ARC FLASH STUDY
Solicitation number
ISO198-23
Issued by

About this file

This document is a request for proposal (RFP) for an arc flash study at multiple buildings located at Naval Support Activity Crane in Indiana. The scope of work includes performing an assessment of the existing electrical distribution systems and producing stamped as-built drawings, an arc flash risk assessment with safe approach distances and required PPE, and installation of arc flash labels. The base bid includes work at 16 identified buildings, with optional additional work at 3 other buildings. Responses are due by August 31, 2023. The contract will be a firm fixed-price contract and is 100% set aside for small businesses. The selected contractor must begin work within 10 days of award and complete the project within 180 days.

View the file

Other files

File Type Posted
AMD07 ISO198-23 ARC FLASH.docx DOCX document
Arc Flash Building Answers to Questions.xlsx XLSX spreadsheet
arc flash site visit attendance.pdf PDF
Arc Flash SOW_20230920-1.pdf PDF
Arc Flash Building SqFt_20230919.pdf PDF
AMD06 ISO198-23 ARC FLASH.pdf PDF
AMD05 ISO198-23 ARC FLASH.pdf PDF
AMD04 ISO198-23 ARC FLASH SITE VISIT.pdf PDF
Arc Flash Contractor Questions.docx DOCX document
AMD03 ISO198-23 ARC FLASH SITE VISIT.pdf PDF
AMD02 ISO198-23 ARC FLASH.pdf PDF
AMD01 ISO198-23 ARC FLASH.pdf PDF
CDRLS table.pdf PDF
Building Square Footage.pdf PDF
Acronym Table.pdf PDF
Combine Submittals.pdf PDF
Applicable Documents.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

CODE 8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

ISO198-23

UNICOR, FPI CENTRAL OFFICE

400 1ST ST NW

WASHINGTON DC 20534-0004

See - SOW - Section C

5. REQUISITION/PURCHASE REQUEST NUMBER

Jason Morgan 1-800-827-3168 ext 3002

6. PIIIIIIHSGHSHS

ROJECT NUMBER

3198-23

108-10-2023

10 DAYS

AUGUST 31,2023

ISO198-235000002211

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Jason Morgan, Contracting Officer Phone: (1-800-627-3168) ext 3002 E-mail Address: Jason.morgan2@usdoj.gov

UNICOR, Federal Prison Industries 3301 Leestown Road Lexington KY, 40511

Jason Morgan

RFP16200000132 2 of 47

Section A: Optional Form 308 or SF33 Section B: Supplies or Services Pricing or Cost (Line Items)

1. The following information pertains to the SF1442, Solicitation, Offer, and Award:

OMB Clearance Number 1103-0018

Block 8: Emailed, Hand carried or Overnight Express to:

UNICOR, FPI

ATTN: Jason Morgan, UNICOR Contracting Officer, 3301 LEESTOWN RD, LEXINGTON, KY 40511

859-255-6812 EXT 3002

Block 17: LUMP SUM (ENTER THE AMOUNT IN SECTION B.

Block 24, and 27, See Section H.

GENERAL INTENTION: It is the intent of this solicitation to result in a Firm Fixed Price, Architecture and Engineering Type Contract to perform an ARC Flash study in 16 buildings at Naval Support Activity (NSA) Crane, Located in Crane, Indiana.

The solicitation is 100% set aside for small business. The North American Industrial Classification System (NAICS) Code applicable to this project is 541300, Architectural, Engineering, and Related Services

Contract Line Item: Offerors shall enter unit price and amount for contract line item.

SITE VISIT: If a site visit is requested by any potential offeror a date will be set to accommodate timely submission of the names of attendees. Potential attendees will have one week to submit the required documents prior to the established date of the site visit for background checks to be processed;

regardless if the offeror currently holds a DBIDS pass.

QUESTIONS WILL ONLY be accepted in writing and WILL NOT BE ACCEPTED AFTER August 23, 2023 at 10:00 AM EST. Responses to questions will be posted via www.sam.gov

NO PHONE CALLS PLEASE.

Proposal due date is August 31, 2023, at 2:00 PM EST. Late offers will not be accepted.

RFP16200000132 3 of 47

Physical access to the Government’s facility at Naval Support Activity (NSA), Crane shall be through the use of the Defense Biometric Identification System (DBIDS) and associated data processing/information services for purposes of protecting U.S./Coalition/allied government/national security areas of responsibility and information.

The contractor shall obtain employee personal identity verification credentialing (badge) by submitting to the NSA Crane Visitor Center, 103 Furlong St, Crane, IN 47522, form SECNAV 5512/1 (APR 2014), for each contractor employee. Upon Base Registrar authorization of form 5512/1 the contractor shall submit form NSA Crane 5512/47 DBIDS Badge Application Record to the NSWC Crane Security Division (812)-854-1213. The Contractor shall retrieve badges of employed personnel upon separation. A background check will be conducted as part of the process and two forms of identification are required. A visitor's pass will be provided if the background check is cleared. Please allow an significant time (1-2 hours) for the entire process.

PROJECT MUST BE COMPLETED BY 09/30/2024

PROJECT MAGNITUDE

Pursuant to paragraph 36.204 of the Federal Acquisition Regulation, the estimated cost of this acquisition is between $500,000 and $1,000,000.

THE FOLLOWING INFORMATION IS REQUIRED TO BE COMPLETED BY THE

OFFEROR:

VENDOR'S Unique Entity Identifier:___________________________

VENDOR'S POINT OF CONTACT: _____________________________________

VENDOR'S TELEPHONE & FAX NUMBER: ______________________________

VENDOR'S EMAIL ADDRESS: ________________________________________

VENDOR'S BUSINESS SIZE (i.e. SMALL,LARGE,ETC.): ________________

By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the SAM database (System Award Management) prior to award, during performance and through final payment of any contract resulting from this solicitation.

RFP16200000132 4 of 47

_______________________________________________ signature

RFP16200000132 5 of 47

SECTION B

SUPPLIES OR SERVICES AND PRICES/COSTS

Item No. SUPPLIES OR SERVICE Quantity U/M UNIT PRICE AMOUNT IN US$ Delivery Date

Terms:

00001 ICSG-0001 1 EA 02/27/2024

ARC FLASH RISK ASSESSMENT

RFP16200000132 6 of 47

Acquisition & Construction Management Branch Code 1022 Statement of Work (SOW) Arc Flash Project

1.0 SCOPE

The scope of this effort is to provide all management, labor, material, equipment, transportation, supervision, and environmental and quality controls, to perform an ARC Flash study in 16 buildings at Naval Support Activity (NSA) Crane, Located in Crane, Indiana. The purpose of this study is to provide an Arc Flash Risk Assessment on the buildings electrical distribution system. The information from this study is combined to provide labels that indicate the safe approach distances, Arc Flash Incident Energy, and a list of personal protective equipment needed at each location. Stamped/certified as-built drawings shall be provided for each buildings electrical distribution system.

2.0 ACRONYM TABLE

See attached Acronym Table

3.0 APPLICABLE DOCUMENTS

Unless otherwise specified, the revision level and date for each specification or standard cited within the solicitation/contract (including any specifications or standards cited in any drawing, handbook, or referenced specification or standard contained within this solicitation), shall be that listed in the Department of Defense Index of Specifications and Standards (DODISS) and supplement thereto. The following documents of the revision or issue in effect at the date of award form a part of this SOW for reference. In the event of a conflict between the documents referenced herein and the contents of this SOW, the contents of this SOW shall prevail.

See Applicable Documents attachment.

4.0 PERFORMANCE REQUIREMENTS

The performance requirements for this effort include performing an assessment of the existing conditions to produce an Arc Flash risk assessment. This assessment shall include posted labels for all safe approach distances and a list of PPE required for

RFP16200000132 7 of 47 access into the Arc Flash zones. Stamped as built drawings shall be produced by the contractor reflecting accuracy of existing conditions for each identified buildings electrical distribution system.

4.1 REQUIREMENTS

The buildings that are involved in the base bid effort include 122, 143, 363, 2547, 2805, 2987, 3227, 3234, 3285, 3286, 3287, 3330 West, North, and South, 3334, 3461, 142, and 8000 (Lake Glendora).

Additional bid options are:

• Bid Option #1 – Building 3330 Central (Bid option #1 will not award without base bid)

• Bid Option #2 – Building 3168 (Bid Option #2 will not award without bid option #1 and base bid)

• Bid Option #3 – Building 3006 (Bid option #3 will not award without bid option #2, bid option #1 and base bid)

A) Contractor shall produce any/all updates to the GOV provided as-built drawings to reflect accurate electrical distribution systems currently in place. A stamped/certified set of as-builts shall be provided by the contractor. (CDRL A008)

B) Contractor shall provide an Arc Flash risk assessment identifying safe approach distances, Arc Flash incident energy, and a list of PPE required for each location.

C) Any as-builts provided by the contractor shall be both PDF and AutoCAD version 2021, with AutoCAD versions developed using the Tri-Service A/E/C/ CADD Standards.

D) Arc Flash stickers shall be installed at each applicable location

E) The Contractor shall clean the worksite at the end of each workday. The Contractor shall dispose of any scrap material and clean any spills that may occur.

F) All buildings in the base bid and bid options listed above are located at NSA Crane unless noted otherwise.

Additional Notes:

A) Contractor shall provide a production report for the prior day starting after NTP(CDRL A001).

B) Contractor shall provide a schedule at the PAK meeting and

RFP16200000132 8 of 47 joseph.p.regan Highlight provide an updated schedule if any deviation over five (5) days of the approve schedule occurs (CDRL A002).

C) All building access will need to be coordinated with the RTA (2 days minimum) in advance of the access needed.

Submittal Requirements

A. Contractor is responsible for providing a Submittal Register utilizing form ER 415-1-10 (CDRL A003) for all anticipated submittal items.

B. Submittals are to be provided to the GVT for review and acceptance by the COR.

C. The QCM shall follow processes set forth in the Quality Control plan and UFGS Spec 01 45 00.10 20 to ensure the products being submitted are contract compliant.

4.2 Installation Access

Physical access to the Government’s facility at Naval Support Activity (NSA), Crane shall be through the use of the Defense Biometric Identification System (DBIDS) and associated data processing/information services for purposes of protecting U.S./Coalition/allied government/national security areas of responsibility and information. The contractor shall obtain employee personal identity verification credentialing (badge) by submitting to the NSA Crane Visitor Center, form SECNAV 5512/1 (APR 2014), for each contractor employee. Upon Base Registrar authorization of form 5512/1 the contractor shall submit form NSA Crane 5512/47 DBIDS Badge Application Record to the NSWC Crane Security Division. The Contractor shall retrieve badges of employed personnel upon separation.

Each employee shall affix their badge on their person above the waste at all times while on the Activity. Badges may only be removed for safety reasons and must be reaffixed when work is completed.

DBIDS information can be found at the following website:

http://dbids.dmdc.mil/ For Contract employees or subcontractors requiring infrequent access to the Activity, one day temporary passes MAY be authorized. Requests for temporary passes shall be submitted, including the completed SECNAV 5512/1 form, to the COR at least 5 working days prior to the requested base access day. Employees shall also be prepared to provide a completed SECNAV 5512/1 form to the authorizing individual the day of their visit. Temporary

RFP16200000132 9 of 47 passes MAY be authorized up to and including a 28 day duration.

A base pass request DOES NOT guarantee base access. Approved base access will be communicated to the Contractor by the NSWC Construction Manager, or their designee.

Be advised that the DBIDS process and temporary pass process both involve a background check. Persons with a Felony conviction in the last 10 years will not be issued badges or passes.

Individuals supporting these efforts shall comply with the latest security regulations applicable to the government facility/installation.

a. Depending on the facility/installation regulations, contractor personnel shall present a proper form of identification(s) and vehicle proof of insurance or vehicle rental agreement.

b. All contractor persons engaged in work while on government property shall be subject to inspection of their vehicles at any time by the government, and shall report any known or suspected security violations to the local host Security Department.

Failure to obtain entry approval will not affect the contract price or the time of completion.

4.3 Program Management

The Contractor shall be responsible for field verification of actual conditions prior to commencement of work. The Contractor shall be responsible for quality control of all work that is performed via this task order. The Contractor is responsible for compliance with the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, and shall maintain a safe working environment at all times during the performance of this task order. Although this document is intended to identify all significant features of work to be accomplished in the performance of this task order, it should not be considered absolutely inclusive of all minor tasks required for completion of the major work described herein.

4.3.1 Design and Construction Quality Control Plan

The Contractor shall establish and maintain a Quality Control program that is administered by a Design and Construction Quality Control organization, using Quality Control (Design and Construction) Plans, (CDRL A004) Commissioning Plans and Reports, meetings, a Coordination and Mutual Understanding Meeting, three phases of control, submittal review and approval, testing, completion inspections, and QC certifications, Inspections in accordance with UFGS Section 01 45 00.10 20

RFP16200000132 10 of 47

Quality Control for Minor Construction and documentation necessary to provide design, materials, equipment, workmanship, fabrication, construction and operations which comply with the requirements of this Contract. The QC program must cover on-site and off-site work. No construction work or testing may be performed unless the Contractor’s QC Manager is on the work site.

4.3.2 Inspection Benchmarks

A) Periodic quality / safety checks at Government determined frequency. The Government may or may not provide notification to the Contractor prior to quality and safety checks.

B) The Contractor shall notify the COR once each building is substantially complete. The COR will schedule a pre-final inspection with the Contractor, the building POC, and any other Government personnel deemed necessary. If no deficiencies are recorded during this pre-final inspection, this inspection will serve as the final inspection for that building. If there are deficiencies recorded, the COR will schedule a final inspection after the Contractor has corrected the identified deficiencies.

C) Final (At completion) Inspection The Contractor shall notify the COR at least 5 working days prior to the requested date for the final acceptance inspection.

The Contractor shall state within the notice that all items previously identified on the pre-final punch list will be corrected and acceptable, along with any other unfinished Contract work, by the requested date of the Final Acceptance Inspection. The Contractor must be represented by the QC Manager, the Project Superintendent, and others deemed necessary. Attendees for the Government may include the COR, Construction Management personnel, and personnel representing the building POC.

4.4 Safety and Health

The Contractor shall demonstrate a current and compliant Occupational Health and Safety Program in accordance with NSWCCRANEINST 5100.1A. The requirements of this contract may require Contractor personnel to come in contact or be exposed to hazardous conditions. The Contractor shall abide by all applicable federal, local, and state occupational safety and health requirements. The Government will provide Standard Operating Procedures (SOP) when applicable. The Contractor must have on record a corporate safety plan and shall provide a copy to the COR when instructed. The Contractor shall ensure all

RFP16200000132 11 of 47 employees have appropriate Personal Protection Equipment (PPE).

The Contractor shall ensure employees have all required training and certifications related to Occupational Safety and Health Administration (OSHA) requirements. The Contractor shall demonstrate a current and compliant Environmental, Safety, and Occupational Health Program in accordance with DoDD 4715.1E.

(CDRL A012

Any Contractor employee exhibiting unsafe behavior may be removed from the NSWC Crane site. Such removal shall not relieve the Contractor from meeting its contractual obligations and shall not be considered an excusable delay as defined in FAR 52.249-14.

4.4.1 Activity Hazard Analysis (AHA)

Before beginning each activity, task, or Definable Feature of Work (DFOW) involving a type of work presenting hazards not experienced in previous project operations, or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity must prepare an AHA. Format the AHA in accordance with EM 385-1-1, Section 1 or as directed by the COR. Submit the AHA for review, at maximum, ten (10) working days after the PAK meeting. (CDRL A005) The Government reserves the right to require the Contractor to revise and resubmit the AHA if it fails to effectively identify the work sequences, specific anticipated hazards, site conditions, equipment, materials, personnel and the control measures to be implemented.

4.4.2 Accident Prevention Plan

Contractor shall provide a site-specific Accident Prevention Plan (APP), including Activity Hazard Analyses (AHA), in accordance with EM 385-1-1 Appendix A, paragraph 3.k and accordance with DoDD 4715.1E, for the construction team to follow during design, each DFOW, site visits, testing, and investigations. Update the APP if there are changes in the personnel, or the tasks to be performed. Submit the APP for review and acceptance by the Government at maximum, ten (10) days after the PAK meeting. (CDRL A006) Plan must be accepted by the COR before work can begin. SSHO may also be designated the role of the QCM and Superintendent if individual meets all applicable criteria.

4.5 Closeout Submittals

As-built drawings are developed and maintained by the Contractor and depict actual conditions, including deviations from the

RFP16200000132 12 of 47

Contract Documents. These deviations and additions may result from coordination required by, but not limited to: contract modifications; official responses to Contractor submitted Requests for Information; direction from the Contracting Officer; designs, which are the responsibility of the Contractor, and differing site conditions. Maintain the as built throughout construction as redlined hard copies on site. These files serve as the basis for the creation of the record drawings. Other closeout submittals may include, but not limited to, warranty documentation, operation and maintenance manuals, manifests, testing results, equipment training report, as applicable. The as-built drawings shall be submitted for COR approval, at a minimum, five (5) working days prior to Beneficial Occupancy Date (BOD). (CDRL A008)

5.0 TECHNICAL DATA DELIVERABLES

All CDRL’s that are sent to the COR for approval shall use CR- 1022-ACQ-FM-11000-000002, CDRL transmittal form as a cover page.

See Attached CDRL table

6.0 SPECIAL CONDITIONS

6.1 Contracting Officer’s Representative (COR)

The COR is the point of contact for non-substantiated communications of a technical nature. Only the Contracting Officer has the authority to change the requirements of this order(s).

6.2 Requiring Technical Activity (RTA)

The RTA contacts are Functional Managers, Task Managers, and project leads. RTAs do not have the authority to direct Contractor personnel or change the requirements of this order(s) or change the requirements of any TO(s). RTA’s shall be copied on each CDRL deliverable identified.

6.3 Hazardous Materials

The Contractor will provide a responsible party for the handling of the hazardous materials and the respective SDS. This responsibility includes proper training in the handling and disposal of the hazardous materials. If any unforeseen hazardous material is found or suspected to be hazardous material, the contractor shall notify the COR. (CDRL A007) Stop work and wait for government instruction.

RFP16200000132 13 of 47

6.4 Control of Contractor Personnel

Contractor personnel shall physically access government facilities and installations for purposes of site visitation, meeting attendance, supervisory and work performance within government spaces (either temporary or permanent). Individuals supporting these efforts shall comply with the latest security regulations applicable to the government facility/installation.

a) Depending on the facility/installation regulations, Contractor personnel shall present a proper form of identification(s) and vehicle proof of insurance or vehicle rental agreement.

b) All Contractor persons engaged in work while on government property shall be subject to inspection of their vehicles at any time by the government, and shall report any known or suspected security violations to the local host Security Department.

c) All persons engaged in work while on Government property shall be subject to search of their persons (no bodily search) and vehicles at any time by the Government, and shall report any known or suspected security violations to the NSWC Crane Security Department.

d) Assignment, transfer, and reassignment of Contractor personnel shall be at the discretion of the Contractor. However, when the Government directs, the Contractor shall remove from contract performance any person who endangers life, property, or national security through improper conduct.

e) All Contractor personnel engaged in work while on Government property shall be subject to the Standards of Conduct contained in SECNAVINST 5370.2J (Standards of Conduct and Government Ethics).

f) Prior to conducting work under this contract, the Contractor shall provide a list of employees that will be working on site.

The employee list shall contain full names, security clearance levels, social security numbers, job titles, and official birth certificates. This list shall be updated within forty-eight hours after changes occur.

g) Any photography on base is not permitted without prior approval and photography permit request submitted to the COR.

Permit request must be approved and signed by the COR prior to

RFP16200000132 14 of 47 any photos being taken. All photos taken, after approval, must be analyzed and approved prior to release.

h) Restricted Areas - visitor control and surveillance of personnel in a restricted area requires security consciousness and is the responsibility of all personnel working in the area.

6.5 Accident Reporting

The Contractor shall maintain an accurate record of and shall report all accidents to the COR within 10 minutes after incident occurs. (CDRL A009) For Navy Projects, complete a near miss report (CDRL A009). Near miss reports are considered positive and proactive Contractor safety management actions.

6.6 Smoking Regulations

Smoking on NSWC Crane, Crane, IN premises shall be in approved areas only in accordance with NSACRANEINST 5100.13A (NSA Crane Smoking and Tobacco Use). Smoking in vehicles is prohibited.

6.7 Damage Reporting

The Contractor shall maintain an accurate record of and shall report to the COR (within 10 minutes) all damages to Government Owned Equipment and Facilities as prescribed by OPNAVINST

5102.1. (CDRL A010)

6.8 Investigations

Contractor employees shall cooperate with Government investigative agencies conducting criminal or administrative investigations.

6.9 Government Observations

Government personnel, such as Inspector General or higher headquarters staff, are authorized to observe Contractor operations. Efforts will be made to minimize the degree of disturbance on Contractor performance.

6.10 Hours of Operation

NSWC Crane core duty hours for on-site Contractor personnel and the Contractor’s liaison facility personnel assigned to this

RFP16200000132 15 of 47 effort are 0900 to 1430 hours, Monday through Friday, during regular Government workdays.

Government personnel are afforded a flextime schedule that allows a starting time between the hours of 0600 and 0900, with a quitting time between the hours of 1430 and 1800 depending on the applicable work schedule. Contractors are required to work during Government work hours in accordance with company timekeeping policies. The RTA will need to coordinate individually with each building POC where work is to be performed to arrange contractor available working times.

Exceptions may be approved by the COR if requested by the Contractor.

6.11 Closed Days

All closed days will be designated by the Commander, NSA Crane.

Closed days will be associated with holidays, National Security, and/or inclement weather/dangerous conditions. The Contractor will not be allowed to work on NSA Crane during designated closed days.

6.12 Inclement Weather

When the Government Agency is closed by the Commander because of inclement weather conditions and/or dangerous conditions, notification of the closing will be broadcast over local radio and television stations.

6.13 Licenses, Certifications, and Training

The Contractor shall provide capable personnel with qualifications, experience levels, security clearances, and necessary licenses, certifications, and training required by Federal, State, and Local laws and regulations. Training necessary to ensure that personnel performing under this contract maintain the knowledge and skills to successfully perform the required functions is the responsibility of the Contractor. Training necessary to maintain professional certification is the responsibility of the Contractor.

6.14 Contractor Identification

This contract is for non-personal services as defined by FAR Subpart 37.104. As such, Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishing badges or other visible identification for

RFP16200000132 16 of 47 meetings with Government personnel. In addition, Contractor personnel shall appropriately identify themselves as Contractor employees in telephone conversations and in formal and informal written correspondence. Contractor shall provide a Contractors Personnel Roster. (CDRL A011)

6.15 Post Award Meetings

A Post Award Meeting with the successful offeror will be conducted within 15 working days after award of the contract.

The meeting will be held at (to be identified at award). The Contractor will be given at least five working days’ notice prior to the date of the meeting by the Contracting Officer. The requirement for a Post Award meeting shall, in no event, constitute grounds for excusable delay by the Contractor in performance of any provisions of the contract. A second post award meeting may, if necessary, be held after the receipt of the first invoice to assure that adequate documentation has been received to substantiate the validity of the invoice for the stated period of performance, in accordance with C-242-H002. The Contractor will be given at least five (5) working days’ notice prior to the date of the meeting by the Contract Specialist.

7.0 Place of Performance

The primary work site will be Naval Surface Warfare Center Crane Division, Crane, IN unless noted otherwise.

8.0 Period of Performance (POP)

The POP for this effort is: 180 days from award

Section D: Packaging and Marking

PRESERVATION, PACKING AND MARKING

Preservation, packaging, and packing for all items delivered hereunder shall be in accordance with commercial practice, and shall be paid by the contractor. All packaging, postage fees and payment related to submitting information, forms and reports, etc. to the Government (i.e. Contracting Officer, Contracting Officer's Representative) shall be paid by the Contractor.

MARKING

RFP16200000132 17 of 47

All information submitted to the Contracting Officer or the Contracting Officer's Representative shall clearly indicate the contract number and task order number, if applicable, for which the information is being submitted.

Section E: Inspection and Acceptance

CONTRACTING OFFICER'S REPRESENTATIVE (COR)

The COR is responsible, as applicable, for: receiving all deliverables, inspecting and accepting the supplies or services provided hereunder in accordance with the terms and conditions of this contract; providing direction to the contractor which clarifies the contract effort, fills in details or otherwise serves to accomplish the contractual Scope of Work; evaluating performance;

and certifying all invoices/vouchers for acceptance of the supplies or services furnished for payments. Also, see Section H.3 of the solicitation.

52.236-5 Material and Workmanship (APR 1984)

52.246-12 Inspection of Construction. (Aug 1996)

Section F: Delivery & Performance

PERFORMANCE SITE

Naval Surface Warfare Center Crane Division, Crane, IN 47522

Buildings 122, 143, 363, 2547, 2805, 2987, 3227, 3234, 3285, 3286, 3287, 3330 West, North, and South, 3334, 3461, 142, and 8000 (Lake Glendora).

FAR 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

For each building, the Contractor shall be required to (a) commence work under the awarded contract within 10 calendar days of receipt of task order, and (b) prosecute the work diligently.

The time stated for completion shall include final cleanup of the premises.

(End of clause)

Alternate I (Apr1984)

RFP16200000132 18 of 47

Section G Contract Administration Data:

FEDERAL GOVERNMENT HOLIDAYS

The following is a list of Federal Holidays observed by the Government:

Washington's Birthday (3rd Monday in February) Memorial Day (last Monday in May) Juneteenth (JUN 19) Independence Day (JUL 4) Labor Day (1st Monday in September) Columbus Day (2nd Monday in OCT) Veteran's Day (November 11th) Thanksgiving (4th Thursday in November) Christmas (DEC 25)

ADMINISTRATIVE INFORMATION

A. ROLE OF GOVERNMENT PERSONNEL AND RESPONSIBILITY FOR

CONTRACT AWARD AND ADMINISTRATION

1. Administration of this contract shall be performed by:

Jason Morgan, Contract Specialist Telephone: 1-800-827-3168 ext 3002 E-mail: jason.morgan2@usdoj.gov Address:

UNICOR, Federal Prison Industries Attn: Jason Morgan, UNICOR Contracting Officer

3301 LEESTOWN RD

LEXINGTON, KY 40511

Written communications shall make reference to the contract number and shall be mailed to the above address, or sent via Email to jason.morgan2@usdoj.gov

Administrative Contracting Officer is Jason Morgan at jason.morgan2@usdoj.gov

The Contracting Officer (CO) has the overall and primary responsibility for the administration of this Contract. The CO alone, without delegation, is authorized to take actions on behalf of the Government to: modify or deviate from the contract terms, conditions, requirements, specifications, details and/or delivery schedules; make final

RFP16200000132 19 of 47 decisions involving deductions from contract payments or other consideration due to the Government, for nonperformance or unsatisfactory performance, whether or not in dispute; terminate the contract for convenience or default; issue final decisions regarding contract questions or matters under dispute. The CO may delegate certain other responsibilities to an authorized representative.

JAR 2852.201-70, CONTRACTING OFFICER'S REPRESENTATIVE

a) The following are hereby designated to act as Contracting Officer's Representative (COR) under this contract:

Joseph Regan, Program Analyst Acquisition & Construction Management Branch Naval Surface Warfare Center, Crane Division, (NSWC Crane) Code 1022, Bldg. 2 300 Highway 361 Crane, IN 47522-5001 Ph:812-854-2639

DSN: 482-2639

Email: joseph.p.regan.civ@us.navy.mil

(b) The COR is responsible, as directed by the CO, for: 1.

receiving all deliverables, inspecting and accepting the supplies or services provided hereunder in accordance with the terms and conditions of this contract; 2. providing direction to the contractor which clarifies the contract effort; 3. fills in details or otherwise serves to accomplish the contractual Scope of Work; 4. evaluating performance; and certifying all invoices/vouchers for acceptance of the supplies or services furnished for payments.

(c) The COR does not have the authority to alter the contractor's obligations under the contract, and/or modify any of the expressed terms, conditions, specifications, or cost of the agreement. If as a result of technical discussions, it is desirable to alter/change contractual obligations or the Scope of Work, the Contracting Officer shall issue such changes in writing and signed.

RFP16200000132 20 of 47

REQUIREMENTS FOR CORRECTION OF SUB-STANDARD PERFORMANCE

When any member of the Contract Administration Team (CO & COR) becomes aware of substandard performance in any area of the Contract, the Contractor will be given verbal and/or written notification, depending on the circumstances of the issue. The Contractor shall resolve the performance issues consistent with the requirements specified in the SOW and/or task order. For other types of deficiencies where the corrective actions are not specifically stated, the Contractor shall submit a Plan of Action to correct the performance issue within ten (10) working days. If it is not corrected to the satisfaction of the Contract Administration Team member, the Contract Administration Team member shall annotate the performance files and include the observations in the Contractor Performance Report as appropriate.

52.236-7 Permits and Responsibilities (NOV 1991)

Section H Special Contract Requirements:

PROJECT MAGNITUDE

Pursuant to paragraph 36.204 of the Federal Acquisition Regulation, the estimated cost of this acquisition is between $500,000.00 and $1,000,000.00

CONTRACT AWARD

The Government intends to award a Firm Fixed-Price Architecture and Engineering type Contract as a result of this request for proposal. Award will be made to the offeror, pursuant to an affirmative determination of responsibility, whose offer conforms to the terms of the solicitation, and is determined to be in the best interest of the Government, based upon evaluation of the factors included in this solicitation.

SUBMISSION AND PAYMENT OF INVOICES

Reference Standard Contract Clause entitled "Prompt Payment For Construction Contracts (FAR 52.232-

27) of this solicitation. All invoices shall include the complete contract number and line item(s) billed. To avoid delay in payment, invoices shall be submitted in an original and one copy (if prepared by a copying process, one copy shall be marked

RFP16200000132 21 of 47

"Original").

Pay Applications and Certified Payrolls shall be submitted to:

UNICOR, Federal Prison Industries, ATTN: Jason Morgan, UNICOR Contracting Officer, 3301 LEESTOWN RD, LEXINGTON, KY 40511

859-255-6812 EXT 3002

jason.morgan2@usdoj.gov Joseph Regan, Program Analyst Acquisition & Construction Management Branch Naval Surface Warfare Center, Crane Division, (NSWC Crane) Code 1022, Bldg. 2 300 Highway 361

Crane, IN 47522-5001 Ph:812-854-2639

DSN: 482-2639

Email: joseph.p.regan.civ@us.navy.mil

Due to mail delays caused by security precautions, do not use U.S. Postal Service mail. Packages from any of the messenger services (FedEx, UPS, DHL, etc.) are accepted at this address. The preferred method of invoice submission is electronically (via email) to Jason.morgan2@usdoj.gov.

Delay in contractor payment due to invoice submission to any address other than the physical or email address listed above shall be the fault of the contractor, and payment will be processed only upon receipt at the physical or email address noted above, and after approval by UNICOR's customer NSWC and the project COR.

ALL INVOICES SHALL REFERENCE THE CONTRACT NUMBER.

All invoices must match the contract dollar amount and payments will only be processed upon approval by UNICOR's customer NSWC and project COR.

PREFERED METHOD: Submission of "Invoices by E-mail":

Payment Applications must be submitted using AIA Document G702/G703.

Please submit 1 invoice to the following individual at their

RFP16200000132 22 of 47 business e-mail addresses listed below:

Jason Morgan, Contracting Officer Jason.morgan2@usdoj.gov

Michael Compton, Construction Control Representative mcompton@central.unicor,gov

LIABILITY COVERAGE / INSURANCE

52.228-5 Insurance-Work on a Government Installation

Insurance-Work on a Government Installation (Jan 1997)

(a) The Contractor shall, at its own expense, provide and maintain during the entire performance of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.

(b) Before commencing work under this contract, the Contractor shall notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective-

(1) For such period as the laws of the State in which this contract is to be performed prescribe;

or

(2) Until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.

(c) The Contractor shall insert the substance of this clause, including this paragraph (c), in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor shall maintain a copy of all subcontractors' proofs of required insurance, and shall make copies available to the Contracting Officer upon request.

RFP16200000132 23 of 47

(a) (In accordance with Standard FAR Contract Clause 52.228-5 entitled "Insurance - Work on a Government Installation (JAN 1997) the Contractor shall procure and maintain, during the entire period of his performance under this contract, the following minimum insurance:

(1) General Liability Insurance Bodily injury liability insurance, in the minimum limit of $500,000 per occurrence is required on the comprehensive form policy.

(2) Automobile Liability Insurance This insurance is required on the comprehensive form policy and shall provide bodily injury liability and property damage liability covering the operation of all automobiles sued in connection with the performance of the contract. At least, the minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage shall be required.

(3) Workmen's Compensation and Employer's Liability Insurance Employer's liability coverage is required in the minimum amount of $100,000 or as required by the state where the project is performed.

(b) Prior to the commencement of work hereunder, the Contractor shall furnish to the Contracting Officer a certificate or written statement of the above required insurance. The policies evidencing required insurance shall contain an endorsement to the effect that cancellation of any material change in the policies adversely affecting the interests of the Government in such insurance shall not be effective for such period as may be prescribed by the laws of the state in which this contract is to be performed and in no event less than thirty (30) days after written notice thereof to the Contracting Officer.

(c) The Contractor agrees to insert in all subcontracts the required insurance information provided above, including this paragraph (c).

CONTRACTOR'S RESPONSIBILITY

It is the responsibility of the Contractor to follow any Special Security Requirements of the facility where the work is performed in the performance of the contract and to consider the effects of those security requirements in the pricing of the

RFP16200000132 24 of 47 proposal. The Contractor is required to furnish all services, materials, labor, tools, and equipment necessary to fulfill the work as set out in the Statement of Work. The Contractor must be aware of standards, codes, requirements and guidelines governing the construction of Government buildings. The Contractor shall comply with all local, state, and federal building codes and life safety codes. The Contractor shall be responsible for all office supplies, included but limited to, pencils, pens, calculators, binders, paper, printers, fax machines, markers, whiteboards, hole punches, staples, etc. The office supplies are not provided as part of this Statement of Work. It shall be the sole responsibility of the Contractor to obtain all information required to successfully carry out each contract task, other than the information provided by the project COR.

RFP16200000132 25 of 47

PART II

Section I Clauses:

52.202-1 Definitions (Jun 2020)

52.203-3 Gratuities (APR 1984)

52.203-5 Covenant Against Contingent Fees (MAY 2014)

52.203-7 Anti-Kickback Procedures (JUN 2020)

52.203-8 Cancellation, Rescission, and Recovery of Funds for illegal or Improper Activity (MAY 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014)

52.203-12 Limitation on Payments to Influence Certain Federal Transactions(JUN 2020)

52.203-16 Preventing Personal Conflicts of Interest (Jun 2020)

52.203-17 Contractor Employee Whistleblower Rights and Requirement to inform Employees of Whistleblower Rights (JUN 2020)

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements- Representation (Jan 2017)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017)

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011)

52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011)

52.204-10 Reporting Executive Compensation and First Tier Subcontract Awards (JUN 2020)

52.204-13 System for Award Management Maintenance (OCT 2018)

52.204-14 Service Contract Reporting Requirements (OCT 2016)

RFP16200000132 26 of 47

52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020)

52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014)

52.204-21 Basic Safeguarding of Covered Contractor Information Systems (NOV 2021)

(a) Definitions. As used in this clause— Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.

Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public websites) or simple transactional information, such as necessary to process payments.

Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).

Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information ( 44 U.S.C. 3502).

Safeguarding means measures or controls that are prescribed to protect information systems.

(b) Safeguarding requirements and procedures.

(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:

(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).

(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.

(iii) Verify and control/limit connections to and use of external information systems.

RFP16200000132 27 of 47

(iv) Control information posted or processed on publicly accessible information systems.

(v) Identify information system users, processes acting on behalf of users, or devices.

(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.

(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.

(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.

(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.

(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.

(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.

(xii) Identify, report, and correct information and information system flaws in a timely manner.

(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.

(xiv) Update malicious code protection mechanisms when new releases are available.

(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.

(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.

(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial products or commercial services, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.

RFP16200000132 28 of 47

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (NOV 2021)

52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021)

The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has…