Repair BEQ HP510 Solicitation No. N40085-21-R-0080 MCB Camp Lejeune, North Carolina Project 18-0042

ROICC CAMP LEJEUNE

POC: Brooks Sumner Brooks.sumner@navy.mil

ONLY THE FOLLOWING LIST OF CONTRACTORS MAY SUBMIT A

PROPOSAL FOR THIS PROJECT:

N40085-16-D-6300 Blue Rock Structures, Inc.

10689 Hwy 17 Pollocksville, NC 28573 POC: Ellen Hartness Phone: 910-743-0505 ehartness@bluerockstr.com

N40085-16-D-6301 Daniels & Daniels Construction Co., Inc.

P.O. Box 10337 Goldsboro, NC 27532 POC: Damon Jones Phone: 919-778-4525 damonj@danddcc.com

N40085-16-D-6302 Joyce & Associates Construction, Inc.

6994 Hwy 70 Newport, NC 28570 POC: Mary Caison Phone: 252-223-3171 info@joyceandassoc.com

N40085-16-D-6303 Military & Federal Construction Co., Inc.

846 Bell Fork Road Jacksonville, NC 28540 POC: Neil Oliver Phone: 910-353-3797 estimating@militaryandfederal.com

N40085-16-D-6304 Quadrant Construction, Inc.

166 Center Street Jacksonville, NC 28546 POC: Steven Kellum Phone: 910-937-0003 chriswhaley@qcenc.com

N40085-16-D-6305 T.E. Davis Construction Co.

1175 East Davis Road Jacksonville, NC 28546 POC: Brandon Horne Phone: 910-353-3112 bhorne@tedavisconstruction.com

GENERAL REQUIREMENTS

NAVFAC Solicitation No.: N40085-21-R-0080

Public Works Project No.: 18-0042

Title: Repair BEQ HP510

Contract Completion Date: 515 days after award

Estimated Cost Range: Between $5,000,000 and $10,000,000

Wage Determination: General Decision Number: NC20210038 01/01/2021 Building

Liquidated Damages: $4,100 per Calendar Day

Notes: One person may fill the roles of Superintendent and Safety and Health Officer, if duly qualified for both positions as defined in the project specification. However, the Quality Control Manager must be a stand-alone position.

Special Scheduling: None

Basis for Award: Lowest Price

Proposal Acceptance Period: 60 days from receipt of offers

Site Visit: No.

Bond Requirements: Bid bonds are required in accordance with FAR 53.301-24. An electronic copy of your bid bond may be submitted with your proposal. A hard copy of your bid bond must be submitted to the ROICC office within one (1) week after the due date and time for receipt of proposals. Failure to submit a bid bond by the deadline will result in your proposal being removed from consideration. Payment and/or performance bond(s) will be requested at the time of award per the current process.

• No bonds are required for proposals less than $35K.

• Proposals valued at $35K and greater will require a payment bond only.

• Proposals valued at $150K and greater will require a bid bond, a payment bond, and a performance bond.

Proposal Due Date: May 5, 2021

2:00 PM EST

E-Mail Address for Proposals: generalmacc@navy.mil AND brooks.sumner@navy.mil

Proposals may also be hand-delivered to Building 1005.

Requests for Information (RFIs): RFIs must be submitted by the prime contractor to brooks.sumner@navy.mil. The cut off for RFIs is April 21, 2021 by 2:00 PM EST in order to process all inquiries by the proposal due date.

The specifications and drawings are posted as attachments on https://beta.sam.gov/.

“OFFERORS ARE ADVISED THAT FUNDING MAY NOT BECOME AVAILABLE. IF

FUNDS ARE NOT AVILABLE, NO AWARD WILL BE MADE AS RESULT OF THIS

SOLICITATION. OFFERORS WILL NOT BE REIMBURSED FOR ANY EFFORT OR

PROPOSAL COSTS RESULTING FROM THIS SOLICITATION.”

"General Decision Number: NC20210038 01/01/2021

Superseded General Decision Number: NC20200038

State: North Carolina

Construction Type: Building

County: Onslow County in North Carolina.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.

If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate, if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/01/2021

IRON0848-005 07/01/2020

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 26.00 15.80

* PLUM0421-003 07/01/2020

Rates Fringes

PIPEFITTER.......................$ 29.35 12.41

SUNC2011-019 08/24/2011

Rates Fringes

BRICKLAYER.......................$ 19.00 0.00

CARPENTER (Drywall Hanging Only)............................$ 13.83 0.00

CARPENTER (Form Work Only).......$ 13.38 1.80

CARPENTER, Excludes Drywall Hanging, and Form Work...........$ 16.39 4.26

CEMENT MASON/CONCRETE FINISHER...$ 15.80 0.00

ELECTRICIAN......................$ 20.64 6.68

HVAC MECHANIC (HVAC Duct Installation Only)...............$ 17.37 1.82

LABORER: Common or General......$ 11.13 0.32

LABORER: Landscape & Irrigation.......................$ 9.13 0.28

LABORER: Pipelayer..............$ 13.35 2.80

LABORER: Mason Tender-Brick/Cement/Concrete.....$ 12.00 0.00

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 18.47 2.41

OPERATOR: Bulldozer.............$ 16.00 1.87

OPERATOR: Crane.................$ 19.77 4.48

OPERATOR: Forklift..............$ 13.86 0.00

OPERATOR: Grader/Blade..........$ 15.72 1.49

OPERATOR: Loader................$ 16.17 0.25

PAINTER: Brush, Roller and Spray............................$ 12.35 0.00

PLUMBER..........................$ 18.48 3.93

ROOFER...........................$ 11.75 1.06

SHEET METAL WORKER, Excludes HVAC Duct Installation...........$ 15.81 1.40

TRUCK DRIVER.....................$ 13.38 1.48

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

52.225-11 Buy American-Construction Materials under Trade Agreements.

As prescribed in 25.1102(c), insert the following clause:

Buy American-Construction Materials under Trade Agreements (Oct 2019)

(a) Definitions. As used in this clause-

Caribbean Basin country construction material means a construction material that–

(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.

Commercially available off-the-shelf (COTS) item-

(1) Means any item of supply (including construction material) that is-

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C.40102(4), such as agricultural products and petroleum products.

Component means an article, material, or supply incorporated directly into a construction material.

Construction material means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means-

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Designated country means any of the following countries:

(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);

(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);

(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina

Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or

(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).

“Designated country construction material” means a construction material that is a WTO

GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.

Domestic construction material means-

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if-

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic;

or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

Free Trade Agreement country construction material means a construction material that-

(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.

Least developed country construction material means a construction material that-

(1) Is wholly the growth, product, or manufacture of a least developed country; or another country, has been substantially transformed in a least developed country into a new and

United States means the 50 States, the District of Columbia, and outlying areas.

WTO GPA country construction material means a construction material that-

(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or another country, has been substantially transformed in a WTO GPA country into a new and

(b) Construction materials.

(1) This clause implements 41 U.S.C.chapter 83, by providing a preference for domestic construction material. In accordance with 41 U.S.C.1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and Free Trade Agreements (FTAs) apply to this acquisition. Therefore, the Buy American restrictions are waived for designated country construction materials.

(2) The Contractor shall use only domestic or designated country construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.

(3) The requirement in paragraph (b)(2) of this clause does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

[Contracting Officer to list applicable excepted materials or indicate “none”]

(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the restrictions of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)

(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy

American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(4)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction MaterialDescription Unit of Measure Quantity Price (Dollars)*

Item1:

Foreign construction material

Domestic construction material

Item2:

Foreign construction material Domestic construction material

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]

[Include other applicable supporting information.]

[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]

MCB Camp Lejeune, North Carolina Project No. 18-0042

4/7/2021

(End of clause)

Alternate I (May 2014). As prescribed in 25.1102(c)(3), add the following definition of “Bahrainian, Mexican, or Omani construction material” to paragraph (a) of the basic clause, and substitute the following paragraphs (b)(1) and (b)(2) for paragraphs (b)(1) and (b)(2) of the basic clause:

“Bahrainian, Mexican, or Omani construction material” means a construction material that-

(1) Is wholly the growth, product, or manufacture of Bahrain, Mexico, or Oman; or another country, has been substantially transformed in Bahrain, Mexico, or Oman into a new and different construction material distinct from the materials from which it was transformed.

(b) Construction materials. (1) This clause implements 41 U.S.C. chapter 83, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and all the Free Trade Agreements except the Bahrain FTA, NAFTA, and the Oman FTA apply to the this acquisition. Therefore, the Buy American statute restrictions are waived for designated country construction materials other than Bahrainian, Mexican, or Omani construction materials.

(2) The Contractor shall use only domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.