RFI Responses Design-Build MTZ Parking.pdf
PDF 113 KB Posted
- Attached to
- Y1LZ--36C26124R0004 | Project 612-23-003 | Design Build, Create Martinez Parking Lot and Access
- Solicitation number
- RFP36C26124R0004
About this file
This document contains responses to requests for information (RFIs) regarding solicitation number RFP36C26124R0004 from the Department of Veterans Affairs for design-build services to create a parking lot and access at the VA Martinez OPC campus located in Martinez, California. The responses provide an updated utilities site plan drawing, relax the definition of project recency from five to ten years to improve vendor competition, confirm that only Phase I responses are due on December 15, 2023 with Phase II proposals to be requested only from selected Phase I offerors, and clarify that there is only one valid solicitation posted on SAM.gov under the provided notice ID and links.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA Responses to Requests for Information (RFI’s)
Solicitation # RFP36C26124R0004
Project Title: Design-Build to Create Parking Lot & Access for VA Martinez OPC
Campus
Project Number: 612-23-003
RFI #1 – Please confirm all pages of Attachment 10 (MTZ-SITE PLAN 3-2011 UTILITIES Campus
Drawings) are formatted correctly and to scale?
RFI#1 Response: There were electrical conduits installed in the last few months, please see the attached pdf for an update. VA confirms the provided utilities in the package and the updated version are the most current utilities layout at VA Martinez. See attached “Updated Additional MTZ-SITE PLAN 3-2011 UTILITIES”
Drawings.
RFI #2 – On Solicitation Page 20 of 97, Recency is defined as a project completed in the previous five calendar years. Up to two of the project examples to be submitted for Factor 2 require examples of design/build projects that the prime contractor and the partner firm have completed together. For the project(s) required to demonstrate the prime contractor and partner firm working together, we respectfully request the
Government relax the definition of recency to ten (10) years from the solicitation issue date.
RFI #2 Response: Upon review and consideration, to improve competition from vendors, the Government will update the definition of Recency as requested to ten (10) calendar years from the Solicitation date, versus five (5) calendar years as cited on page 20 of the solicitation.
RFI #3 - Can you please confirm that only Phase I response is due on 12/15/23?
RFI #3 Response: Phase I is due on 12/15/2023. As cited on page 25, “Responses to Phase-Two Request for
Proposal shall only be accepted after Phase I is complete and only from selected offerors.” The VA will determine who the selected offerors for Phase II proposals are after Phase I evaluation is completed. Selected
Offerors for Phase II will receive an e-mail from VA directly asking for Phase II proposals for further evaluation.
RFI #4 - This solicitation was posted twice today, 11/14/2023, on sam.gov. The first one showed up around
11:09 AM PST and the second one posted around 1:42 PM PST. The documents appear to be the same. Please confirm we should be utilizing the documents posted with the latest version of this solicitation.
RFI #4 Response: There is only one Solicitation posted out on SAM.gov under notice ID:
RFP36C26124R0004. You can view this at link:
https://sam.gov/opp/2be458830f5447caa0d416a93e4324cd/view .
All Amendments to the Solicitation will be posted at this same link. Reach out to Rosario.chaidez1@va.gov and Daniel.Jhun@va.gov if there are any concerns, issues, or questions.
END OF RFI RESPONSES