Exhibit_G_-_General_Requirements_CMaR.pdf
PDF 288 KB Posted
- Solicitation number
- RFQ-26-3
- Issued by
- Brevard County, Florida
About this file
This file is Exhibit G—General Requirements for the Waterside Construction Management at Risk Services for Continuing Services Contract (RFQ-26-3) issued by the Canaveral Port Authority in Florida. The document establishes comprehensive administrative and technical requirements governing construction contractor performance for waterside facility projects, including berths, piers, fenders, mooring dolphins, bollards, and underwater inspections at Port Canaveral. The exhibit addresses all items and work shown on drawings as new unless marked "EXISTING," "NOT IN THIS CONTRACT," or "OWNER FURNISHED MATERIAL." Contractors must field-verify all existing utilities and structures prior to construction commencement and comply strictly with water quality standards established under Florida Administrative Code Chapter 17-3, maintaining turbidity levels not exceeding 29 Nephelometric Turbidity Units above background levels for Class III waters at Port Canaveral. All removed, salvaged, and excess materials become Owner property; disposal and storage costs are borne by the Contractor. The contract requires submission of a Critical Path Method schedule, materials submittals within 20 days of Notice to Proceed, and completion of all shop drawing submittals at minimum 30 calendar days prior to construction requirements.
The document mandates extensive project management and documentation requirements including weekly progress meetings, daily progress reports, comprehensive photographic documentation (digital, weekly progress photos, aerial, and time-lapse video), and pre-construction, progress, and pre-installation meetings with mandatory Contractor and subcontractor attendance. All Contractor and subcontractor employees requiring access to secure Port areas must obtain Port Canaveral Business Purpose Badges and Transportation Workers Identification Credentials (TWIC), with associated fees borne by the Contractor; up to ten unescorted non-TWIC personnel are permitted per TWIC-badged supervisor in secure areas. Start-up and demonstration testing must occur over seven consecutive days with the Work operating successfully as specified; any interruption requires restarting from day one with actual damages assessed against the responsible party. Project closeout includes substantial completion and final completion certifications, record document submittals in both hard copy and PDF format, final cleaning to commercial standards, and comprehensive warranties and bonds from manufacturers and subcontractors. All costs associated with surveys, permits (excluding Port-paid building permit fees), reinspection fees, temporary utilities, security measures, and project administration are Contractor's responsibility.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOTE: The following contract is provided for reference and planning purposes only. A final contract will be in substantially the same form but remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
RFQ-26-3
Exhibit G
011116-1
EXHIBIT G
SECTION 01 11 16
GENERAL REQUIREMENTS
1.00 ITEMS AND WORK SHOWN ON THE DRAWINGS: Regardless of the drawing line weights, fonts, or graphics used, all items and Work shown on the drawings shall be new, and shall be provided, fabricated, and installed by the Contractor unless specifically identified on the drawings with the words “EXISTING” or “NOT IN THIS CONTRACT” or “OWNER FURNISHED MATERIAL.”
1.01 EXISTING UTILITIES AND STRUCTURES: All existing utilities and facilities depicted on the drawings are located from existing records. Guaranty is not made that all existing facilities are depicted or that those depicted are entirely accurate. The Contractor shall field verify any and all utilities, structures or facilities prior to start of construction. Prior to start of construction the Contractor shall request each Utility Agency to locate their facilities, including supply valves, in the vicinity. The Owner and the Engineer shall assume no liability for damages sustained or costs incurred related to the Contractor's operations. The Contractor shall notify the Engineer of any and all deviations between existing conditions and the Contractual Drawings.
1.02 PRESERVING WATER QUALITY: The Contractor shall exercise extreme care as not to degrade water quality. All required provisions shall be provided to insure compliance with all water quality standards of the State of Florida and associated Agencies.
Attention is called to Chapter 17-3, Florida Administrative Code, and in particular, the requirements that turbidity shall not exceed 29 Nephelometric Turbidity Units above background level. The waters at Port Canaveral are classified Class III. Adequate silt -containment procedures and equipment shall be installed and maintained to control turbidity during the contract at no additional expense to the Owner.
1.03 REMOVED, SALVAGED, AND EXCESS MATERIAL; DEBRIS AND TRASH: Unless otherwise depicted in the Drawings or Specifications, all materials removed or salvaged under this Contract shall be the property of the Owner. Excess materials, including fill, shall be the property of the Owner. Salvaged materials shall not be reused in the Contract, except upon written approval of the Engineer. All removed, salvaged, or excess materials not approved for reuse shall be either disposed of off-site, or packaged and placed in storage within Port Canaveral Property as directed by the Engineer. Debris and trash encountered during the Contract, or generated by the Contractor, shall be disposed off-site. All costs associated with disposal or storage shall be borne by the Contractor.
1.04 MATERIALS SUBMITTALS: Within 20 days after Notice to Proceed and before remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-2 commencement of installation of any materials or equipment, Contractor shall provide the Engineer, for review and acceptance, a schedule itemizing all submittals and shop drawings with their proposed submission dates.Contractor shall submit to the Engineer, for written approval, one (1) paper copy and an electronic copy in PDF format of Shop Drawings, catalog cuts, etc. Submit together, at one time, a complete package prepared for Engineer's approval. Partial and/or incomplete submittal information shall not be processed. Signed and sealed shop drawings required for review (i.e., fire sprinklers, fire alarm) shall be submitted with five (5) paper copy (signed and sealed) and an electronic copy in PDF format.
Where required, Contractor shall include the names, addresses and telephone numbers of the Manufacturers, trade names with catalog cuts, catalog numbers, data, Manufacturer's drawings, installation layout, installation instructions, fabrication instructions, shop drawings, industry certification, equipment block diagrams, schematic diagrams, and guarantees. The product of reputable Manufacturers regularly engaged in the commercial production of the specified equipment shall not be rejected on the basis of minor differences, provided minimal requirements of this Specification relative to form, fit and function are met. Reference, on the submittal top sheet, specific Technical Sections for the required item submittals.
In case of conflict or discrepancy, the governing order of the documents shall be as follows:
1. Change Order(s).
2. Contractual Documents.
3. Proposal(s).
4. Special General Conditions.
5. General Conditions.
6. Supplemental Technical Specifications.
A. Shop Drawings - Contractor’s Responsibility
1. The Contractor shall not commence construction depicted by a Shop
Drawing returned for correction until a revision or correction thereof has been reviewed and returned to him, by the Engineer, with written approval.
2. The Contractor shall submit all Shop Drawings to the Engineer sufficiently in advance of construction requirements to provide no less than a minimum of thirty (30) calendar days.
3. Notification of Deviations from Contract Documents.
a. The Contractor shall indicate in bold type at the top of the cover remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-3 sheet of the submittal of shop drawings if there is a deviation from Contract Drawings, Contract Specifications and referenced specifications or codes.
b. The Contractor shall list any and all deviations from Contract Drawings, Contract Specifications and referenced specifications or codes and identify in "green" ink prominently on the Shop Drawings.
4. The Contractor shall be responsible for, and bear all costs of damages resulting from, the ordering of any material or from proceeding with any part of work prior to the written approval by the Engineer of the required Shop Drawings.
5. The Contractor shall be solely responsible for observing and making any and all changes including but not limited to the arrangement of piping, connections, wiring, manner of installation, etc., which shall be required by the materials/equipment he proposed to supply both as pertains to Contractor’s own work and any work affected under other parts, headings, or divisions of Drawings and Specifications.
6. The Contractor shall not utilize Shop Drawings as means of proposing alternate items to demonstrate compliance to Contractual requirements.
7. Each submittal shall bear a stamp verifying that Contractor has fulfilled Contractor's obligations under the Contract Documents with respect to Contractor’s review and approval of that Submittal.
8. Shop Drawings and schedules shall be verified and coordinated with the scope of work of all trades and Sub-contractors, prior to submittal for review by the Engineer. All Submittals shall bear the Contractor's stamp of approval as verification of such checking and coordination. Drawings or schedules submitted without Contractor’s stamp of approval shall be rejected and returned to the Contractor for resubmission.
B. Engineer’s Review of Shop Drawings
1. The Engineer's review of Shop Drawings, Data and Samples submitted by the Contractor, shall verify the items(s) conform to the requirements in the Contract Documents and are compatible with the design. The Engineer's review and exceptions, if any, shall not constitute an approval of functionality, dimensions, connections, quantities, and details of the material, equipment, device, or item depicted.
2. The review of Shop Drawings and schedules shall be general, and shall not be construed:
a. As permitting any departure from the Contractual requirements.
remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-4
b. As relieving the Contractor of responsibility for any errors, including details, dimensions, and materials.
c. As approving departures from details furnished by the Design Engineer, except as otherwise provided herein.
3. If the submitted drawings or schedules depict variations and/ or depict a departure from the Contract requirements which the Engineer finds to be in the interest of the Owner and to be so minor as not to involve a change in Contract Price or time for performance, the Engineer shall return the reviewed drawings without noting an exception.
4. "Approved As Noted" or “Make Corrections Noted” - Contractor shall incorporate Engineer's changes into the submittal before release to Manufacturer. The Contractor shall send a letter of correspondence to the Engineer acknowledging the changes and their incorporation into the Shop Drawing(s).
5. "Revise And Resubmit" - Contractor shall resubmit the Shop Drawing(s) to the Engineer. The resubmittal shall incorporate the Engineer's comments highlighted on the Shop Drawing.
6. "Rejected" or “Not Approved” - Contractor shall resubmit Shop Drawing to the Engineer for review.
7. Resubmittals shall be handled in the same manner as first submittals. On resubmittals the Contractor shall address, in writing or on resubmitted Shop Drawings, revisions other than the corrections requested by the Engineer on previous submissions. The Contractor shall make any and all corrections required by the Engineer.
8. If the Contractor considers any correction indicated on the Shop Drawings to constitute a change to the Contractual Documents, the Contractor shall give written notice thereof to the Engineer.
9. When the Shop Drawings are complete to the satisfaction of the Engineer, the Contractor shall provide construction in accordance therewith and shall make no further changes therein except upon written instructions from the Engineer.
10. Only the Engineer shall utilize the color "red" in marking Shop Drawing submittals.
C. Shop Drawing Submittal(s):
1. Shop Drawings shall be complete and detailed and shall include but not be limited to fabrication, erection and setting drawings and schedule drawings, manufacturer's scale drawings, and wiring and control diagrams. Cuts, catalogs, pamphlets, descriptive literature, and remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-5 performance and test data, shall be considered only as supportive information. As used herein, the term "manufactured" applies to standard units usually mass-produced; and "fabricated" means items specifically assembled or made out of selected materials to provide individual design requirements.
2. Manufacturer's catalog sheets, brochures, diagrams, illustrations and other standard descriptive data shall be clearly marked and identify pertinent materials, products or models. Delete information that is not applicable to the Contract by striking or cross-hatching.
3. Data on materials and equipment shall include, but not be limited to, materials and equipment lists, catalog data sheets, cuts, performance curves, diagrams, materials of construction and similar descriptive material. Materials and equipment lists shall give, for each item, the name and location of the Supplier or Manufacturer, trade name, catalog reference, size, finish and all other pertinent data.
4. All mechanical and electrical equipment furnished by the Contractor shall include a list of the equipment name, address and telephone number of the Manufacturer's Representative and recommended service companies.
1.05 LIST OF DRAWINGS:
All work shall conform to the drawings listed on the drawing cover sheets and as listed in the Contractual Documents. Contractor will be provided a separate signed/sealed certified building inspector set of plans that will be required to be kept on site at all timesand must be turned over to the owner with the as-builts.
1.06 SUBSTITUTIONS:
A. Contractor's Base Bid shall be per Drawings and Specifications.
1. Substitutions for products shall be requested during the bidding period by submitting to the Owner a written substitution request a minimum of seven
(7) days prior to Bid Date.
2. Owner shall consider requests utilizing this Section for substitution of Products in place of those specified.
3. Substitutions submitted seven (7) days prior to Bid Date shall be included in an Addendum if accepted.
4. After the award of the Contract, requests shall be considered only in case of Product unavailability or other conditions beyond the control of the Contractor, or the request is part of the Value Engineering Cost Proposal in accordance with Section 01240.
remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-6
B. Submit separate requests for each substitution. Support each request with:
1. Complete data substantiating compliance of proposed substitution with requirements stated in the Contractual Documents:
a. Product identification, including Manufacturer's name, address and telephone number.
b. Manufacturer's literature identifying:
1. Product description.
2. Reference standards.
3. Performance and test data.
c. Samples, as applicable.
d. Name and address of similar applications on which Product has been utilized, and date of each installation.
2. Itemized comparison of the proposed substitution with product specified;
list pertinent variations.
3. Data relating to changes in construction schedule.
4. Any effect of substitution on separate contracts.
5. List of changes required in other work or Products associated with this
Contract.
6. Accurate cost data comparing proposed substitution with product specified.
a. Amount of any net change to Contract Sum.
7. Associated license fees or royalties.
8. Availability of maintenance services, sources and/ or replacement materials.
C. Substitutions shall not be considered for acceptance when:
1. Substitutions are depicted or implied on Shop Drawings or product data submittals without a formal request from Contractor.
2. In judgment of Engineer, substitutions do not include adequate information required for a complete evaluation.
3. Requested after Contract Award directly by a Subcontractor or Supplier.
D. Substitute products shall not be ordered or installed without written acceptance from Engineer.
remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-7
E. Engineer shall determine acceptance of proposed substitutions.
1.07 CONTRACTOR'S REPRESENTATION
A. Substitution requests from Contractor verifies:
1. Contractor has investigated the proposed product and verifies that it is equivalent or superior to that specified in the Contractual Documents.
2. Contractor shall provide equivalent warranties or bonds for substitutions as that for products specified.
3. Contractor shall coordinate installation of accepted substitution into the
Contract, and shall make such changes as shall be required for the Contract to be complete in all respects.
4. Contractor waives claims for any and all additional costs related to the substitutions.
5. Contractor‘s cost data is complete and includes related costs under this Contract, but not:
a. Costs under separate contracts.
b. Costs for redesign or revision of Contract Documents.
6. Cost data shall not be submitted if request is for inclusion in an addendum. Request after Contract award shall contain complete cost comparison.
1.08 EXISTING BULKHEAD AND PIER: Not applicable.
1.09 NAVIGATION CHANNEL: Not applicable.
1.10 TRANSPORTATION: Not applicable.
1.11 TEMPORARY UTILITIES: Contractor shall supply all utilities and sanitary facilities during the construction period. Before final acceptance, temporary connections and piping installed by Contractor shall be removed in a manner satisfactory to the Engineer
1.12 LAYOUT OF WORK-SURVEY LINES AND GRADES: The Engineer shall indicate on drawings alignment markers for horizontal control and benchmarks or reference elevations for vertical control. These benchmarks and elevations become the sole responsibility of the Contractor, and if replacement is required, as a result of the Construction and in the judgment of the Engineer, the Contractor shall pay for the cost of replacement. All layout of work-survey lines and grades shall be performed by a Professional Surveyor, Registered in the State of Florida. The Surveyor shall verify alignment with existing structures and/or grades. Costs of survey and Surveyor shall be remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-8 borne by the Contractor.
1.13 CONSTRUCTION AND PERMITS: Permits apply to this project and must be strictly complied with during the contractor's performance of the work. As in all construction, a contractor must adhere to EPA guidelines mandated to the State of Florida for NPDES General Permit relative to Stormwater Management and file the required certifications.
When directed by the Building Official, contractor must submit for a building permit (see application at the end of this section). In addition, construction shall be in strict accordance with issued regulatory permits and other applicable permits for all work.
Building permits are issued through the Canaveral Port Authority Building Department.
Building permit fees will be paid by the Port Authority. All reinspection fees will be paid by the contractor. Contractor shall comply with the conditions of all permits relating to the construction.
1.14 SCHEDULE: The Contractor shall provide a Critical Path Method (CPM) schedule for the entire project. Submit a paper copy and an electronic color copy, in PDF format, of the schedule. The Contractor shall not obstruct any functions or operations of the Port Authority or its Tenants.
Contractor may work evenings as necessary (6:00 p.m. to 4:00 a.m.) to complete project within the allotted time frame unless prohibited by the permits. No additional compensation for evening or night work will be made. Contractor shall provide all necessary lighting and electrical power. However, betweenMarch 1 and October 30, the lighting shall conform to the Canaveral Port Authority’s Exterior Light Management and Security Alternatives Plan.
1.15 ACCESS FOR PERSONS WITH PHYSICAL DISABILITIES: Contractor shall comply with Americans with Disability Act (ADA), including the ADA Accessibility Guidelines.
Documents are available from the U.S. Department of Justice, Civil Rights Division,
(202) 514-0301, and from the Architectural and Transportation Barriers Compliance Board (ATBCB), (800) USA-ABLE.
1.16CONSTRUCTION PHOTOGRAPHS: Contractor shall take digital photographs of the project. All digital photos shall be date stamped with the date the photo was taken.
Photographs shall be submitted to Engineer inJPEG format on a CD Rom. All costs for digital photographs shall be borne by the Contractor.
A. Existing Conditions: All areas within project boundaries.
B. Progress Photos: Contractor shall provide Owner with weekly progress photos of areas of significant change since the last photo.
remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-9
C. Underground Utilities: Photograph existing underground utilities as they are encountered and photograph new utilities as they are installed.
D. Maintenance of Traffic
E. As-Built
F. Aerial Photographs (JPEG on CD), periodic (no less than monthly) and as-built.
G. Digital Video recording of Existing Conditions.
H. Live feed of project available on the internet.
I. Provide a time-lapse of Project from start to completion at the end of the project.
1.17PROJECTMEETINGS: Project Meetings will normally be conducted by the Engineer in the Port Authority’s Engineering Conference Room. Special meetings may be called and held on the project site. At a minimum, Contractor and its’ Superintendent shall attend all meetings. Other concerned parties, such as, but not limited to, major subcontractors, suppliers, manufacturers, and Contractor’s Consultants, shall be required to attend the meetings, if requested by the Engineer. All participants at the meetings shall be familiar with the Project and authorized to conclude matters relating to the Work. All costs associated with the meeting attendance shall be borne by the Contractor.
A. Preconstruction Meeting: This meeting will be held prior to the start of any construction. Contractor shall be prepared to review and discuss his CPM schedule, submittal schedule, schedule of values, sequence of construction, and other items of significance that could affect the progress of the Work.
B. Progress Meetings: These meetings will be conducted by the Construction
Manager and held weekly during the entire Project at the Construction Manager’s Project Site Facility. The Construction Manager shall be prepared to review and discuss the progress since the last meeting, updates to the CPM schedule, status of submittals, maintenance of traffic, utility outages, material and equipment deliveries, quality and work standards, housekeeping, change orders, pay applications and back-up documentation, and other items that could affect the progress of the Work.
C. Pre-Installation Meetings: These meetings will be held at the site before each remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-10 construction activity that requires coordination with other construction or as specified in the technical specifications. The Installer and representatives of manufacturers and fabricators involved in or affected by installation, and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Contractor and Contractor’s attendees shall be prepared to review the progress of other construction activities and preparations for the particular activity under consideration at each pre-installation meeting.
1.18 DAILY/WEEKLY PROGRESS REPORTS: Contractor shall submit paper copies of
Daily Progress Reports in a bundled package at the Progress Meeting. Electronic copies of the reports, in PDF format, can be either emailed to the Port Authority's designee identified in the Pre-construction meeting or providedon a CD along with the paper copies.
1.19START-UP AND DEMONSTRATION
A. COMPONENT TEST AND CHECK-OUT
1. Start-up Certification: Prior to system start-up, successfully complete all the testing required of the individual components of the Work. Submit six
(6) copies of Check-Out-Memo’s for each individual component or piece of equipment, signed by the Contractor or the subcontractor and the manufacturer’s representative along with one (1) electronic copy in PDF format. All copies of the Operation and Maintenance Manuals must be provided before start-up may begin. These forms shall be completed and submitted before Instruction in Operation to Owner or a request for imitating any final inspections. Insert one (1) coy of this form into the applicable section of each Operation and Maintenance Manual.
2. Demonstrate to the Design Engineer and Owner that all temporary jumpers and/or bypasses have been removed and that all of the components are operating under their own controls as designated.
3. Coordinate start-up activities with the Owner and with the Design Engineer prior to commencing system start-up.
B. START-UP
1. Confirm that all equipment is properly energized, that the valves are set to their normal operating condition and that the flow path through the new Work is unobstructed.
2. Slowly fill each hydrostatic structure in the process flow stream with water.
remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-11
3. Initiate start-up and training in accordance with and with the use of the operation and maintenance manuals.
4. Observe the component operation and make adjustments as necessary to optimize the performance of the Work.
5. Coordinate with Owner for any adjustments desired or operational problems requiring debugging.
6. Make adjustments as necessary.
C. START-UP DEMONSTRATION AND TESTING
1. After all Work components have been constructed, field tested, and started up in accordance with the individual Specifications and manufacturer requirements, and after all Check-Out Forms have been completed and submitted, perform the Start-Up Demonstration and Testing. The demonstration period shall be held upon completion of all systems at a starting date to be agreed upon in writing by the Owner or his representative. Prior to beginning the start-up demonstration testing, the Contractor shall submit a detailed schedule of operational circumstances for approval by the Design Engineer. The schedule of operational circumstances shall describe, in detail, the proposed test procedures for each piece of equipment. The demonstration test procedures shall generally follow the example Demonstration Test Procedure Form.
Provide similar test procedure forms for each piece of equipment or section of the Work to include all particular aspects and features of that equipment or section of the Work as specified in the Technical Sections of the Specifications.
2. The Start-Up Demonstration Testing will be conducted for seven (7) consecutive days. The Work must operate successfully during the seven
(7) day testing period in the manner intended. If the Work does not operate successfully, or if the start-up is interrupted due to other contracts, the problems will be corrected and the test will start over from day one.
The party causing the interruption will be subject to the assessment of actual damages due to delay.
3. During the start-up demonstration period, operate the Work, instruct designated personnel in the function and operation of the Work, and cause various operational circumstances to occur. Demonstrate the essential features of the equipment and its relationship to other equipment. The approved schedule of operational circumstances and Demonstration Test Procedures Forms will be used as the agenda during the Start-Up Demonstrations Testing periods for all equipment and sections of the Work. Coordination of the demonstration test schedule will remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-12 be accomplished through the Owner.
4. Acceptability of the Work’s performance will be based on the Work performing as specified under these actual and simulated operating conditions, to provide facility functioning as intended and as defined in the Contract Documents. The intent of the start-up demonstration and testing is for the Contractor to demonstrate to the Owner and the Design Engineer that the Work will function as a complete and operable system under normal, as well as emergency operating conditions, and is ready for final acceptance.
5. Demonstrate the essential features of the whole system as it applies to the Work, including the mechanical equipment, piping, structures, finishes, controls, instrumentation, power distribution and lighting systems. Use the approved procedures and circumstances to include on a punch list attached to the Certificate of Completed Demonstration. The system shall be demonstrated only once, after completion of start-up tests. If circumstances arise that interrupt the test procedures (such as weather, unforeseen process problems, or problems caused by the Contractor whether or not the problems are the fault of the Contractor, etc.,) then the test shall be terminated and rescheduled to a later date after the problem is corrected. The test shall be run in its entirety if so directed by the Design Engineer.
6. Demonstrate the essential features of all the mechanical systems including, but not limited to, the following as they apply to the Work:
a. Mechanical Piping System
b. Submersible Wastewater Pumps
7. Demonstrate the essential features of all electrical systems including, but not limited to the following as they apply to the Work:
a. Electrical systems controls and equipment:
1. Electrical power equipment
2. Motor control centers
3. Motor control devices
4. Relays
5. Special transformers
6. Stating devices
7. Emergency Generator.
b. Panel boards:
remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-13
1. Distribution panels.
2. Main panels, power panels.
3. Switchboard.
c. Wiring devices:
1. Face plates.
2. Low-voltage controls.
3. Outlets: convenience, special purpose.
4. Switches: regular, time.
8. Upon successful completion of the Start-up, Demonstration and Testing, the Owner’s personnel will receive the specified training for each system.
Training of the Owner’s personnel will not be considered valid unless it takes place using a system that has successfully passed the Start-up, Demonstration and Testing.
Upon completion of all specified operator training, the Contractor shall submit to the Design Engineer six (6) copies of the Certificate of Completed Demonstration Form, for each item of equipment or system in the Work, signed by the Contractor, Subcontractor, Design Engineer, and the Owneralong with one (1) electronic copy in PDF format.. Insert one (1) copy of this form in the applicable section of each Operation and Maintenance Manual..
1.20 SITE CONSTRAINTS: Contractor shall be responsible for securing his work sites with appropriate fencing, barriers, gates, and access control. Contractor will be required to relocate and/or reconfigure his site security measures as the work progresses to accommodate operational changes if required by the Owner.
Laydown area at the project is limited as depicted in the project drawings. Contractor is responsible for the security of his laydown areas and shall provide a security fence that surrounds his laydown areas. Roadways at and near the site are in continuous use and shall not be blocked by the Contractor or his operationsor equipment.
1.21 BORROW AREA: Not used.
1.22 SECURITY-ACCESS BADGING: All Contractor and Subcontractor employees requiring access to the secure areas of the Port (as depicted on the map at the end of this section) must meet the following requirements:
A. WHERE TO OBTAIN INFORMATION: The Port Canaveral Business Purpose remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-14
Badge application, application guidelines, training criteria, and fee information is located on the Port’s website at https://www.portcanaveral.com/Business/Public- Safety-Security. From the homepage of the website click on the “Security/Badging” link along the left hand column of the page to access the information.
B. PORTCANAVERAL BUSINESS PURPOSE BADGE:
1. Application: Complete a Badge Credential Application (Rev. 6/28/2011), which includes an original signature of an authorized agent (see Section F below).
2. Completion of Security Training: Complete the appropriate training course, and provide a printed copy of the transcript to the Badging office upon completion. This must be provided prior to receiving up your badge.
3. Payment of Fees: Badges may be picked up upon payment of the appropriate fees (No Charge for TWIC Holders, and $25 for Non-TWIC holders). Make checks payable to “Canaveral Port Authority” with “215 training” noted on the check.
C. “VISITOR OR CONTRACTOR’S” BADGE:
1. Visitor's Badge: Good for daily access, and may not be issued more than five (5) times within a ninety (90) day period (referred to as the "5/90 Rule") without an exemption. A pre-authorization is required in advance of arrival.
2. Contractors Badge: Issued to contractors who may require access beyond 5 times in a 90 day period, and the project is of limited duration. A special Visitor/Contractor application must be completed. The application is available on the website under the “Contractor” section or from the Badging Office. No training or application fee is required to obtain the badge.
D. LOST BADGES/Transfer: The fee is $35.00
E. SECURITY TRAINING REQUIREMENT:
Security training is a pre-requisite for all applicants seeking a Port Canaveral Business Purpose Badge. The training courses are grouped into the following categories:
TYPE TRAINING
REQUIRED GROUP REQUIREMENTS METHOD OF
INSTRUCTION
RECERTIFICATION
105.210 Security
Officer Course
• Persons who have a TWIC and perform TWIC escorts.
CPA Classroom Upon Expiration of TWIC Badge https://www.portcanaveral.com/Business/Public-Safety-Security https://www.portcanaveral.com/Business/Public-Safety-Security remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-15
105.215 Port Employee Course
• Non- TWIC personnel and those who have a TWIC, but do not perform TWIC escorts.
* CPA Classroom
• TWIC Holder: Upon Expiration of the Badge.
• Non-TWIC Holder: Every five years.
Registration for 105.210 and 105.215 Training Courses:
Contact CPA Public Security (pss@portcanaveral.com) for a schedule of classes for 105.210 and 105.215.
F. AUTHORIZED SIGNATURE FORM FOR BADGES: Prior to submitting a badge application, a company representative must submit an Authorized Signature Form to the Engineering Department listing the names of those authorized to sign the applications on the company’s behalf. A copy of the form is located at the end this section. Once signed, the Engineering Department will forward the completed form to the Port Canaveral Badging office for processing.
G. BADGE APPLICATION COMPLETION: Persons designated on the Authorized
Signature Form shall ensure that a complete Badge Application is presented to Port Badging Office by the applicant. (Copies are permissible).
H. 5/90 RULE: Contractor and Subcontractor employees requiring a temporary badge shall submit an Access Control Pre-Authorization Request form, signed by the person designated to do so under paragraph "D" above. A copy of the form is located at the end of this section. This form shall be submitted to Port Control via e-mail: portbadging@bcso.us no less than 24 hours prior to the requested access date.
I. RESPONSIBILITY FOR FEES: All fees associated with compliance for Security
Badging shall be borne by the Contractor. Badging fees shall not be prorated or reduced for periods less than one year.
J. TWIC BADGE REQUIREMENT: In addition to the Canaveral Business
Purpose Badge, referenced above, the U.S. Coast Guard requires all contractor and subcontractor employees to obtain a Transportation Workers Identification Credential (TWIC) badge for UNESCORTED access within the secure areas of the Port. Individuals who need unescorted access, and those who require frequent access to the secure areas of the Port in the course of their employment must obtain a TWIC.
To pre-register for an enrollment appointment, or to get additional information about TWIC guidelines, click on the following link www.tsa.gov/twic. To pre-mailto:pss@portcanaveral.com mailto:portbadging@bcso.us?subject=Port%20Badging%20Inquiry http://www.tsa.gov/twic remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-16 enroll and schedule an appointment, click on the pre-enrollment link at the top of the web-sites main page.
Prior to coming to the TWIC office here at Port Canaveral for your scheduled appointment, make sure you have all your required enrollment documents, and the printed “Pre-Enrollment Receipt” obtained from the web-site at the time of your enrollment. This is your confirmation of your appointment.
K. TWIC ESCORTSREQUIREMENTS/GUIDELINES:
Up to 10 employees are allowed at the project site without a TWIC badge, provided they are continuously monitored by an individual with a valid TWIC badge credential who has completed the 105.210 training. The contractor must ensure the project site does not go beyond the 10 to 1 ratio of non-TWIC badge personnel to TWIC badged personnel in "Secure Areas".
A 5 to 1 ratio is required in "Restricted Areas" within the Port. Personnel without TWIC badges must be met at the gate and be escorted to the project site by an individual meeting the above requirements. All deliveries must be screened and pre-authorized prior to entering a secure/restricted area.
L. SECURITY GUARD COSTS: If a contractor cannot meet the TWIC badging or escort requirements, then the contractor will provide an appropriate number of class “D” licensed security guards to meet the escort requirements specified under paragraph “H” above. These guards will be provided at the contractors own expense.
M. RETURN OF BADGES: Contractors are responsible for the return of the Port Badges issued to their employees upon the completion of the project or the site-specific job assigned to the employee; or upon leaving employment of the contractor.
1.23 PROJECT CLOSEOUT
A. SECTION INCLUDES: Administrative and procedural requirements for project closeout.
1. Inspection procedures
2. Project record document submittals.
3. Final cleaning.
B. SUBSTANTIAL COMPLETION
remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-17
1. Before requesting inspection for certification of Substantial Completion, complete the following. List exceptions in the request.
a. If 100 percent completion cannot be shown, include a list of incomplete items, the value of incomplete construction, and reasons the Work is not complete.
b. Advise Owner of pending insurance change-over requirements.
c. Submit specific warranties, workmanship bonds, maintenance agreements, final certifications and similar documents.
d. Obtain and submit releases enabling the Owner unrestricted use of the Work and access to services and utilities; include occupancy permits, operating certificates and similar releases.
e. Submit record drawings, maintenance manuals, final project photographs,and similar final record information.
f. Deliver tools, spare parts, extra stock, and similar items.
g. Make final change-over of permanent locks and transmit keys to the Owner. Advise the Owner's personnel of change-over in security provisions.
h. Complete start-up testing of systems, and instruction of the Owner's operating and maintenance personnel. Discontinue or change over and remove temporary facilities from the site, along with construction tools, mock-ups, and similar elements.
i. Complete final clean up requirements, including touch-up painting.
Touch-up and otherwise repair and restore marred exposed finishes.
2. When the Contractor considers the Work to be substantially complete, he shall submit a written notice to the Engineer that the Work, or designated portion of the Work, is complete and ready for inspection.
3. Within 5 days of receipt of a request for inspection, the Engineer will either proceed with inspection or advise the Contractor of unfulfilled requirements. When the Engineer and Owner concur that the Work, or designated portion of the Work, is substantially complete, the Engineer will prepare the Certificate of Substantial Completion following inspection.
4. Should the Engineer determine that the Work is not substantially complete, he will advise the Contractor of construction or other requirements that must be completed or corrected before the certificate will be issued.
remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-18
a. The Engineer will repeat inspection when requested and assured that the Work has been substantially completed.
b. Results of the completed inspection will form the basis of requirements for final acceptance.
C. FINAL COMPLETION
1. When Contractor considers the Work to be complete, he shall submit written certification to the Engineer that the Work is completed and ready for final inspection. Include the following:
a. Submit the final payment request with releases and supporting documentation not previously submitted and accepted. Include certificates of insurance for products and completed operations.
b. Submit an updated final statement, accounting for final additional changes to the Contract Sum.
c. Submit a certified copy of the Engineer's final inspection list of items to be completed or corrected, stating that each item has been completed or otherwise resolved for acceptance, and the list has been endorsed and dated by the Engineer.
d. Submit final meter readings for utilities, a measured record of stored fuel, and similar data as of the date of Substantial Completion, or when the Owner took possession of and responsibility for corresponding elements of the Work.
e. Submit consent of surety to final payment.
f. Submit a final liquidated damages settlement statement.
g. Submit evidence of final, continuing insurance coverage complying with insurance requirements.
2. The Engineer will inspect the Work upon receipt of notice that the Work, including inspection list items from earlier inspections, has been completed, except items whose completion has been delayed because of circumstances acceptable to the Engineer.
a. Upon completion of inspection, the Engineer will prepare a certificate of final acceptance, or advise the Contractor of Work that is incomplete, or of obligations that have not been fulfilled but are required for final acceptance.
b. If necessary, re-inspection process will be repeated.
D. REINSPECTION FEES
remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-19
1. Should the Owner perform re-inspections due to failure of the Work to complywith the claims of status of completion made by the Contractor:
2. Contractor will compensate the Owner for such additional services.
3. Owner will deduct the amount of such compensation from the final payment to the Contractor.
E. RECORD DOCUMENT SUBMITTALS
1. Maintain at the site one complete set of record documents; protect from deterioration and loss in a secure, fire-resistive location.
a. Provide access to record documents for the Engineer's reference during normal working hours.
b. Label each document "PROJECT RECORD" in 2 inch high printed letters.
c. Do not use for construction purposes.
2. Record Drawings: Refer to Sections017700 and 017823.
3. Record Specifications: Maintain one complete copy of the Project Manual, including addenda, and one copy of other written construction documents such as Change Orders and modifications issued in printed form during construction.
a. Mark these documents to show substantial variations in actual Work performed in comparison with the text of the Specifications and modifications.
b. Give particular attention to substitutions, selection of options and similar information on elements that are concealed or cannot otherwise be readily discerned later by direct observation.
c. Note related record drawing information and Product Data.
4. Record Product Data: Maintain one copy of each Product Data submittal.
a. Mark these documents to show significant variations in actual Work performed in comparison with information submitted. Include variations in products delivered to the site, and from the manufacturer's installation instructions and recommendations.
b. Give particular attention to concealed products and portions of the Work which cannot otherwise be readily discerned later by direct observation.
c. Note related Change Orders and mark-up of record drawings and Specifications.
remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-20
5. Record Sample Submitted: Immediately prior to the date or dates of Substantial Completion, the Contractor will meet at the site with the Engineer and the Owner to determine which of the submitted Samples that have been maintained during progress of the Work are to be transmitted to the Owner for record purposes.
Comply with delivery to the Owner's Sample storage area.
6. Record Survey: Refer to Sections017700 and 017823.
7. Miscellaneous Record Submittals: Refer to other Specification Sections for requirements of miscellaneous record-keeping and submittals in connection with actual performance of the Work.
8. At Contract close-out, deliver two (2)hard copies and one electronic copy, in PDF format, of Record Documents to Engineer for Owner. Accompany submittal with transmittal letter in duplicate containing the following information:
a. Date.
b. Project title and number.
c. Contractor's name and address.
d. Title and number of each Record Document.
e. Signature of Contractor or his authorized representative.
F. FINAL CLEANING
1. Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to the condition expected in a normal, commercial building cleaning and maintenance program.
2. Complete the following cleaning operations before requesting inspection for Certification of Substantial Completion and maintain until final completion, except in areas occupied or designated by Owner.
a. Remove labels that are not permanent labels.
b. Clean transparent materials, including mirrors and glass in doors and windows. Remove glazing compound and other substances that are noticeable vision-obscuring materials. Replace chipped or broken glass and other damaged transparent materials.
c. Clean exposed exterior and interior hard-surfaced finishes to a dust-free condition, free of stains, films and similar foreign substances. Restore reflective surfaces to their original reflective condition.
d. Leave concrete floors broom clean.
e. Vacuum carpeted surfaces.
f. Wipe surfaces of mechanical and electrical equipment. Remove excess lubrication and other substances.
g. Clean plumbing fixtures to a sanitary condition.
h. Clean light fixtures and lamps.
remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-21
i. Clean the site, including landscape development areas, of rubbish, litter and other foreign substances.
j. Sweep paved areas broom clean; remove stains, spills and other foreign deposits.
k. Rake grounds that are neither paved nor planted, to a smooth even-textured surface.
3. Engage an experienced exterminator to make a final inspection and rid the
Project of rodents, insects and other pests.
4. Remove temporary protection and facilities installed for protection of the Work during construction.
5. Comply with regulations of authorities having jurisdiction and safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on the Owner's property. Do not discharge volatile, harmful or dangerous materials into drainage systems. Remove waste materials from the site and dispose of in a lawful manner.
6. Where extra materials of value remaining after completion of associated Work have become the Owner's property, arrange for disposition of these materials as directed.
1.24 WARRANTIES AND BONDS
A. SCOPE OF WORK
Compile specified warranties and bonds, as in Article 4 of the General Conditions and as specified in these Specifications.
B. SUBMITTAL REQUIREMENTS
1. Assemble warranties, bonds and service and maintenance contracts, executed by each of the respective manufacturers, suppliers, and subcontractors
2. Number of original signed copies required: Two (2) each.
3. Table of Contents: Neatly typed, in orderly sequence. Provide complete information for each item.
a. Product of work item.
b. Firm, with name of principal, address and telephone number.
c. Scope.
d. Date of beginning of warranty, bond or service and maintenance remains subject to contract negotiation, Consultant’s Proposal, and other terms and conditions.
WATERSIDE Construction Management at Risk Services for Continuing Services Contract
011116-22 contract.
e. Duration of warranty, bond or service maintenance contract.
f. Provide information to Owner:
1. Proper procedure in case of failure.
2. Instances which might affect the validity or warranty or bond.
g. Contractor, name or responsible principal, address and telephone number
C. FORM OF SUBMITTALS
1. Prepare in duplicate packets.
2. Format:
a. Size 8-1/2 inches by 11 inches, punch sheets for standard three (3) post binder.Fold larger sheets to fit into binders.
b. Cover: Identify each packet with typed or printed title
“WARRANTIES AND BONDS”. List:
1. Title of Project.
2. Name of Contractor.
3. Binders: Commercial quality, three (3) postbinder, with durable and cleanable plastic coversand maximum post width of two (2) inches.
c. A labeled CD with warranties and bonds completely scanned in
PDF format.
D. WARRANTY SUBMITTALS REQUIREMENTS
1. For all major pieces of equipment, submit a warranty from the equipment manufacturer.
This is the start of the file's text. The full file is on GovTribe.