RFQ 2024-27 Addendum -1.pdf

PDF 295 KB Posted

Attached to
Cost-Benefit Evaluation of State Surplus Property Program
Solicitation number
S-10700-00010016
Issued by
Marion County, Oregon

About this file

This is an addendum to a Request for Quotes issued by Clackamas County for on-call Clackamas Broadband Exchange (CBX) residential drop construction services funded through the American Rescue Plan Act (ARPA). Addendum Number 1, issued on April 18, 2024, modifies Section 4 of the original RFQ by replacing the CBX Drop Costs sheet with a comprehensive pricing schedule that establishes unit costs for various broadband infrastructure construction activities. The pricing schedule includes line items for boring operations using 1-inch and 2-inch rolled conduit (with and without rock), trenching with conduit sticks of various lengths, rock plowing, aerial cable installation, vault construction in three different sizes, fiber cable pulling in conduit, fusion splicing for single and multiple fibers, case installation, risers, and home installation services that include coordination with homeowners, building entry, fiber drop coiling, ONT mounting, and weatherproofing of all penetrations.

The addendum specifies that CBX will provide fiber cable and optical network terminals (ONT) for home installations, while contractors are responsible for all other materials required for building entry. The pricing structure requires contractors to submit firm unit costs for each line item on the CBX Drop Costs sheet, with completed quotes to include the firm name, printed name of the authorized representative, and submission date. No specific response deadline, award date, or contract term information is provided in this addendum document, as these details remain governed by the original RFQ terms.

View the file

Other files

File Type Posted
RFP Evaluation Surplus Property_Final.pdf PDF
RFP_AttA_Sample Contract~1.docx DOCX document
RFP_AttE_Price Proposal~2.docx DOCX document
RFP_AttG_Responsibility Inquiry~1.docx DOCX document
RFP_AttB_Disclosure Exemption Affidavit.doc DOC document
RFP_AttC_Proposer Information and Certification sheet.doc DOC document
RFP_AttF_Certified Disadvantaged Business Outreach Plan.doc DOC document
Questions and Answers_4.18.2024.docx DOCX document
Revised Notice of Intent to Award.docx DOCX document
RFP_AttD_Reference Check~1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PH: 503-742-5400 WWW.CLACKAMAS.US

REQUEST FOR QUOTES #2024-27

On-Call Clackamas Broadband Exchange (CBX), American Rescue Plan Act (ARPA) Residential Drop Construction

ADDENDUM NUMBER 1

April 18, 2024

On April 18, 2024, Clackamas County (“County”) published Request for Quotes #2024-27 (“RFQ”). The County has found that it is in its interest to amend the RFQ through the issuance of this Addendum #1. Except as expressly amended below, all other terms and conditions of the original RFQ and subsequent Addenda shall remain unchanged.

1. The following changes are hereby made to Section 4. Quote, Item C.

a. Remove and replace the CBX Drop Costs sheet with the following:

CBX Drop Costs Drop Construction cost per foot Boring 1 in rolled conduit 2 in rolled conduit 1 in rolled conduit rock 2 in rolled conduit rock Trenching 1 in conduit stick, 20 ft 1 in conduit stick, 10 ft 2 in conduit stick, 20 ft 2 in conduit stick, 10 ft Trench or Plow Rock 1” conduit Trench or Plow Rock 2” conduit Plow 1 in conduit 2 in conduit Aerial self support single fiber cable self support 12 count fiber cable strand & lash, single fiber cable Strand & lash, 12 count cable Vault (Unit Cost) 24x36x24 vault 24x36x36 vault 17x30x18 vault Pull Fiber Cable in conduit Pull fiber cable in 1" conduit Pull fiber cable in 2" conduit Splicing (Unit Cost) Fusion Splice (1-12 fibers)

PH: 503-742-5400 WWW.CLACKAMAS.US

Fusion Splice (13-96 fibers) Re-enter Existing Case Install New Aerial Case Install New Vault Case Risers Risers 1” Risers 2” Home Install (Unit Cost)

Unit cost to coordinate and perform a home install.

This would entail coordinating a time with the home owner, discussing location of building entry, performing the entry and coiling the new fiber drop in the house and mounting the ONT. All building penetrations need to be weather proof to ensure moister does not enter the home. CBX will provide the fiber cable and ONT. All other materials needed for the building entry will be the reasonability of the contractor.

Firm Name:____________________________________

Print Name:_______________________________

Date:____________________________________

End of Addendum #1