Amendment 0001.docx

DOCX document 15 KB Posted

Attached to
Manufacturing, Installation, and Testing of Double-Walled Warm Deuterium
Solicitation number
1333ND21QNB610162
Issued by

View the file

Other files

File Type Posted
AMENDMENT 0005.docx DOCX document
AMENDMENT 0004.docx DOCX document
Amendment 0002.docx DOCX document
Drawing Number 002-3073.pdf PDF
Dawing Number 002-2858.pdf PDF
NIST COVID Procedures.pdf PDF
RFQ 1333ND21QNB610162.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 0001

RFQ 1333ND21QNB610162

Title: Manufacturing, Installation, and Testing of Double -Walled Warm Deuterium

QUESTION 1: Section #5.1 and #5.2 refer to the inner Deuterium transfer line as 1-1/4” SCH 40 pipe, drawing # 002-3073 indicates 1” SCH 40 pipe. Which is correct?

RESPONSE 1: Drawing 002-3073 should show the pipe as 1-1/4” pipe, it is now shown incorrectly as 1” pipe.

Drawing 002-2858 does not show pipe size, it should show pipe size as `-1/4” pipe.

QUESTION 2: Can you please provide size of Deuterium Charging Line drawing #002-2858.

RESPONSE 2: Drawing 002-2858 does not show pipe size, it should show pipe size as `-1/4” pipe.

QUESTION 3: Section 5.4, page 19, “…non-destructive tests (NDT) of welds are detailed in section 6.4 of this specification.” I see no section 6.4, section 6.3.3, however, does provide information for additional testing. Is this a typo?

UPDATED DRAWINGS ARE ATTACHED TO THIS POST AS A PART OF THIS AMENDMENT

All other terms and conditions remain unchanged and in full force and effect.

End of Amendment