Exhibit_E_-_ODP_Procedures.pdf

PDF 104 KB Posted

Attached to
Waterside Construction Management at Risk Services for Continuing Services Contract
Solicitation number
RFQ-26-3
Issued by
Brevard County, Florida

About this file

Exhibit E is a procedural document issued by the Canaveral Port Authority outlining the requirements and processes for requesting an ODP (On-Demand Purchase) purchase order for the Waterside Construction Management at Risk Services contract. The document details the vendor registration requirements, which mandate that suppliers be registered with the Port through an online application process requiring submission of a vendor application, W-9 form, and insurance certificate. The ODP process requires suppliers to obtain price quotes, complete an ODP form signed by the supplier, subcontractor (if applicable), and Construction Manager, and submit these documents to the CPA for processing. Following CPA Engineering review and CPA Finance approval, CPA Purchasing issues and distributes the purchase order to relevant parties including the Construction Manager and supplier.

The document establishes invoice processing procedures requiring submission on an invoice summary form with no more than 10 invoices per form, with signatures from both the subcontractor (if applicable) and Construction Manager approving payment. Invoices must be processed promptly to avoid payment delays. The document notes that price quotes must include taxes and separately itemize freight charges without tax application to freight costs. At project completion, a deductive change order will be executed based on actual invoiced amounts for materials, freight, and sales tax to adjust the Construction Manager's purchase order accordingly. The procedures apply to material and service procurement for the Port's ongoing waterside facility construction, repair, and renovation projects.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit E

REQUESTING AN ODP PURCHASE ORDER

Supplier needs to be a registered vendor with the Port.

It is possible to register online by going to www.PortCanaveral.com.

Click on the link "Business with Us" on the top of the screen.

“Doing Business with Port Canaveral – there you will click on vendor application, PO terms and conditions, Insurance requirements and the W-9 form.

Purchasing must receive a vendor application, W9 and insurance certificate for anyone who will be on Port property to issue a vendor number. Have vendor email or fax application to the information on the application, it would also be helpful to have them email the information to the Admin Coordinator for the project that way they know to be on the lookout for the new vendor.

Get price quote/proposal/sales order for material being requested.

Fill out the ODP form (CPA will provide one when needed)

Have the ODP form signed by the:

• Supplier

• Subcontractor -- if there is no subcontractor involved write NONE on the signature line for the subcontractor.

• Construction Manager

Send the filled out and signed ODP form along with a copy of the price quote/proposal/sales order to CPA. The ODP form will not have taxes included, but the quote should have taxes included. If there is freight to be included, it should also be separated from the materials and no taxes on the freight on the quote.

CPA will sign the ODP form and email a copy of the fully signed ODP form to Construction Manager.

Construction Manager should then email a copy to the subcontractor who should then email a copy to the supplier.

If there is no subcontractor, Construction Manager should then email a copy of the ODP form to the supplier.

CPA Engineering will request a purchase order for the needed material.

CPA Finance will review/approve the purchase requisition.

CPA Purchasing will review/approve/issue the purchase order.

CPA Purchasing will fax and/or email a copy of the purchase order to the supplier.

CPA Purchasing will send a copy of the purchase order to CPA Engineering Department, who will then inform the Construction Manager. The Construction Manager should request a copy from the supplier for their records.

PROCESSING ODP INVOICES

Invoices need to be listed on a invoice summary form when submitted for payment.

No more than 10 invoices should be listed on each invoice summary.

Each invoice must be signed and dated by the subcontractor (if there is one) and the Construction Manager indicating that the invoice is approved by the subcontractor/construction manager for payment.

Invoices should be processed immediately to avoid payment delays. DO NOT SIT ON INVOICES WHICH ARE

APPROVED FOR PAYMENT.

DEDUCTIVE CHANGE ORDER

At the end of the project, a deductive change order for the total material, freight and sales tax on material will be done to decrease the Construction Manager's purchase order. The change order will be based on actual invoiced amounts for material and freight.

http://www.portcanaveral.com/