shall be transmitted to the Owner, the Architect and others designated by the Owner with the Construction Manager’s monthly Applications for Payment. Additional copies of the report outlined in section 1.1.2.2(a), above, shall be bound separately and distributed monthly as directed by the Owner.

.4 The report outlined-in section 1.1.2.2 (g), above, shall be maintained at the Project site and be available to the Owner and Architect. A copy, bound separately, of the daily diary shall be submitted to the Owner and the Architect with the Construction Manager’s Monthly Application for Payment..

1.1.3 Scheduled Control.

.1 Master Project Schedule. Upon award of the Contract, the Construction Manager shall submit a master overall Project Schedule, including scheduling for construction, and Owner occupancy of the Project. This Project Schedule will be in a Critical Path Method (CPM) format. This Project Schedule will serve as the framework for the subsequent development of all detailed schedules. The master overall Project Schedule shall be produced and updated on or before the first (1) day of each month throughout the Project and at such greater frequency to allow the Construction manager to submit to the Owner an Updated Project Schedule with each Application for Payment. All Project Schedule updates must clearly indicate what Work items are on the critical path, what Work items are critical and in need of completion within the next thirty (30) days, and what Work items have slipped on the schedule within the preceding thirty (30) days. The Project Schedule updates must also list all long lead-time Work items on which the Construction Manager is waiting and other issues that need attention within the succeeding thirty (30) days..

.2 Failure of the Construction Manager to develop and submit a master Project Schedule as stated in this Article

1 shall be sufficient grounds for the Owner to find the Construction Manager in substantial default and certify to the Owner that sufficient cause exists to terminate the Contract or to withhold payment. Following development and submittal of the Project Schedule as described above, the Construction Manager shall, on or before the first (1) day of each calendar month, and at such greater frequency to allow the Construction Manager to submit to the Owner an Updated Project Schedule with each Application for Payment, , update and/or revise the Project schedule to clearly show: (1) the actual progress of the Work performed, in contrast with the planned progress of performance of such Work as depicted on the original Project Schedule, and all updates and/or revisions thereto as reflected in the Updated Project Schedule last submitted prior to submittal of each such Updated Project Schedule, (2) all Work activities that are on the critical path, (3) all Work items that are critical and in need of completion within the next thirty (30) days, (4) all Work activities that have slipped on the Project Schedule within the preceding thirty (30) days , (5) all long lead-time Work items on which the Construction Manager is waiting and (6) other issues that need attention within the succeeding thirty (30) days or thereafter. Each such update and/or revision to the Project Schedule shall be submitted to the Owner and the Architect in duplicate. All revisions to the Project Schedule shall be highlighted and accompanied with a narrative justification. Failure of the Construction Manager to update, revise, and submit the Project Schedule as stated above shall be sufficient grounds for the Owner to find the Construction Manager in substantial default and certify to the Owner that sufficient cause exists to terminate the Contract or to withhold payment to the Construction Manager until a Project Schedule or Project Schedule update acceptable to the Owner is submitted.

1.1.4 Cost Control. The Construction Manager shall operate this subsystem so as to provide sufficient timely data and detail to permit the Construction Manager to control and adjust, by building and site element, the Project requirements, needs, materials, equipment, and systems, so as to insure that construction will be completed at a cost which, together with all other Project costs, will not exceed the Guaranteed Maximum Price.

1.1.5 Project Accounting. The Construction Manager shall operate this subsystem so as to enable the Construction

Manager to effectively plan, monitor and control the funds available for the Project, the cash flow, the costs, change orders, contingencies, payments, Owner direct purchases, sales and other tax savings and other major financial factors by comparison of budget, estimate, projected costs, total commitment, amounts invoiced, and amounts payable. This subsystem will be produced and updated on or before the first (1) day of each month and at such greater frequency to allow the Construction Manager to produce and update this subsystem contemporaneous with each Application for Payment and shall include the reports listed immediately below, which together will serve as a basic accounting tool and an audit trail. This report will also provide for accounting by building and site elements.

.1 Costs Status Report. This report shall present the budget, estimate, and base commitment (awarded contract and purchase orders) for any change given contract or budget item. It shall show approved change orders for each contract, which will become the total commitment when added to the base commitment. Pending change orders will also be shown to produce the total estimated probable cost to complete the Work.

.2 Payment Status Report. This report shall show the value in place (both current and cumulative), the amount invoiced (both current and cumulative), the amount retained, the amount payable (both current and cumulative), and the balance remaining. A summary of this report shall accompany each pay request.

.3 Detailed Status Report. This report shall show the complete activity history of each item in the Project accounting structure. It shall include the budget, estimate, and base commitment figures for each contract. It shall give the change order history, including change order numbers, descriptions, proposed and approved dates, and the proposed and approved dollar amounts. It shall also show all pending or rejected change orders.

.4 Cash Flow Diagram. This report shall show the projected accumulation of cash payments against the project.

Cash flow projections shall be generated for anticipated monthly payments as well as cumulative payments.

.5 Job Ledger. This ledger shall be maintained as necessary to supplement the operation of the Project accounting subsystem. The job ledger will be used to provide construction cost accountability for general conditions work, on-site reimbursable expenses, and costs requiring accounting needs.

.6 Owner Direct Purchases. This report shall show Owner direct purchase commitments, payments, sales and other tax savings, balances to be paid, deductive change order references and pay application line references.

.7 Contingency Report. This report shall show the history and current status of each contingency, including descriptions, change order references, amounts, and subcontractor references.

1.2 CONSTRUCTION PHASE

1.2.1 Market Analysis.

.1 Monitoring and Analyzing Market Conditions. The Construction Manager shall monitor conditions in the construction market to identify factors that will or may affect costs and time for completing the Project.

The Construction Manager shall make analysis as necessary to (1) determine and report on availability of labor, material, equipment, potential bidders, and possible impact of any shortages or surpluses of labor or material, and (2) in light of such determinations, make recommendations as may be appropriate with respect to long lead procurement, separation of construction into bid packages, sequencing of work, use of alternative materials, equipment or methods, other economics in design or construction, and other matters that will promote cost savings and completion within the scheduled time.

.2 Reporting on Market Analysis and Prospective Bidders. On or before the thirtieth (30) calendar day after receiving Notice to Proceed with the Construction Phase Work, the Construction Manager shall submit to the Architect and the Owner a written "Construction Market Analysis and Prospective Bidders Report" setting out recommendations and providing information as to prospective bidders.

1.2.2 Solicitation of Bids.

.1 The Construction Manager shall prepare invitations for bids (or requests for proposal, when applicable) for all procurement of long lead times, materials and services, Subcontractor contracts and Project site utilities.

.2 As part of such preparation, the Construction Manager shall review the Specifications and Drawings prepared by the Architect. Ambiguities, conflicts, lack of clarity of language, use of illegally restrictive requirements, omissions, and any other defects in the Specifications or the Drawings perceived or discovered by the Construction Manager shall be brought to the attention of the Owner and Architect in written form.

.3 Unless waived by the Owner, the Construction Manager shall conduct a pre-bid conference with prospective subcontract bidders, the Architect and the Owner. If questions are raised that require an interpretation of the bidding documents or otherwise indicate a need for clarification or correction of the invitation or the Drawings and Specifications, the Construction Manager shall transmit the questions to the Architect. After receiving clarification or correction in writing, the Construction Manager shall prepare an addendum to the bidding document and issue the addendum to all of the prospective bidders.

.4 The Construction Manager, in preparation of the Guaranteed Maximum Price Proposal, shall make all reasonable efforts and strive to obtain at least three (3) written and sealed bids or proposals for each trade category of the Work. The Construction Manager shall establish a pre-qualification procedure for applicable subcontract trades. The Construction Manager shall open and review all bids and enter into a contract with the lowest responsive, responsible bidder, for each scope of work, determined to be qualified by the Construction Manager and approved by Owner. The Owner will review each bid tabulation, supporting bids and proposals, and the Construction Manager’s recommendation to award and will approve or reject the recommendation prior to award. Should the Construction Manager determine it is in the best interest of the Owner to utilize a Subcontractor other than the lowest responsive, responsible bidder, the Construction Manager’s determination must be approved in writing by the Owner, in the Owner’s sole discretion, before the Construction Manager enters into a subcontract with said Subcontractor.

.5 If authorized by the Owner, the Subcontractor may negotiate for the procurement of a particular subcontract trade category or categories of the Work.

.6 Unless otherwise approved by the Owner, each Subcontractor must have successfully completed within the last five (5) years no less than two (2) projects of similar size and complexity to the Project.

1.2.3 Permits, Fees, and Inspections. Unless otherwise provided in the Contract Documents, the Construction Manager shall coordinate, secure and pay for all necessary permits, fees, licenses, and inspections from applicable federal, state, county, and local agencies responsible for permitting and code inspections on projects administered by the Owner (the “Permitting Authority”), the costs of which will be reimbursable as a Cost of the Work. The Owner will directly pay impact and solid waste fees.

1.2.4 Maintenance of Construction Manager's Staff. During the Construction Phase, the Construction Manager shall maintain sufficient off-site support staff and competent full time staff at the Project site, authorized to act on behalf of the Construction Manager to coordinate, inspect and provide general direction of the Work and progress of the Subcontractors and Suppliers, of any tier. Unless otherwise agreed by the Owner, the Construction Manager’s Staff during the Project shall be as set forth in the Construction Management Staff Addendum, which is incorporated herein by reference.

1.2.5 Project Site Requirements.

.1 The Construction Manager shall perform each of the following activities as a part of the Construction Manager Fee:

a. Maintain a log of daily activities, including manpower records, weather, delays, major decisions, etc., and require the same of Subcontractors;

b. Maintain a directory of companies on the Project with names, addresses, telephone numbers, emergency telephone numbers, and fax numbers of key personnel;

c. Establish and enforce Project rules governing parking, clean-up, use of facilities and worker discipline;

d. Provide labor relations management for a harmonious, productive Project;

e. Provide a safety program for the Project to meet OSHA requirements and monitor for Subcontractor compliance without relieving them of responsibilities to perform work in accordance with the best acceptable practice; and

f. Provide a quality control program.

.2 Quality Control.

a. Establishment of Standards. Before the Date of Commencement of the Work, the Construction

Manager shall establish, to the satisfaction of the Owner, standards of workmanship quality.

b. Third Party Inspections.

(i) Notice. The Construction Manager is responsible for timely notice to the Owner relating to the performance of any inspection, test or approval required in the Contract Documents or applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public authorities.

(ii) Owner Opportunity to Observe. The Construction Manager will provide the Owner the opportunity to observe any inspections, tests or approvals. The Owner will cooperate with Construction Manager in observing inspections, tests or approvals and will endeavor not to delay Construction Manager in this regard.

(iii) Cost of Inspection. The cost of all inspections, tests or approvals required by the

Contract Documents or public authorities will be borne by the Construction Manager.

(iv) Special Inspections. If in the reasonable opinion of the Owner, any Work requires special inspection, testing or approval not required or referenced in the Contract Documents, the Owner will instruct the Construction Manager, in writing, to order such special inspection, testing or approval, and Construction Manager will give the proper notices as required by section 1.2.5.2(b)(i). If such special inspection or testing indicates that the Work inspected does not comply with the requirements of the Contract Documents, the Construction Manager will bear all costs thereof, including the cost of the testing and the cost to repair or replace the Work. If such special inspection or testing does not reveal a failure of the Work to comply with the Contract Documents, then Owner will bear such costs and an appropriate Change Order will be issued.

(v) Certificates of Inspection. All required certificates of inspection, testing or approval will be obtained by the Construction Manager and promptly delivered to the Owner.

.3 The Construction Manager shall provide personnel and equipment, or shall arrange for separate subcontracts, to provide each of the following as a direct cost item:

a. Services of independent testing laboratories to provide the necessary testing of materials to ensure conformance to contract requirements;

b. Printing and distribution of all required bidding documents and shop drawings, including the sets required by the Permitting Authority's inspectors.

.4 Weather Protection. The Construction Manager shall ascertain what temporary enclosures, if any, of building areas should and may be provided as a practical matter, to ensure orderly progress of the Work in periods when extreme weather conditions are likely to be experienced. The Construction Manager shall submit recommendations to the Architect and the Owner as to any necessary measures of this nature and as to the contract or contracts in which they should be included.

1.2.6 Project Site Facilities.

.1 Definition. "Project Site Facilities" means any tangible personal property and equipment necessary to carry on the Project, including, but not limited to, trailers, toilets, and, computers.

.2 Duty to Supply. The Construction Manager shall arrange for the supply of all Project Site Facilities necessary to enable the Construction Manager, the Owner's representatives and the Architect to perform their respective duties in the management, inspection, and supervision of construction of the Work.

.3 Acquisition. The method of acquiring such Project Site Facilities that are to become the property of the

Owner at the conclusion of the Project shall be evaluated by considering the cost of the "facility" over the life of the Project. Owning versus leasing shall be considered. The Construction Manager shall present its evaluation with recommendations to the Owner for approval.

.4 Care and Maintenance. For all Project Site Facilities that may become the property of the Owner at the conclusion of the Project, the Construction Manager shall maintain ownership responsibilities of such facilities until final completion of the Project. The Construction Manager is responsible for proper care and maintenance of all equipment while it is in the Construction Manager’s control. At the time of transfer to the Owner, the Owner may refuse acceptance of the equipment if the Owner determines, in its sole discretion, that the equipment has not been properly cared for by the Construction Manager or that such acquisition would not otherwise be in the best interest of the Owner. In such an event, the Construction Manager will not be reimbursed for the item.

.5 Reimbursement. Reimbursement for the costs of Project Site Facilities will be made with the Owner’s final payment to the Construction Manager and shall be at the documented purchase or lease price. At the time of submitting its final Application for Payment to the Owner, the Construction Manager shall provide the Owner with a complete inventory of Project Site Facilities, and include all owner and maintenance manuals for each unit of equipment. The inventory shall describe the equipment and identify the purchase or lease price, serial number, model number and condition.

1.2.7 Construction Manager’s Performance of Work When Advantageous. If approved by the Owner, the Construction

Manager, when qualified and capable, may perform all or a portion of the Work for any item listed on the Guaranteed Maximum Price Amendment, when it is deemed by the Owner and the Construction Manager due to the Project Schedule or the economic benefit for the Cost of the Work.

1.2.8 Project Site Administration. The Construction Manager shall provide, as part of its fee, administrative functions during construction, including but not limited to, the following:

.1 Project Meetings.

a. Hold weekly progress and coordination meetings to provide for an easy flowing Project completed in accordance with the Contract Documents;

b. Implement procedures and assure timely submittals, expedite processing approvals and return of shop drawings, samples, etc.;

c. Coordinate and expedite critical ordering and delivery of materials, work sequences, inspection and testing, labor allocations, etc.;

d. Review and coordinate each Subcontractor's work;

e. Review and implement revisions to the Schedule;

f. Monitor and promote safety requirements;

g. Hold a regular monthly Project status meeting between the Architect, Owner and Construction

Manager;

h. Prepare and distribute all meeting minutes;

i. Identify party or parties responsible for follow-up on any problems, delay items or questions and record course for solution utilizing an “action item format”;

j. Revisit each pending action item at each subsequent meeting until resolution is achieved.

.2 Commissioning.

a. Construction Manager will contract with an independent agency to complete commissioning services under an allowance line item.

.3 Start-Up.

a. With the Owner's personnel, direct the checkout of utilities, operations, systems and equipment for readiness and video tape and assist in their initial start-up and testing by the Subcontractors.

.4 Record Drawings.

a. The Construction Manager shall monitor the progress of its own forces or its Subcontractors on marked-up field prints, which at Substantial Completion shall be submitted to the Architect who will prepare the final record drawings.

1.2.9 Administrative Records. The Construction Manager will maintain at the Project site on a current basis, files and records including, but not limited to, the following:

Contracts or Purchase Orders Shop Drawing Submittal/Approval Logs Equipment Purchase/Delivery Logs Contract Drawings and Specifications with Addenda Warranties and Guarantees Cost Accounting Records:

Labor Costs

Materials Costs Equipment Costs Cost Proposal Requests Payment Request Records Meeting Minutes Cost-Estimates Bulletin Quotations Lab Test Reports Insurance Certificates and Bonds Contract Changes Purchase Orders Material Purchase Delivery Logs Technical Standards Design Handbooks "As-Built" Marked Prints Operating & Maintenance Instruction Daily Progress Reports Monthly Progress Reports Correspondence Files Transmittal Records Inspection Reports Bid/Award Information Bid Analysis and Negotiations Punch Lists PMIS Schedule and Updates Suspense (Tickler) Files of Outstanding Requirements Project Manual

The Project records shall be available at all times to the Owner and Architect for reference or review.

1.2.10 Owner Occupancy/Commissioning.

.1 Smooth Transition. The Construction Manager shall provide a smooth and successful Owner occupancy of the Project. The Construction Manager shall provide consultation with Project management to facilitate Owner occupancy and provide transitional services to get the work, as completed by the Construction Manager, "on line" and in such condition as will satisfy the Owner's operational requirements.

.2 Preliminary Punch List Inspection. The Construction Manager shall conduct the Construction Manager's preliminary punch list inspection and coordinate the completion of all Substantial Completion Punch List Work to be done with Owner occupancy requirements in mind.

.3 Equipment Catalog and Operation Training. The Construction Manager shall catalog operational and maintenance requirements of equipment to be operated by maintenance personnel and convey these to the Owner in accordance with the technical requirements of the Specifications and in such a manner as to promote their usability. The Construction Manager shall provide operational training, in equipment use, for building operators.

.4 Securing Guarantees and Warranties. The Construction Manager shall secure required guarantees and warranties and assemble and deliver same to the Owner in accordance with the technical requirements of the specifications and in a manner that will facilitate their maximum enforcement and assure their meaningful implementation.

.5 Review of As-Built Drawings and Progress Prints. The Construction Manager shall continuously review

"As-Built" Drawings and mark-up progress prints, as a condition of each payment, to ensure their accuracy.

1.2.11 Warranties.

.1 Delivery of Warranties. The Construction Manager shall collect and deliver to the Owner, before final completion and final payment, all specific written warranties and guarantees given by the Construction Manager and others, including, but not necessarily limited to: (i) manufacturers and Suppliers of machinery, materials, equipment, products, and/or supplies purchased by the Construction Manager, as required by the Contract Documents or otherwise applicable to the materials, machinery, equipment, or supplies purchased by the Construction Manager for the Project, and (2) Subcontractors of any tier. Said warranties shall be issued or assignable by their terms to the Owner. The Construction Manager shall cooperate and assist the Owner in the enforcement of all such warranties and guarantees, and by written contract, shall require Subcontractors and Suppliers, of any tier, to do the same.

.2 Warranty Inspection. The Construction Manager shall conduct, jointly with the Owner and the Architect, a warranty inspection of Work and all improvements resulting therefrom eleven (11) months after the date of Substantial Completion. If the Construction Manager fails to attend, participate in, and complete a warranty inspection of the Work within the one-year period from the date of Substantial Completion, the period of the Construction Manager’s warranty shall be extended to thirty (30) days following the date on which the Construction Manager complies with its obligation to conduct a warranty inspection herein.

3. Survival of Warranty Obligations. The foregoing and other obligations of the Construction Manager relating to warranties and guarantees to be given to the Owner under the Contract Documents survive final completion of the Work and acceptance of the Work by the Owner.

Article 2

Subcontracts

2.1 NO RELATIONSHIP BETWEEN OWNER AND SUBCONTRACTORS AND SUPPLIERS

2.1.1 Nothing contained in the Contract Documents shall create any contractual or other legal relationship, either express or implied, between the Owner or Architect and any Subcontractor or Supplier of the Construction Manager.

2.2 REQUIRED SUBCONTRACTORS' QUALIFICATIONS AND SUBCONTRACT CONDITIONS.

2.2.1 Licensure. Before entering into any contract with a Subcontractor, the Construction Manager shall verify that the

Subcontractor is properly licensed by the State of Florida to perform the Work contemplated by the subcontract and shall supply to the Owner satisfactory evidence of such licensure.

2.2.2 Drug Free Work Place Premium Reduction. All certificates of insurance shall note qualification for a Drug Free

Work Place Insurance premium reduction in accordance with Florida law.

2.2.3 Pre-Qualification Form. Subcontract bidders must submit a completed pre-qualification form demonstrating their work experience, financial condition, and adherence to schedule. The Subcontractor's financial condition must demonstrate that adequate fixed and liquid assets and equipment are available to properly perform the subcontract.

2.2.4 Workforce. The Subcontractor must agree to perform no less than fifteen (15%) percent of the Subcontractor’s scope of the Work utilizing the Subcontractor’s own employees.

2.2.5 Limitation of Remedy - No Damages for Delay. All subcontracts shall provide:

.1 Limitation of Remedy – No Damages for Delay

The Subcontractor’s sole and exclusive remedy for delays or other time-related impacts to the performance of the subcontract work caused by events beyond the Subcontractor’s control, including, but not limited to, delays claimed to be caused by or attributable to the Owner or Architect, including claims based on breach of contract, negligence, or any other legal or equitable theory, shall be an equitable adjustment to the Subcontractor’s time to complete the subcontract work. The Construction Manager shall require each Subcontractor to waive and to disclaim any entitlement to any monetary damages or any other delay or time-related impact.

.2 Limitation of Subcontractor Overhead and Profit.

As set forth in AIA Document A133-2009, Standard Form of Agreement between Owner and Construction

Manager as Constructor, in the event of a change in the Work, the amount payable by the Owner to the Construction Manager for adjustments in the Contract Sum is limited exclusively to the actual cost of the Work required by such change, plus no more than fifteen (15%) percent for the cumulative overhead and profit of Subcontractors of all tiers. The Construction Manager shall include this limitation in its subcontracts, and the Construction Manager’s subcontracts shall require that the Subcontractor expressly agree that the foregoing constitutes its sole and exclusive remedies for delays and changes in the Work and, thus, eliminates any other remedies for claims for increases in the contract price, time, damages, loss or additional compensation.

.3 Each subcontract shall require that any claims by Subcontractor for additional time or cost must be submitted to Construction Manager in the same time and manner in which the Construction Manager must submit such claims to the Owner as set forth in the Contract Documents. Failure to comply with the conditions for giving notice and submitting claims shall result in the waiver of such claims.

2.3 INCLUSION OF SUBCONTRACTS IN PROJECT MANUAL. The Construction Manager shall include in the

Project Manual a copy of each subcontract, including the general supplementary conditions.

SUPPLEMENTAL CONDITIONS
TO CONSTRUCTION MANAGEMENT AGREEMENT
BY AND BETWEEN
and
Canaveral Port Authority
FOR THE CONSTRUCTION MANAGEMENT OF:
TABLE OF CONTENTS
Project Management
1.1.3 Scheduled Control.
1.2 CONSTRUCTION PHASE
Contracts or Purchase Orders
The Project records shall be available at all times to the Owner and Architect for reference or review.
Article 2

File details come from the government source that posted it. Updated .