P-1555U WCSR PROD.pdf
PDF 550 KB Posted
- Attached to
- P1555U Wallace Creek Service Road
- Solicitation number
- N4008527R9001
About this file
This is a NAVFAC MIDLANT Permits Record of Decision (PROD), Revision 1, documenting environmental and regulatory permits required for the P1555U Wallace Creek Service Road Realignment project at Marine Corps Base Camp Lejeune. The project is located at MCB Camp Lejeune and is being executed under Contract N40085-24-D-0042, Task Order N40085-24-F-5993, with eProjects Work Order Number 1810206. Project Manager Lisa Ferrell prepared the document on 8 September 2025, with an update date of 19 September 2025.
The PROD identifies permits across three project phases: Planning-Environmental, Design, and Construction-Operating. During the Planning-Environmental phase, the project determined that permits for Essential Fish Habitat Assessment, Marine Mammal Protection Act, Take Permits, and Endangered/Species/Critical Habitat consultations are not required based on absence of streams and coverage under the MCBCL 2020-2025 Integrated Natural Resource Management Plan. A NEPA Categorical Exclusion was issued on 20 January 2021 (NEPA LE20117). The Design phase requires permits from the North Carolina Department of Environmental Quality (NCDEQ) for Erosion & Sediment Control Plan Approval and Post-Construction Stormwater Permit, with responsible agents identified as NAVFAC ML Design (Civil). The project involves modifying three existing stormwater permits and issuing a new permit through the MCBCL MS4 program. The Construction-Operating phase requires permits for Monitoring Well Abandonment, Monitoring Well Permit, Explosive Safety Submission (DDESB), Utility Outages (MCBCL PWD), and Dig Ticket approval (NC 811), with construction contractors bearing primary responsibility for these submissions.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAVFAC MIDLANT PERMITS RECORD OF DECISION (PROD) REV. 1
PROJECT TITLE: PHASE:
LOCATION: PREPARED:
WORK ORDER NO: UPDATED:
PROJECT MANAGER:
1 CATEGORY REQ'D? PERMIT TYPE: Essential Fish Habitat Assessment Consultation SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME:
Other Permits RESPONSIBLE AGENT: (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
2 SPECIAL CONDITIONS:
2 CATEGORY REQ'D? PERMIT TYPE: Marine Mammal Protection Act SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME:
Other Permits RESPONSIBLE AGENT: (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
2 SPECIAL CONDITIONS: Not applicable
3 CATEGORY REQ'D? PERMIT TYPE: Take Permits SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME:
Other Permits RESPONSIBLE AGENT: (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
2 SPECIAL CONDITIONS:
4 CATEGORY REQ'D? PERMIT TYPE: Endangered/Species/Critical Habitat SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME:
Other Permits RESPONSIBLE AGENT: (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
2 SPECIAL CONDITIONS:
5 CATEGORY REQ'D? PERMIT TYPE: NEPA CATEX SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: MCBCL EMD PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME: NEPA Categorical Exclusion RESPONSIBLE AGENT: MCBCL PWD (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
NEPA 2 SPECIAL CONDITIONS: NEPA Decision Memorandum (NEPA LE20117) issued January 20, 2021.
There is not a permit required for this. No essential fish habitat within the project study area due to lack of streams.
Not required. While the project location may support habitat for federally protected species, as outlined in the Marine Corps Base Camp Lejeune (MCBCL) 2020-2025 Integrated Natural Resource Management Plan (INRMP): “The Biological Assessment and Biological Opinion for this INRMP will function as the consultation of record for all listed species for the next 5 years or until such time as a new consultation supersedes the measures in this document. Terms and conditions and conservation measures may continue in this INRMP, but the intent of this INRMP is to include all necessary protection, monitoring, and management measures for listed species.”
There is not a permit required for this. While the project location may support habitat for federally protected species, as outlined in the Marine Corps Base Camp Lejeune (MCBCL) 2020-2025 Integrated Natural Resource Management Plan (INRMP): “The Biological Assessment and Biological Opinion for this INRMP will function as the consultation of record for all listed species for the next 5 years or until such time as a new consultation supersedes the measures in this document. Terms and conditions and conservation measures may continue in this INRMP, but the intent of this INRMP is to include all necessary protection, monitoring, and management measures for listed species.”
Lisa Ferrell
P1555U Wallace Creek Service Road Realignment Planning-Environmental MCB Camp Lejeune 8-Sep-25 Contract N40085-24-D-0042, Task Order N40085-24-F-5993, eProjects Work Order Number 1810206 19-Sep-25
PROJECT TITLE: PHASE:
LOCATION: PREPARED:
WORK ORDER NO: UPDATED:
PROJECT MANAGER:
CATEGORY REQ'D? PERMIT TYPE: Erosion & Sediment Control SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: NCDEQ PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME: Erosion & Sediment Control Plan Approval Water Pollution RESPONSIBLE AGENT: NAVFAC ML Design (Civil) (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
2 SPECIAL CONDITIONS:
CATEGORY REQ'D? PERMIT TYPE: Stormwater Management SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: NCDEQ PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME: Post-Construction Stormwater Permit Water Pollution RESPONSIBLE AGENT: NAVFAC ML Design (Civil) (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
2 SPECIAL CONDITIONS:
CATEGORY REQ'D? PERMIT TYPE: Wastewater Collection System SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME:
Water Pollution RESPONSIBLE AGENT: (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
2 SPECIAL CONDITIONS:
CATEGORY REQ'D? PERMIT TYPE: General NPDES (≥1 Acre Land Disturbance) SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: NCDEQ PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME: General Construction Permit Discharge Permit RESPONSIBLE AGENT: NAVFAC ML Design (Civil) (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
2 SPECIAL CONDITIONS:
The P1555 project is a combination of a linear transportation project and parking lot project. Three existing stormwater permits will be modified to cover stormwater treatment for this project: Hadnot Point Master Permit SW8 020319, Wallace Creek Service Road SW8 090109, and the Marine Mart SW8 130301. A new permit consisting of all linear roadway and parking lot will be issued through the MCBCL MS4 program.
P1555U Wallace Creek Service Road Realignment MCB Camp Lejeune Contract N40085-24-D-0042, Task Order N40085-24-F-5993, eProjects Work Order Number 1810206 Lisa Ferrell
DESIGN
8-Sep-25
Anticipate seeking approval following pre-final design submittal.
Modifications to three existing stormwater permits will be submitted to the Wilmington NC DEQ Regional Office following receipt of revised Hadnot Point Master Permit. The new permit will be submitted to the MCBCL MS4.
Anticipate seeking approval following pre-final design submittal.
PROJECT TITLE: PHASE: Construction-Operating
LOCATION: PREPARED:
WORK ORDER NO: UPDATED:
PROJECT MANAGER:
1 CATEGORY REQ'D? PERMIT TYPE: Monitoring Well Abandonment Permit SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: NCDEQ PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME: Well Abandonment Permit RESPONSIBLE AGENT: Construction Contractor (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
Environmental Compliance 2 SPECIAL CONDITIONS: Abandonment must be completed by a licensed NC drilling operator.
2 CATEGORY REQ'D? PERMIT TYPE: Monitoring Well Permit SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: NCDEQ PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME: Monitoring Well Permit RESPONSIBLE AGENT: Construction Contractor (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
Environmental Compliance 2 SPECIAL CONDITIONS:
3 CATEGORY REQ'D? PERMIT TYPE: Explosive Safety Submission SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: DDESB PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME: Explosive Safety Submission RESPONSIBLE AGENT: Construction Contractor with qualified UXO competent personnel (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
Explosive Safety 2 SPECIAL CONDITIONS:
4 CATEGORY REQ'D? PERMIT TYPE: Utility Outages SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: MCBCL PWD PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME: Utility Connection Permit and Outage Request RESPONSIBLE AGENT: Construction Contractor/CM (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
Utility Permit 2 SPECIAL CONDITIONS:
5 CATEGORY REQ'D? PERMIT TYPE: Dig Ticket SUBMITTAL DATE APPROVAL DATE
ISSUING AGENCY: NC 811 PLANNED ACTUAL PLANNED ACTUAL
PERMIT NAME: Permission to Dig RESPONSIBLE AGENT: Construction Contractor (PWD, BL/CODE, AE, etc.) NOTES/COMMENTS:
Permission to Dig 2 SPECIAL CONDITIONS:
Lisa Ferrell
P1555U Wallace Creek Service Road Realignment MCB Camp Lejeune Contract N40085-24-D-0042, Task Order N40085-24-F-5993, eProjects Work Order Number 1810206
8-Sep-25