RFQ 1333ND21QNB610162.pdf
PDF 2 MB Posted
- Solicitation number
- 1333ND21QNB610162
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT 0005.docx | DOCX document | |
| AMENDMENT 0004.docx | DOCX document | |
| Amendment 0002.docx | DOCX document | |
| Drawing Number 002-3073.pdf | ||
| Dawing Number 002-2858.pdf | ||
| Amendment 0001.docx | DOCX document | |
| NIST COVID Procedures.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ IFB RFP
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NUMBER PAGE OF
2. CONTRACT NO. 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect calls)
8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODEFACILITY
CODE
CODE
TELEPHONE NO.
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
SEE ADDENDUM
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
29. AWARD OF CONTRACT: REF.
DATED . YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA - FAR (48 CFR) 53.212
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
OFFER
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
17a CONTRACTOR/
OFFEROR.
CODE
8 (A)
SIZE STANDARD:
NAICS:
% FOR:SET ASIDE:UNRESTRICTED OR
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SMALL BUSINESS
10. THIS ACQUISITION IS
EDWOSB
SMALL BUSINESS PROGRAM
STANDARD FORM 1449 (REV. 2/2012) BACK
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
40. PAID BY
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED
CORRECT FOR
PARTIAL FINAL
37. CHECK NUMBER
38. S/R ACCOUNT NO. 39. S/R VOUCHER NUMBER
36. PAYMENT
COMPLETE PARTIAL FINAL
SCHEDULE Continued
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 Detailed engineering design, fabrication, installation and testing of double-walled warm deuterium gas piping per Statement of Work.
Tasks and Milestones per SOW.
PR NUMBER: NB610010-21-01141
SHIP TO:
NATIONAL INST OF STDS AND TECHNOLOGY
BUILDING 301 SHIPPING AND RECEIVING
100 BUREAU DRIVE
GAITHERSBURG MD 20899-0001
FOB : Destination
1.00 JB
PAGE 3 OF 77 1333ND21QNB610162
Table of Contents
Statement of Work
Technical Specifications
Milestone Payment Schedule
Drawing 002-0030 R15
Drawing 002-2858
Drawing 002-2866
Drawing 002-3071
Drawing 002-3072
Drawing 002-3073
NIST Safety and Health Plan Guidelines
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
52.204-13SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018)
52.204-16COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (AUG 2020)
52.204-17OWNERSHIP OR CONTROL OF OFFEROR (AUG 2020)
52.204-18COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (AUG 2020)
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)
52.204-20PREDECESSOR OF OFFEROR (AUG 2020)
52.204-24REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT
(OCT 2020)
52.204-25PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR
EQUIPMENT (AUG 2020)
52.204-26COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES--REPRESENTATION (OCT 2020)
52.209-2 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS-REPRESENTATION (NOV 2015)... 71
52.209-11 REPRESENTATION BY CORPORATIONS REGARDING DELINQUENT TAX LIABILITY OR A FELONY CONVICTION UNDER
ANY FEDERAL LAW (FEB 2016)
52.212-1INSTRUCTIONS TO OFFERORS--COMMERCIAL ITEMS (JUN 2020)
52.212-2 EVALUATION--COMMERCIAL ITEMS (OCT 2014)
52.212-3OFFEROR REPRESENTATIONS AND CERTIFICATIONS--COMMERCIAL ITEMS (FEB 2021)
52.212-4 CONTRACT TERMS AND CONDITIONS--COMMERCIAL ITEMS (OCT 2018)
52.212-5CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS--COMMERCIAL
ITEMS (JAN 2021)
52.225-4BUY AMERICAN--FREE TRADE AGREEMENTS--ISRAELI TRADE ACT CERTIFICATE (FEB 2021)
52.225-25PROHIBITION ON CONTRACTING WITH ENTITIES ENGAGING IN CERTAIN ACTIVITIES OR TRANSACTIONS RELATING
TO IRAN--REPRESENTATION AND CERTIFICATIONS (JUN 2020)
52.232-8 DISCOUNTS FOR PROMPT PAYMENT (FEB 2002)
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUNE 2013)
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (DEC 2013)
52.237-2 PROTECTION OF GOVERNMENT BUILDINGS, EQUIPMENT, AND VEGETATION (APR 1984)
52.243-1 CHANGES--FIXED-PRICE (AUG 1987)
52.247-34 F.O.B. DESTINATION (NOV 1991)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
1352.201-70 CONTRACTING OFFICER?s AUTHORITY (APR 2010)
1352.233-70 AGENCY PROTESTS (APR 2010)
1352.233-71 GAO AND COURT OF FEDERAL CLAIMS PROTESTS (APR 2010)
1352.209-73 COMPLIANCE WITH THE LAWS (APR 2010)
1352.209-74 ORGANIZATIONAL CONFLICT OF INTEREST (APR 2010)
1352.246-70 PLACE OF ACCEPTANCE (APR 2010)
NIST LOCAL-54ELECTRONIC BILLING INSTRUCTIONS
PAGE 4 OF 77 1333ND21QNB610162
CLAUSES
Statement of Work
PAGE 5 OF 77 1333ND21QNB610162
STATEMENT OF WORK FOR THE
NCNR DEUTERIUM GAS PIPING ASSEMBLY
1(7)
PAGE 6 OF 77 1333ND21QNB610162
1. Background
The National Institute of Standards and Technology (NIST) plans to install a liquid deuterium (LD 2) cold neutron source that will replace an existing liquid hydrogen (LH2) cold neutron source. The LD2 source will shift the neutron spectrum to lower energies, with an average gain of 1.5 for neutrons with wavelengths greater than 0.4 nanometers (nm), and a gain of 2 at 0.9 nm. The LD2 cold neutron source architecture includes a LD2 cryostat, condenser heat exchanger, warm ballast tank, and interconnecting piping. This Statement of Work (SOW) outlines the requirements for the interconnecting piping. The specification ‘Technical Specification for the NCNR Deuterium Piping System.docx’ outlines the detailed technical requirements for this work.
2. Objectives
This objective of this effort is to obtain a length of warm deuterium gas piping and associated infrastructure to provide interconnection between a 16 m3 warm deuterium ballast tank and an existing section of warm gas piping at the NIST Center for Neutron Research (NCNR).
3. Scope
The scope of work to be performed under this effort is for the detailed engineering design, fabrication, installation and testing of double-walled warm deuterium gas piping and associated infrastructure. This piping will provide interconnection between a 16 m3 warm deuterium ballast tank and an existing section of warm gas piping. The inner piping shall be designed to transfer deuterium gas from the cold source deuterium condenser to the ballast tank. The deuterium piping shall be surrounded with a jacket that will be filled by NCNR with helium gas to prevent the possibility of undetected air from entering the deuterium system and to serve as the containment for any adverse deuterium-oxygen event.
4. Tasks
The contractor shall perform the following tasks within the scope of this project:
4.1. Develop a mechanical design for manufacturing the piping based on a conceptual CAD model supplied by the government and all requirements outlined in the project specification.
4.2. Develop a fabrication plan including all metallurgical processes, certifications and testing methodologies required, including detail design and shop drawings for the complete deuterium piping assembly.
4.3. Fabricate and install the deuterium piping assembly in accordance with the project specification.
4.4. Perform testing at the manufacturer’s facility and NCNR in accordance with the project specification.
4.5. Provide as-built drawings and 3-D CAD models (in a NCNR compatible format) in accordance with the specification.
4.6. Provide design calculations and analyses, a quality assurance and fabrication plan, and other documentation as outlined in the project specification and this SOW.
5. Project Milestones
Project Milestones/Estimated Completion Dates
Task Number
Work Milestones Projected Completion Date
4.1 Kick-off meeting - Virtual 2 weeks After
Receipt of Order
(ARO)
4.1, 4.2 Project Design Review 8 weeks ARO
4.3 Shop fabrication complete 6 months ARO
4.3 Installation Readiness Review 6 months ARO
4.3 NIST Safety and Health Plan 6 Months ARO
4.3 Field installation at NCNR complete 8 months ARO
2(7)
PAGE 7 OF 77 1333ND21QNB610162
4.4 NDE, leak and pressure test of assembly complete
9 months ARO
4.5 ,4.6 Site Acceptance Review, final project documentation package
9 months ARO
3(7)
PAGE 8 OF 77 1333ND21QNB610162
6. Deliverables
6.1. Hardware to be delivered by contractor
The contractor shall deliver a deuterium piping assembly in accordance with NIST document ‘Technical Specification for the NCNR Deuterium Piping Assembly.docx’, comprising of the following hardware subsystems
6.1.1. Piping
The contractor shall provide
Warm interconnecting piping between the ballast tank and ballast tank;
Helium piping jacket around the deuterium process pipe.
Ballast tank fill manifold assembly
6.1.2. Miscellaneous
The contractor shall provide:
Pipe supports for contractor provided piping assembly;
Complete documentation package for the piping assembly;
Packaging of all parts to be transported to NIST.
Structural and civil works to protect ballast tank and piping as detailed in the technical specification
6.2. Engineering and services to be provided by contractor
The contractor shall engineer and provide services with regard to the deuterium piping assembly in accordance with NCNR document ‘Technical specification for the NCNR Deuterium Piping Assembly.docx’, including but not limited to the following items:
6.2.1. General
The contractor shall provide:
Project management, scheduling, interface and quality control for the proposed deuterium piping assembly;
Design of all contractor provided piping including intermediate inspections, approvals, modifications and documentation;
Project meetings and fabrication checks at contractors and buyers’ premises;
Pressure and leak checks of contractor provided piping;
Planning for shipping, testing, installation of contractor provided piping, and acceptance testing;
Packing and shipping of all contractor provided piping and parts to be delivered to NIST site;
Providing all necessary quality documentation, inspection and test protocols, material certificates etc. for third party approval of contractor provided piping.
6.2.2. Site Services to be provided by contractor
The contractor shall provide:
Unloading of all piping and equipment delivered from contractor to the NIST site and placing them in their final position;
Organizing and renting of lifting and transport devices necessary installation of piping;
Removal and disposal of packaging material;
Installation of piping between NIST interface (warm deuterium ballast tank) and interface in room D200 of building 235;
4(7)
PAGE 9 OF 77 1333ND21QNB610162
Cleaning, purging, evacuating and filling with helium all contractor supplied piping;
Pressure and leak checks of contractor provided piping.
Arrange for any subcontract installation of structural and civil works to protect ballast tank and piping.
5(7)
PAGE 10 OF 77 1333ND21QNB610162
6.2.3. Minimum documentation to be provided by contractor
Documentation required below shall generally be submitted to NIST at least ten business days for review by NIST prior to the respective review meeting. NIST shall submit approval of the reviewed documents within five working days after receipt of the corrected documents from the contractor.
Drawings and schematics shall be submitted electronically to NIST.
A project plan outlining all steps in the execution of the project (at Kick-off meeting);
Schedule for the design, procurement, fabrication, assembly, delivery, installation, and acceptance testing, showing the major milestones and the critical path (at Kick-off meeting);
Design and layout drawings including all piping and interfaces (at Design Review meeting);
Acceptance test procedures description including leak and pressure tests (at Installation Readiness review);
Welding and examination procedure and qualifications (at Design Review meeting);
QA plan describing the specific quality-related work methods and means as well as the procedures for activities and responsibilities (at Design Review meeting);
All test and inspection reports from internal and external piping checks, pressure and leak checks (at Site Acceptance Review meeting).
6.3. Terms of delivery
All hardware deliverables are to be suitably packed, loaded and shipped to NIST site:
National Institute of Standards and Technology 100 Bureau Drive NCNR Building 235 Gaithersburg, MD 20899
DAP (delivered at place) to their final position.
The piping shall be installed, acceptance tested and fully functional available for NIST including all documentation no later than nine months after award of the contract (see section 9.).
6.4. Deliverable Schedule
Deliverable Description Quantity Date Completed 3 Deuterium piping assembly 1 assembly 8 months ARO 4 Testing of piping assembly 1 unit 9 months ARO
5,6 Final documentation package 1 package 1 month after acceptance by NCNR
7. Government-Furnished Property, Material, Equipment, or Information
NIST will provide the following to support completion of the deuterium piping assembly:
7.1. Piping
Final connection of deuterium piping to existing piping in building 235 room D200;
7.2. Miscellaneous
Lighting, heating, firefighting equipment, oxygen deficiency hazard (ODH) alarms.
7.3. Engineering and services
3-D CAD model of facility and conceptual design of deuterium piping assembly;
Project meetings and fabrication checks at contractors and buyers’ premises as required.
7.4. Site services
Access for contractor personnel to NIST site upon written notification;
Site safety training of contractor personnel when applicable;
Limited storage for contractor provided equipment;
6(7)
PAGE 11 OF 77 1333ND21QNB610162
Electrical power for contractor provided tools and equipment;
Access to sanitary facilities including fresh water;
Receipt and inspection of incoming parts, spares, documentation etc. and appropriate storage;
Free access and clearing paths in order to enable the contractor to place equipment delivered by the contractor in their final position.
8. Procedure in case of modification
In the event that contradictions in this Statement of Work or related documents and/or valid guideline are detected, NIST shall be informed immediately and the problem is to be resolved in writing and the relevant documents amended.
Both NIST and the contractor have the right to inform the other party of requests for modifications.
Each recommended modification must be clearly identified (by a unique number) and be used in all subsequent correspondence.
All modifications that affect specified values or other contractual content must be documented without delay with respective notice to NIST. For each such modification, the following information shall be provided:
Reason for modification;
Effect on the extend of work involved, documentation and drawings;
Effect on scheduling;
Effect on overall cost;
Other influenced factors (reliability, safety, maintenance);
Additional justifying documents.
Modifications shall not become valid until they are approved by the Contracting Officer through a written modification. In the event that modifications affect the price, schedule or guarantee, the contractor shall apply for appropriate correction of the contract through a signed amendment.
9. Security
Note that this work shall be performed at the NIST Center for Neutron Research. Contractors shall be required to obtain a temporary site access card and undergo radiation safety training prior to commencing work. To ensure timely access to the campus, the Contractor must send their information to the TPOC at least two (2) weeks prior to the start date.
10.Place of Performance
Work shall be performed at the NIST Center for Neutron Research, 100 Bureau Drive, building 235, Gaithersburg, MD 20899. Contractor shall perform all work during NIST normal access hours 6:00 AM to 7:00 PM.
11.Period of Performance
The period of performance, from the date of award to completion of installation and final acceptance by the NCNR shall not be longer than nine (9) months. If the project cannot be completed within this time due to delays by NCNR, additional time for completion shall be negotiated and agreed to by NCNR and the Contractor.
7(7)
Technical Specifications
PAGE 12 OF 77 1333ND21QNB610162
for the NCNR deuterium gas piping ASSEMBLY
PAGE 13 OF 77 1333ND21QNB610162
Table of Contents
ABBREVIATIONS AND ACRONYMS
Abbreviation Description NCNR NIST Center for Neutron Research NBSR National Bureau of Standards Reactor COR Contracting Officer’s Representative LD2 Liquid deuterium LH2 Liquid hydrogen D2O Heavy water
1. INTRODUCTION
The National Institute of Standards and Technology (NIST) will install a liquid deuterium (LD2) cold neutron source that will replace an existing liquid hydrogen (LH2) cold neutron source. The LD2 source will shift the neutron spectrum to lower energies, with an average gain of 1.5 for neutrons with wavelengths greater than 0.4 nm, and a gain of 2 at 0.9 nm.
The LD2 cold neutron source architecture includes a LD2 cryostat, condenser heat exchanger, warm ballast tank, and interconnecting piping. This specification outlines the requirements for the interconnecting piping.
2. BACKGROUND
The NIST research reactor, NBSR (National Bureau of Standards Reactor), was designed from the beginning with a provision to add a cryogenically cooled moderator system, or cold neutron source. The initial design was a block of D2O ice, cooled to approximately 25 K by circulating helium gas. A water-cooled lead and bismuth gamma ray shield was included to reduce heating of the ice. The source was installed in the reactor in 1987. Its successful operation was a key to the development of the NIST Cold Neutron Research Facility, a large new experimental area constructed to take advantage of the longer wavelength neutrons produced by this source. The success of this facility, and the high national demand for cold neutrons, led to a design effort to develop a more intense cold neutron source, based on liquid hydrogen.
The first version of this source was installed in the NBSR in 1995 and resulted in a gain in cold neutron intensity of a factor of six. Further refinements of the design resulted in an additional gain of a factor of two for the LH2 unit installed in 2002 and currently in operation.
Nearly two-thirds of the experiments performed at the NCNR utilize cold neutrons with wavelengths greater than 4 Å.
The existing liquid hydrogen cold source that has been in use since 2002 was designed to optimize the flux of cold neutrons transported to the various scattering instruments in the guide hall. It was also designed to be passively safe and operate simply and reliably. All hydrogen system components are surrounded with monitored helium containments to ensure that there are at least two barriers between the hydrogen and the atmosphere.
3. SCOPE OF WORK
PAGE 14 OF 77 1333ND21QNB610162
This specification is for the detailed engineering design, fabrication, installation and testing of double-walled warm deuterium gas piping and associated infrastructure. This piping will provide interconnection between a 16 m3 warm deuterium ballast tank and an existing section of warm gas piping. The inner piping shall be designed to transfer deuterium gas from the cold source deuterium condenser to the ballast tank. The deuterium piping shall be surrounded with a jacket that will be filled with helium gas to prevent the possibility of undetected air from entering the deuterium system and to serve as the containment for any adverse deuterium-oxygen event.
A conceptual CAD model has been developed by NCNR personnel based on experience and expected operational parameters. The design model and other resource documents are included as part of this specification, see Appendix A.
The Contractor shall propose a mechanical design for manufacturing the piping based on the conceptual CAD model supplied by the government and all requirements specified herein. The Contractor shall perform a mechanical and hydraulic analysis for the piping as part of the scope of this work.
The Contractor shall develop a fabrication plan including all metallurgical processes, certifications and testing methodologies required, including detail design and shop drawings for the complete deuterium piping. The design and the position of the welds shall allow for examination in accordance with ASME/ANSI B31.3.
The performance of the deuterium process line has been determined by the NCNR. Therefore, any proposed changes to the design for manufacturing shall be reviewed and approved by the Contracting Officer’s Representative (COR).
Testing at the manufacturer’s facility prior to shipment of equipment to NCNR shall be performed in accordance with section 6.0. A representative of the government may elect to witness tests, e.g. helium mass spectrometer leak tests, performed by the Contractor.
The Contractor shall provide as-built drawings and 3-D CAD models (in a NCNR compatible format) in accordance with the deliverables section (see Section 10). The Contractor shall also provide design calculations and analyses, a quality assurance and fabrication plan, and other documentation as described in section 10.
4. DESIGN
4.1 General
The overall piping design is based on the mechanical, and space limitation analysis performed at the NCNR.
The design emphasizes simplicity, utilizes passive safety features, and provides complete blanketing of all deuterium-containing components with inert helium. The system has been designed such that a single point of failure of any component or weld cannot create a path for air to enter the deuterium space or deuterium to leak to the atmosphere.
The construction of the deuterium piping shall be state-of-the-art, taking into account thermal, hydraulic and mechanical aspects, adequate to ensure smooth operation throughout an expected lifetime of 40 years and suitable for continuous operation, with limited scheduled interruptions only. Its design shall be adequate to ensure no deterioration of mechanical properties within the operation lifetime.
The design, fabrication and testing of the piping shall comply with U.S. standards concerning occupational health, safety and environmental protection, as well as pressure equipment regulations and standards. Exception to pressure equipment regulations is stated in paragraph 5.8.1.
4.2 Description
The deuterium piping shall be assembled using all-welded construction, sub-assemblies consisting of a deuterium process pipe surrounded by a closely fitting helium jacket. Connections are made at each end of the deuterium process line and helium jacket to existing piping/vessels at the NCNR. Additionally, a short deuterium fill manifold is required that will connect to an existing vessel.
4.2.1 Deuterium piping
The inner process piping contains gaseous deuterium. Deuterium is transferred through the piping either to the LD2 moderator cryostat from the warm deuterium ballast tank, or vice versa, depending on whether the LD2 cryogenic system is operating. Condensing deuterium in the moderator draws
PAGE 15 OF 77 1333ND21QNB610162
warm gas from the ballast tank during operation, and vaporizing deuterium is transferred back to the ballast tank when the cryogenic system is shut down. The system is designed such that when operating, condensing deuterium reduces system pressure to approximately 1 bara. When the system is warmed up, the vaporizing deuterium increases system pressure to a maximum pressure of 5 bara.
4.2.2 Helium containment
The inner deuterium process piping is completely surrounded by a helium containment jacket. This serves to prevent the possibility of undetected air from entering the deuterium system and also serves as a monitored barrier against deuterium being released to the atmosphere.
The outer helium containment jacket is an external envelope housing the inner deuterium process pipe as well as its supporting structures. The outer helium jacket shall hold all forces from the inner deuterium process pipe. It shall be designed to allow all possible operating conditions, including all conditions that may occur during all possible failure modes (e.g. failure modes caused by a rupture of the inner process pipe or due to local damage of the external envelope).
4.2.3 Deuterium fill manifold
A manifold at the deuterium ballast tank is required for filling the vessel. The manifold shall include a 1” evacuation valve, two ½” pressure/sample valves, and a ¼” port for a NCNR supplied pressure transducer. See Figure 2 and paragraph 4.2.6.
4.2.4 Routings and interfaces
The piping shall be connected to an existing ballast tank located outside the west side of NIST building 235, room G-100 (Guide Hall) as shown in Figures 3 and 4. The piping will be routed through an opening in the outside Guide Hall wall approximately 30 ft. above grade, then along roof truss horizontally to the south wall of room G-100. It then is routed along the wall, through an opening in the south wall to room D200, where it will stop and be capped just before the interface with existing gas piping and a smaller, 2 m3 ballast tank as shown in Figure 5. Piping length is approximately 75 m.
Final connection of this pipe with the existing gas piping will be performed by the NCNR.
The deuterium fill manifold shall penetrate through the Guide Hall wall and terminate at the fill valve immediately inside the wall.
Interface with existing equipment shall be welded pipe – no brazed or flanged connections are allowed.
4.2.5 Supports and fixations
4.2.5.1 General
The supporting structures shall be designed to appropriately fix all deuterium piping to the concrete or metal structures at the NBSR building. External supports shall be designed for final fit on site to avoid interference with existing structures.
All parts of the supporting structures that will be in contact with the deuterium process pipe and helium jacket shall be made of the same material as the supported lines or compatible materials to avoid galvanic corrosion. All components necessary for installation and fixing shall be included in the scope of delivery.
The Contractor shall submit the designs and positions of the supports to NCNR at the occasion of the design reviews. The positioning and fixing of all support structures to the floors, walls, ceilings and supporting frame shall be approved by NCNR.
4.2.5.2 Internal supports
Internal process pipe supports where required shall support and guide the deuterium process pipe and keep internal displacement within admissible values. The design of any supports included shall ensure that the overall stresses in the deuterium process pipe remains within acceptable values.
PAGE 16 OF 77 1333ND21QNB610162
Fixed supports are fixation points of the process pipes to the external envelope that provide mechanical stability for the process pipes. They shall restrain displacements and rotations of the pipes and transfer weight and pressure loads to the helium jacket.
Sliding supports shall allow axial guidance and relative axial displacement of process pipes with respect to each other as well as with respect to the external envelope. They shall restrain lateral displacements and transfer weight loads to the external envelope.
Any supports included shall be designed to withstand the applied loads during the specified design cases including the pressure test without mechanical failure or permanent deformations.
The supports shall allow evacuating air from the helium jacket volume during vacuum pumping and subsequent helium filling of the jacket.
The design and validation calculations of the internal supports shall be submitted to the NCNR for acceptance at the occasion of the design reviews.
4.2.5.3 External supports
Internal supports shall be designed to transmit all applied loads from the internal piping due to pressure, weight and temperature to the helium jacket. The helium jacket in turn shall transmit all loads to external supports, which shall restrain displacements and rotations of the piping, and transfer their weight, pressure and temperature loads to the civil facility structures (floors, walls or ceilings). Sliding supports shall restrain lateral displacements and transfer weight loads only. The piping shall not transmit any loads to existing piping or equipment where they are connected.
The supports shall be designed to withstand the applied loads during the specified design cases without mechanical failure or permanent deformations. Their design shall allow for the positioning of the elements in the longitudinal, vertical and transversal directions during installation.
4.2.5.4 Piping guard / protection
Piping shall be suitably protected to prevent any objects from impacting and damaging the piping.
Outside the Guide Hall, the planned piping routing runs vertically along the building wall to an elevation of approximately 30 ft above grade, where it will then pass through a penetration (see 4.2.5.5) into the building. The piping run outside the building shall be covered with a guard to protect the piping. Inside the Guide Hall, the planned routing of piping from the ballast tank to the south wall of Guide Hall room D200 will provide adequate protection for the piping as it will run either behind existing structural columns or in the roof truss above the Guide Hall crane. However, from the ceiling to the final interconnection point in room D200, a guard is required to protect the piping. A notional design for a guard is shown in the model included in Appendix A to this specification.
4.2.5.5 Piping insulation
Piping routed outside the guide hall shall be insulated to minimize the influence of outdoor temperatures on the deuterium gas. Minimum acceptable insulation R value is R=3.
4.2.5.6 Penetrations
There are two piping penetrations entering the west wall of the Guide Hall. One penetration is for the piping run to room D200, and the other penetration is for a fill manifold terminating just inside the Guide Hall. The piping penetrations shall be sealed with a suitable weather seal.
4.2.5.7 Bollards/barriers/civil works
Outside the building, piping from the existing 16 m3 ballast tank shall be protected to prevent any objects from impacting and damaging the piping. Additionally, the area around the ballast tank itself is currently open with no protection. The Contractor shall provide bollards to surround the ballast tank to protect it from the risk of any vehicle colliding with the ballast tank. See Figure 6.
PAGE 17 OF 77 1333ND21QNB610162
Piping protection between the ballast tank and wall is required. The current design concept uses Jersey barriers to surround the piping. A suitable foundation is required for the barriers to sit on.
The location of the piping cabinet on the ballast tank is closer than 25 ft to the Guide Hall exit door. Consequently, a barrier wall near the exit door wall is required to comply with the NIST Authority Having Jurisdiction (AHJ) and with NFPA 50A. The notional location of this barrier is also shown in Figure 6.
4.2.6 Valves and instrumentation
No instrumentation is included in the scope of this specification. One evacuation valve and two pressure/sample valves are required on the fill piping at the deuterium ballast tank. Additionally, ¼” port for a pressure transducer (provided by NCNR) is required at the fill connection. See Figure 2 and drawings 002-2866 and 002-300 (Appendix A). All valves shall be bellow seal type to prevent any risk of leakage, no gasket sealed valve stems are allowed. All other valves in the system are the responsibility of NCNR. A ¼” port located near each end of the helium jacket shall be included for NCNR supplied pressure transmitters to measure helium jacket pressure.
4.2.7 Equipment identification and marking
The piping shall have visual certification of its identity and integrity. Pipes shall be permanently marked with producer, dimension, material and serial number. Marking shall not be done by stamping of the equipment itself, but rather by attaching labels to it. For all pressure bearing components enclosed in the helium jacket the identification plates shall be located on the external envelope.
PAGE 18 OF 77 1333ND21QNB610162
5. FABRICATION AND PERFORMANCE REQUIREMENTS
The piping shall be designed to be fabricated with the following materials of construction at pressure and temperature conditions listed below:
5.1 Materials of Construction
All materials and components used in the construction shall be new and suitable for the use for which they are intended. For all pressure-bearing process pipes, the choice of materials shall comply with ASME/ANSI B31.3 and shall be fabricated of austenitic stainless steel.
Fixed supports of the process pipes and external jacket shall be made of the same material used for the pipes and jacket. Any sliding supports of process pipes shall be made of material compatible with the process pipe and jacket to avoid galvanic corrosion.
Table 5.1 Piping material of construction
Component Material Inner deuterium process piping 304L stainless steel, Schedule 40 Outer helium containment jacket 304L stainless steel
5.2 Pressure and temperature rating
Table 5.2 Piping design parameters
Process line name Size Design pressure Nominal operating pressure Nominal operating temperature Inner deuterium process pipe 1.25” NPS 5.25 bara 0-5 bara 230-340 K
Outer helium jacket 2.5” ODT 5.25 bara 0-1.1 bara 230-340 K
5.3 Thermal and hydraulic design
Pressure drop shall be minimized by use of appropriate size pipe and optimized number of bends. Corrugated sections to accommodate piping expansion for the deuterium piping are not allowed, solid pipe only.
Corrugated pipe sections may be allowed for the outer helium jacket if required. The anticipated pipe size for the deuterium and helium jacket is shown in Table 5.2. Contractor shall propose final pipe size based on required flow rates and any other appropriate design considerations. Maximum estimated deuterium flow rate under failure conditions is 13 g/s. Final pipe size shall be approved by NCNR.
5.4 Welding
The fabrication and installation of the deuterium and helium jacket piping requires the implementation of many welds that directly affect mechanical performance, as well as the leak tightness of process gas carrying components and external envelopes. Therefore, all welding works shall meet the following requirements.
Process pipes, including fittings and T-pieces, shall be permanently joined by full penetration butt-welds. Fillet-welds are not accepted in process piping. The external envelope (helium jacket) shall be assembled by means of longitudinal or circumferential butt-welds with full penetration during fabrication. Final field welding of the helium jacket interconnections between assemblies may be made by means of fillet-welds.
The permanent joining of supports and assemblies to the process pipes may be performed via fillet or tack-welds provided that the process pipes are shielded with an appropriate inert gas during the welding operation.
Joint welds shall be performed using the Gas Tungsten Arc Welding (GTAW) process.
Welds shall be preferably executed with automatic orbital welding machines. However, manual welds are also acceptable. Permanent joining techniques other than welding are not allowed for process pipes and external envelopes.
PAGE 19 OF 77 1333ND21QNB610162
Welders and Welding Procedure Specifications (WPS) shall be qualified to ASME Section IX for all welding works performed by the Contractor or their sub-contractors. Each fabrication and installation weld joint shall be covered by a WPS. The Contractor shall guarantee that the WPS comply with the requirements of
ASME/ANSI B31.3.
The requirements applicable to the non-destructive tests (NDT) of welds are detailed in section 6.4 of this specification.
The Contractor shall collect all the information concerning welding works in a welding quality book. This book shall be opened at the design phase and closed at the end of the acceptance tests. The book shall include, but not be limited to, the following information:
Welding plan, Welding inspection records, Welding procedure specifications, Welding procedure qualifications, Qualifications for non-destructive control of welds, Welders’ qualifications, Non-destructive controls records, Welding inspection records.
5.5 Geometry
5.5.1 Deuterium lines
The deuterium line has been sized for efficient operation and to navigate around obstacles between the deuterium ballast tank and the interface with the existing piping. The proposed routing is shown in the model included in Figure 1 and Appendix A. Routing of the piping shall be proposed by the Contractor at the preliminary design review. Final routing is subject to approval by NCNR.
5.5.2 Helium jacket
The helium jacket surrounds and follows the same routing as the deuterium line. Final routing is subject to approval by NCNR.
5.6 Maximum Operating Conditions
The deuterium system has two normal operating modes, cold or warm. When operating cold, a portion of the deuterium inventory is liquefied in a cryogenic condenser heat exchanger, which reduces deuterium absolute pressure to approximately one (1) bara. When the cryogenic helium refrigerator is shut down, the liquefied deuterium vaporizes, increasing the system absolute pressure to five (5) bara maximum.
The jacket is pressurized with helium to approximately 1.1 bara. The helium system pressure remains unchanged for either the cold or warm deuterium operating modes.
5.7 Cleaning
All surfaces shall be free from moisture, dirt, organic compounds, scale, paint or other foreign matter. Shop fabricated components shall be suitably sealed to prevent contamination during shipment. Similarly, appropriate steps shall be taken to maintain piping cleanliness during installation at the NCNR. Cleaning procedures and precautions shall be included in the Contractor’s quality assurance and fabrication plan (see section 10).
5.8 Restrictions
5.8.1 Pressure relief valves are not permitted. Overpressure protection is the responsibility of the NCNR.
PAGE 20 OF 77 1333ND21QNB610162
6. QUALITY ASSURANCE REQUIREMENTS
Some of the basic elements of a QA plan call for certified material and processes, including comprehensive tests to ensure reliability and rigorous standards for acceptance.
6.1 Codes and Standards
The equipment specified in this technical specification, shall be in conformance with all applicable US standards regulating safety aspects for pressurized piping. The Contractor is responsible for determining the applicability of appropriate standards. The applicable construction code for design, choice of materials, manufacturing, installation, inspections and controls of the metallic piping in this specification is ASME/ANSI B31.3 – Process Piping, ASME B31.12 – Hydrogen Piping and Pipelines, and CGA G-5.4, Standard for Hydrogen Piping at User Locations
For any equipment and assemblies not covered by the specified standards, the Contractor shall take into account the requirements specified in this technical specification and perform their design, manufacturing, installation and verification in accordance with the present latest technology.
6.2 Materials
All materials shall conform to all applicable material requirements and shall have material certifications.
Acceptance test certificates are required for all metallic materials, semi-finished and finished metallic products obtained or used by the Contractor or their sub-contractors. Material numbers, batch numbers and the properties mentioned below are to be indicated. All certificates shall be submitted to NCNR during the tests at the Contractor’s premises.
6.3 Testing and Inspections
6.3.1 General
The Contractor is responsible for the completeness of the tests that are required to achieve the quality assurance in line with the requirements of this specification. The Contractor shall prepare a detailed test program and submit it to the NCNR for approval.
The Contractor shall ensure that sufficient qualified staff, equipment and arrangements for the performance of all tests both at the Contractor’s premises and at NCNR are provided. All necessary documents such as preliminary test materials, drawings, records, calibration lists, specifications and instructions for non-destructive tests, test bodies, work patterns etc. shall be provided by the Contractor.
Inspectors appointed for non-destructive and destructive material testing and leak inspections shall have the qualifications and thorough technical knowledge to manage the tests in full compliance with the requirements. Non-destructive test (NDT) personnel shall be qualified in accordance with ANSI/ASNT CP- 189-2016, ASNT Standard for Qualification and Certification of Nondestructive Testing Personnel.
The Contractor shall submit to NCNR test records and protocols of all tests performed at their premises and at NCNR not later than 2 weeks after the respective test is completed. If, during such a test, any defect is found, the respective test shall be repeated partly or completely after elimination of the deficiencies. Full achievement of all required tests proven by consistent test protocols is a binding prerequisite for acceptance.
NCNR staff shall have the option to witness any tests conducted at the Contractor’s or his subcontractor’s facilities. The Contractor shall notify NCNR at least 10 days prior to any planned test to allow time to arrange travel.
The requirements applicable to the non-destructive tests (NDT) of welds, which will be performed during fabrication and installation phases, shall comply with ASME/ANSI B31.3 paragraphs 343-345.
PAGE 21 OF 77 1333ND21QNB610162
6.3.2 Visual examination
100% visual examination shall be performed according to ASME/ANSI B31.3 paragraphs 341.4.1(a) and
344.2. The acceptance criteria of weld imperfections shall be as per ASME/ANSI B31.3 Table 341.3.2.
6.3.3 Other examination
Deuterium process piping welds and helium jacket welds shall undergo additional examination according to at least the minimum requirements of ASME/ANSI B31.3 paragraph 341.4.1(b) (either radiograph or ultrasonic examination). The execution of X-ray examinations of welds, assessment of X-ray films and preparation of the related documentation shall be based on ASME/ANSI B31.3 paragraph 344.5.
Alternatively, ultrasonic examination shall be performed according to ASME/ANSI B31.3 paragraph 344.6.
6.3.4 Pressure testing
All pressure tests shall be carried out at the test pressure defined ASME/ANS B31.3 paragraph 345 and any other applicable standards. For pressure tests performed at the Contractor’s facilities, either pneumatic or hydrostatic pressure tests may be permitted subject to the Contractor’s plan for removing any presence of residual water or any other liquid, and acceptable safety precautions taken. For pressure tests performed at NCNR, only inert gas may be used.
6.3.5 Leak testing
All piping assemblies shall be 100% leak tested at ambient temperature in accordance with the methods outlined in specification ASTM E498, latest edition. Assembly welds shall be tested as per test method “A” of the specification, with weld joints bagged externally, helium introduced into the bag. The helium leak rate shall not exceed 1x10-9 std. cc/sec.
6.3.6 Test of assemblies
Component and subassembly examination and testing shall be performed at the Contractor’s shop. Additional testing and examination will be required during installation at NCNR. At the completion of installation, the entire piping assembly shall be final pressure and leak tested to assure system integrity. Final assembly pressure testing at design pressure shall be performed using an inert gas. Final helium leak testing shall be performed to the same specification as in paragraph 6.3.5. Any leaks discovered shall be repaired and the assembly retested.
7. CONFLICTS
If there is any discrepancy between the drawings and the written specifications, the written specifications shall take precedence and the COR shall be notified of any discrepancy.
8. GOVERNMENT FURNISHED EQUIPMENT
8.1 Engineering Design Documents
A 3D solid model of the deuterium piping assembly and several documents detailing the existing piping and infrastructure are included as part of this specification (see Appendix A). These documents are provided solely as a reference and useful resource. The solid model designs are included as reference. The final deuterium piping design is the responsibility of the Contractor.
8.1.1 Deuterium Piping Concept Design
NCNR drawings detailed in Appendix A, plus a 3-D solid model, are included and part of this specification. The 3-D model will be furnished by NCNR in IGES and STEP universal formats.
PAGE 22 OF 77 1333ND21QNB610162
9. ACCEPTANCE
In accordance with FAR 52.246-2 all the delivered items under this contract will be inspected to ensure they meet all the requirements set forth herein. The NCNR, to verify the required performance, as stipulated herein, will witness the inspections and acceptance tests listed below at the NCNR in Gaithersburg, MD.
The Contractor shall provide all equipment for metrology, inspection and quality control required to verify that the critical dimensional features, pressure capability, leak rate and other parameters of the deuterium piping conforms to the Contractor’s shop drawings and this specification. The Contractor shall provide equipment calibration certificates to the
NCNR.
The design for manufacturing and mechanical analysis shall be reviewed, compared to NCNR’s mechanical analysis and approved by NCNR.
The deuterium piping will be deemed accepted and an acceptance certificate issued when the acceptance tests show compliance with the measured hydraulic characteristics and pressure capability of the process lines as specified in Sections 5.3 and 6.3, and when one complete pressure cycle with helium is made without any damage or degradation of the mechanical properties of the assembly. An operating cycle comprises the complete pressurization and depressurization of the deuterium process line from 1 bara to 5 bara with the helium jacket pressurized to 1.1 bara at ambient temperature.
In the event project delays are experienced due to circumstances outside of the Contractor’s control, NIST will provide additional time to accommodate for project completion. The additional time provided will be in accordance with the delay caused by the Government.
Should any part of the piping assembly fail to meet the requirements set forth herein, the section in question shall be repaired by the Contractor at no additional expense to the Government.
10. DELIVERABLES
The Contractor shall provide to the NCNR all equipment and documentation as specified in this document and accompanying Statement of Work (SOW), including but not limited to:
1. Design for manufacturing and mechanical analysis reports to be provided at the Design Review meeting. The design and analysis reports shall include but not be limited to:
Pressure and hydraulic analyses
Piping flexibility analysis
Load analyses
2. A quality assurance and fabrication plan that will ensure the deuterium piping will meet the requirements stipulated herein due four (4) weeks after the Design Review meeting.
3. Shop drawings due four (4) weeks after the Design Review meeting.
4. As-built shop drawings, 3-D models, certified test results due one (1) month after system acceptance by NCNR.
Drawings and models shall be provided in universal IGES or STEP format. Electronic documentation shall be provided in PDF format.
5. Delivery of one complete deuterium piping assembly, due six (6) months after contract award.
6. Installation and testing of the deuterium piping assembly and bollards/barriers/civil works, due eight (8) months after contract award.
7. Successful completion of all acceptance tests (see section 9) due nine (9) months after contract award.
The government shall have ten (10) business days after receipt to review any documents (electronic or paper) submitted for approval by the Contractor.
PAGE 23 OF 77 1333ND21QNB610162
11. SCHEDULE / MEETINGS
The Contractor shall prepare and present a comprehensive project schedule to the TPOC at the Kick-off meeting.
The project shall be complete and final acceptance issued by NCNR nine (9) months after contract award.
The contractor shall also plan and prepare for the following project meetings, whereby the agenda, participations and location are to be determined in coordination with NCNR:
1. Kick-off meeting (KOM) after signing of the contract
2. Design Review (DR), for approving the detail design…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .