Amendment 0002.docx
DOCX document 15 KB Posted
- Solicitation number
- 1333ND21QNB610162
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT 0005.docx | DOCX document | |
| AMENDMENT 0004.docx | DOCX document | |
| Drawing Number 002-3073.pdf | ||
| Dawing Number 002-2858.pdf | ||
| Amendment 0001.docx | DOCX document | |
| NIST COVID Procedures.pdf | ||
| RFQ 1333ND21QNB610162.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT 0002
RFQ NUMBER: 1333ND21QNB610162
TITLE: Manufacturing, Installation, and Testing of Double -Walled Warm Deuterium
The purpose of Amendment 0002 is to provide submitted questions with the technical response.
QUESTION 1: Drawing 002-3071 shows pipe route double wall piping, specification states piping outside requires insulation for containment, is insulation field applied?
RESPONSE 1: Insulation can be applied either in the field or in their shop. The Government anticipates that it would be applied in the field.
QUESTION 2: What is the ambient temperature or air temperature?
RESPONSE 2: Ambient conditions are Gaithersburg – approximately 90 deg F high, 25 deg low annually.
QUESTION 3: Client provided additional drawings # 002-3072, #002-3073, 002-2858, not sure if these drawings are for double wall pipe?
RESPONSE 3: Drawings 002-3072 and 002-3073 are sub parts to assembly 002-3071. Drawing 002-2858 is a single wall pipe (not a double wall pipe).
All other terms and conditions remain unchanged and in full force and effect.
End of Amendment