Solicitation Summary
This is a Request for Proposal (RFP) for the P1555U Wallace Creek Service Road realignment project at MCB Camp Lejeune, North Carolina. The solicitation is limited to three pre-qualified contractors: Quadrant Construction, Inc. (N40085-23-D-0013), Civil Works Contracting, LLC (N40085-23-D-0014), and Riza Construction, Inc. (N40085-23-D-0015). The Naval Facilities Engineering Command (NAVFAC) is the contracting activity, with Anna Lundquist serving as the primary point of contact. Proposals are due December 1, 2026, at 2:00 PM EST, submitted via email to anna.m.lundquist.civ@us.navy.mil and lauren.f.loconto.civ@us.navy.mil. The contract completion date is 730 days after award, with an estimated cost range of $5,000,000 to $10,000,000.
The solicitation employs a lowest-price award basis and includes a base bid (CLIN 0001) with eight subitems (0001A–0001H) covering sitework, structural fill, demolition, contaminated spoils handling, and utility removal work. Seven optional contract line items (CLINs 0002–0008) are included for additional landscaping, sidewalk modifications, concrete island improvements, and alternative spoil disposal methods. All pricing must be provided as firm fixed-price, with liquidated damages of $1,263.51 per calendar day. Bid bond requirements apply to proposals valued at $35,000 or greater (payment bond only) and $150,000 or greater (bid, payment, and performance bonds, each at 20 percent of proposal amount). The Davis-Bacon Act wage determination (NC20260090) applies, with prevailing wage rates ranging from $10.20 to $24.57 per hour depending on classification. RFI submissions close November 16, 2026, at 3:00 PM EST, and all specifications and drawings are posted on sam.gov.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P1555U Wallace Creek Service Road Solicitation No. N40085-27-R-9001
MCB Camp Lejeune, North Carolina Project No. P1555U
10/29/2026
ROICC CAMP LEJEUNE
POC: Anna Lundquist anna.m.lundquist.civ@us.navy.mil
ONLY THE FOLLOWING LIST OF CONTRACTORS MAY SUBMIT A PROPOSAL FOR
THIS PROJECT:
N40085-23-D-0013
Quadrant Construction, Inc.
166 Center Street
Jacksonville, NC 28546
(910) 937-0003
POC: Chris Whaley chriswhaley@qcenc.com
N40085-23-D-0014
Civil Works Contracting, LLC
190 Raleigh Street
Wilmington, NC 28412
(910) 859-8574
POC: Pat Paluso ppaluso@civilworkscontracting.com
N40085-23-D-0015
Riza Construction, Inc.
228 Chaparral Trail
Jacksonville, NC 28546
(910) 934-0385
POC: Evette Britton evette.britton@rizaconstruction.com
GENERAL REQUIREMENTS
NAVFAC Solicitation No.: N40085-27-R-9001
Public Works Project No.: P1555U
Title: P1555U Wallace Creek Service Road
Contract Completion Date: 730 days after award
Estimated Cost Range: Between $5,000,000 and $10,000,000
Wage Determination: General Decision Number: NC20260090 5/18/2026 Highway
Liquidated Damages: $1,263.51 per Calendar Day
Notes: One person may fill the roles of Superintendent, Quality Control Manager, and Safety and Health
Officer, if duly qualified for all three positions as defined in the project specification.
Special Scheduling: None
Basis for Award: Lowest Price
SEE PRICING SHEET BELOW
Proposal Acceptance Period: 60 days from receipt of offers
Site Visit: A site visit will be scheduled via amendment.
Bond Requirements: Bid bonds are required based on the dollar values listed below. If required, the bid bond should be 20% of the proposal amount. An electronic copy of your bid bond may be submitted with your proposal. Failure to submit a required bid bond by the deadline will result in your proposal being removed from consideration. Utilize the bond formats at FAR 53.300. Payment and/or performance bond(s) will be requested at the time of award per the current process.
• No bonds are required for proposals less than $35K.
• Proposals valued at $35K and greater will require a payment bond only.
• Proposals valued at $150K and greater will require a bid bond, a payment bond, and a performance bond.
Proposal Due Date: 12/1/2026 2:00 PM EST
E-Mail Address for Proposals: anna.m.lundquist.civ@us.navy.mil and lauren.f.loconto.civ@us.navy.mil
Requests for Information (RFIs): RFIs must be submitted by the prime contractor to anna.m.lundquist.civ@us.navy.mil. The cut off for RFIs is 11/16/2026 by 3:00 PM EST in order to process all inquiries by the proposal due date.
The specifications and drawings are posted as attachments on https://sam.gov/.
“OFFERORS ARE ADVISED THAT FUNDING MAY NOT BECOME AVAILABLE. IF FUNDS
ARE NOT AVILABLE, NO AWARD WILL BE MADE AS RESULT OF THIS SOLICITATION.
OFFERORS WILL NOT BE REIMBURSED FOR ANY EFFORT OR PROPOSAL COSTS
RESULTING FROM THIS SOLICITATION.”
General Decision Number: NC20260090 05/18/2026
State: North Carolina
Construction Types: Highway
Counties: North Carolina Counties of
Brunswick, Cumberland, Currituck, Edgecombe, Franklin, Greene, Hoke, Johnston, Nash, New Hanover, Onslow, Pender, Pitt, Wake and Wayne
Modification Number Publication Date
0 01/02/2026
1 05/18/2026
SUNC2014-005 11/17/2014
Rates Fringes
TRUCK DRIVER (GVWR OF 26,001 LBS OR GREATER)........$ 12.37 0.00
TRUCK DRIVER (GVWR OF 26,000 OR LESS)...............$ 11.12 0.00
POWER EQUIPMENT OPERATOR: MILLING MACHINE...........$ 15.36 0.00
POWER EQUIPMENT OPERATOR: MECHANIC..................$ 17.55 0.00
POWER EQUIPMENT OPERATOR (TACK TRUCK/DISTRIBUTOR
OPERATOR)...........................................$ 14.52 0.00
POWER EQUIPMENT OPERATOR (SLIP FORM MACHINE)........$ 16.50 0.00
POWER EQUIPMENT OPERATOR (SCRAPER ROUGH)............$ 11.35 0.00
POWER EQUIPMENT OPERATOR (SCRAPER FINISH)...........$ 12.71 0.00
POWER EQUIPMENT OPERATOR (ROLLER OTHER).............$ 11.36 0.00
POWER EQUIPMENT OPERATOR (ROLLER ASPHALT FINISH)....$ 13.85 0.00
POWER EQUIPMENT OPERATOR (ROLLER ASPHALT BREAKDOWN).$ 12.45 0.00
POWER EQUIPMENT OPERATOR (PAVER CONCRETE)...........$ 18.20 0.00
POWER EQUIPMENT OPERATOR (PAVER ASPHALT)............$ 15.59 0.00
POWER EQUIPMENT OPERATOR (PAVEMENT MARKING
EQUIPMENT)..........................................$ 12.11 0.00
POWER EQUIPMENT OPERATOR (OILER/GREASER)............$ 13.55 0.00
POWER EQUIPMENT OPERATOR (OFF-ROAD HAULER/WATER
TANKER).............................................$ 11.36 0.00
POWER EQUIPMENT OPERATOR (MATERIAL TRANSFER VEHICLE
(SHUTTLE BUGGY))....................................$ 15.18 0.00
POWER EQUIPMENT OPERATOR (LOADER GREATER THAN 2
CUBIC YARDS)........................................$ 14.14 0.00
POWER EQUIPMENT OPERATOR (LOADER 2 CUBIC YARDS OR
LESS)...............................................$ 13.76 0.00
POWER EQUIPMENT OPERATOR (GRADER/BLADE ROUGH).......$ 14.62 0.00
POWER EQUIPMENT OPERATOR (GRADER/BLADE FINE)........$ 18.47 0.00
POWER EQUIPMENT OPERATOR (EXCAVATOR ROUGH)..........$ 14.00 0.00
POWER EQUIPMENT OPERATOR (EXCAVATOR FINE)...........$ 16.60 0.00
POWER EQUIPMENT OPERATOR (DRILL OPERATOR STRUCTURE).$ 21.14 0.00
POWER EQUIPMENT OPERATOR (DRILL OPERATOR ROCK)......$ 14.38 0.00
POWER EQUIPMENT OPERATOR (CRANE ROUGH/ALL TERRAIN)..$ 20.67 0.00
POWER EQUIPMENT OPERATOR (CRANE OTHER)..............$ 20.08 0.00
POWER EQUIPMENT OPERATOR (CRANE BOOM TRUCKS)........$ 20.54 0.00
POWER EQUIPMENT OPERATOR (CONCRETE GRINDER/GROOVER).$ 20.34 2.30
POWER EQUIPMENT OPERATOR (BULLDOZER ROUGH)..........$ 14.34 0.00
POWER EQUIPMENT OPERATOR (BULLDOZER FINE)...........$ 17.04 0.00
POWER EQUIPMENT OPERATOR (ASPHALT BROOM TRACTOR)....$ 11.85 0.00
PAINTER (BRIDGE)....................................$ 24.57 0.00
LABORER: PIPELAYER..................................$ 12.17 0.00
LABORER: COMMON OR GENERAL..........................$ 10.20 0.00
LABORER (TRAFFIC SIGNAL/LIGHTING INSTALLER).........$ 14.89 0.00
LABORER (GUARDRAIL/FENCE INSTALLER).................$ 12.87 0.00
LABORER (CEMENT MASON/CONCRETE FINISHER TENDER).....$ 12.54 0.00
LABORER (CARPENTER TENDER)..........................$ 12.88 0.00
LABORER (ASPHALT SCREED/JACKMAN)....................$ 14.33 0.00
LABORER (ASPHALT RAKER AND SPREADER)................$ 12.46 0.00
IRONWORKER..........................................$ 16.02 0.00
ELECTRICIAN (TELECOMMUNICATIONS TECHNICIAN).........$ 16.79 0.63
ELECTRICIAN (ELECTRICIAN)...........................$ 17.97 0.00
CEMENT MASON/CONCRETE FINISHER......................$ 14.48 0.00
CARPENTER...........................................$ 13.72 0.00
BLASTER.............................................$ 21.04 0.00
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the
Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to
Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually.
Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than
�SU�, �UAVG�, �SA�, or �SC� denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The �SU� identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007
6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
�SU� wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The �SA� identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007
01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the �SA� identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION
52.225-12 Notice of Buy American Requirement-Construction Materials.
As prescribed in 25.1102(b)(1), insert the following provision:
Notice of Buy American Requirement-Construction Materials (May 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material,"
"domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American-Construction Materials"
(Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the
Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy
American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs
(c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested-
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
PRICING SHEET
Under the line items furnished, the offers shall state prices for each Exhibit Line Item Number
(ELIN) given hereinafter:
ELIN 0001 – Base Bid
Price includes completing all work associated with the P1555U Wallace Creek Service Road
Realignment, including ELINs 0001A – 0001H in accordance with the provided drawings and specifications, but excluding work described in ELINs 0002-0008. The price for this line item should include all applicable costs, overhead and profit for this work.
ELIN 0001A
Price includes completing all work associated with all sitework for all entrances, roads and roundabout complete in accordance with the provided drawings and specifications, but excluding work described in ELINs 0001B-0001H, 0002-0008. The price for this line item should include all applicable costs, overhead and profit for this work.
ELIN 0001B
Price includes completing all work associated with the undercut and disposal of geotechnically unsuitable subgrade soils and replacement with Imported Structural Fill complete in accordance with the provided drawings and specifications, but excluding work described in
ELINs 0001A, 0001C-0001H, 0002-0008. The price for this line item should include all applicable costs, overhead and profit for this work.
Quantity Unit Price Total
750 CY $ $ _____________________________________
ELIN 0001C
Price includes completing all work associated with the demolition, excavation, backfill and disposal of buried debris 1/2 CY and larger in size encountered within planned excavation limits and not identified in the contract documents for demolition complete in accordance with the provided drawings and specifications, but excluding work described in ELINs 0001A-
0001B, 0001D-0001H, 0002-0008. The price for this line item should include all applicable costs, overhead and profit for this work.
150 Tons $ $ _____________________________________
ELIN 0001D
Price includes completing all work associated with the handling, temporary stockpiling, sampling, analysis, and disposal of contaminant impacted surplus excavation spoils
(including, but not limited to, PFAS, petroleum, metals, and SVOCs) complete in accordance with the provided drawings and specifications, but excluding work described in
ELINs 0001A-0001C, 0001E-0001H, 0002-0008. The price for this line item should include all
750 CY $ $ _____________________________________
ELIN 0001E
Price includes completing all work associated with the removal and disposal of existing utility less than 6” diameter and less than 4’ deep, crossing in conflict with proposed improvements matching existing size not identified in the Contract Documents in accordance with the provided drawings and specifications, but excluding work described in
ELINs 0001A-0001D, 0001F-0001H, 0002-0008. The price for this line item should include all
50 LF $ $ _____________________________________
ELIN 0001F
greater than 6” diameter and less than 4’ deep, crossing in conflict with proposed improvements matching existing size not identified in the Contract Documents in accordance with the provided drawings and specifications, but excluding work described in
ELINs 0001A-0001E, 0001G-0001H, 0002-0008. The price for this line item should include all
ELIN 0001G
less than 6” diameter and greater than 4’ deep, crossing in conflict with proposed improvements matching existing size not identified in the Contract Documents in accordance with the provided drawings and specifications, but excluding work described in
ELINs 0001A-0001F, 0001H, 0002-0008. The price for this line item should include all
ELIN 0001H
greater than 6” diameter and greater than 4’ deep, crossing in conflict with proposed improvements matching existing size not identified in the Contract Documents in accordance with the provided drawings and specifications, but excluding work described in
ELINs 0001A-0001G, 0002-0008. The price for this line item should include all applicable costs, overhead and profit for this work.
ELIN 0002 – Option 1
Price includes completing all work associated with the additional landscaping in accordance with the provided drawings and specifications, but excluding work described in ELINs 0001, 0003-0008. The price for this line item should include all applicable costs, overhead and profit for this work.
1 LS $ $ _____________________________________
ELIN 0003 – Option 2
Price includes completing all work associated with the decrease proposal of new 8’ wide sidewalk to 6’ wide in accordance with the provided drawings and specifications, but excluding work described in ELINs 0001-0002, 0004-0008. The price for this line item should include all
ELIN 0004 – Option 3
Price includes completing all work associated with the splitter islands to be concrete in leu of grass in accordance with the provided drawings and specifications, but excluding work described in ELINs 0001-0003, 0005-0008. The price for this line item should include all
ELIN 0005 – Option 4
Price includes completing all work associated with the undercut and disposal of geotechnically unsuitable subgrade soils that exceed CLIN 0001B’s quantity and replacement with
Imported Structural Fill complete in accordance with the provided drawings and specifications, but excluding work described in ELINs 0001-0004, 0006-0008. The price for this line item should include all applicable costs, overhead and profit for this work.
250 CY $ $ _____________________________________
ELIN 0006 – Option 5
Price includes completing all work associated with the handling, temporary stockpiling, sampling, analysis, and disposal of contaminant impacted surplus excavation spoils
(including, but not limited to, PFAS, petroleum, metals, and SVOCs) that exceed CLIN
0001D’s quantity complete in accordance with the provided drawings and specifications, but excluding work described in ELINs 0001-0005, 0007-0008. The price for this line item should include all applicable costs, overhead and profit for this work.
250 CY $ $ _____________________________________
ELIN 0007 – Option 6
Price includes completing all work associated with the undercut and disposal of non-contaminated surplus excavation spoils at an Off-Installation permitted licensed treatment/disposal facility in lieu of the MCBCL Landfill complete in accordance with the provided drawings and specifications, but excluding work described in ELINs 0001-0006, 0008.
The price for this line item should include all applicable costs, overhead and profit for this work.
3,750 CY $ $ _____________________________________
ELIN 0008 – Option 7
Price includes completing all work associated with the excavation, handling, temporary stockpiling, sampling, analysis, and disposal of contaminant impacted surplus excavation spoils (including, but not limited to, PFAS, petroleum, metals, and SVOCs) complete, at an
Off-Installation permitted licensed treatment/disposal facility in lieu of the MCBCL landfill in accordance with the provided drawings and specifications, but excluding work described in
ELINs 0001-0007. The price for this line item should include all applicable costs, overhead and profit for this work.
1,000 CY $ $ _____________________________________
TOTAL ELINs 0001 - 0008: $______________________________________
Notes
A. Award will be made on the total sum price of Contract Line Item 0001, and the extended total under Contract Line items 0002 through 0008. For CLINs 0001A through 0001H, enter unit prices and extended totals in spaces provided. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid, and the total will be recomputed accordingly. If an Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.
B. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR
17.206(b) Evaluation not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for the Option(s) to the total price for CLIN 0001. In accordance with FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Option(s).
C. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
D. Failure to enter a price for any CLIN will result in a proposal being rejected.
E. The Government reserves the unilateral right to award CLINs 0002 through 0008 to the
Contractor at the proposed price within 120 calendar days after the contract award. A firm fixed price is required for CLINs 0001 through 0008. The Contract Completion Date
(CCD) does not change if CLINs 0002, 0003, 0004, 0005, 0006, 0007, and 0008 are exercised.
F. If CLINs 0002 through 0008 are exercised, additional bonding and consent of surety is required. Consequently, the Performance Bond must reflect 100 percent of the aggregate amount of all items.