ASBESTOS INSPECTION REPORT of:

Building # HP510

MCB CAMP LEJEUNE

Monday, April 6, 2020

Print Date

Monday, April 6, 2020 Page 1 of 4Print Date:

INSPECTION SUMMARY

BLDG #:

OCCUPANT:

YEAR BUILT:

BUILDING COMMENTS:

HP510

ASBESTOS MANAGER: 910-451-5837

Friable ACM(s) identified

Non-friable ACM(s) identified

Tested Non ACM or REMOVED Materials

DESCRIPTION LOCATION Date

ACM only presents a health hazard when asbestos fibers are airborne and inhaled.

Avoid disturbance which will release fibers. The presence of asbestos does not constitute a health hazard.

HEALTH ASPECTS:

Do not disturb or cause damage to ACM. Do not sand, grind or abrade materials or cause damage with any type of equipment.

CONDITIONS TO AVOID:

Report any damage, dust or debris that may come from ACM or suspect ACM, or any change in the condition of materials, or accidental disturbance to the Asbestos Program Manager.

REPORTS OF DAMAGE:

Corrective action initiated to minimize fiber release and protect personnel. RESPONSE ACTION:

ACM will be inspected periodically to evaluate any changes in condition.INSPECTION:

The Camp Lejeune Asbestos Program Manager maintains a copy of the survey for the building

RECORDKEEPING:

NOTICE: The following asbestos-containing materials have been identified in this structure. Refer to survey findings for additional information or contact the Asbestos Program Manager. Please note ACM that is intact and undisturbed is not considered a significant health hazard to building occupants.

DESCRIPTION LOCATION Date Quantity

DESCRIPTION LOCATION Date Quantity

No friable ACM records found in database

No non friable ACM records found in database

No non ACM records found in database

NOTIFICATION OF ACM IN BUILDING

Monday, April 6, 2020 Page 2 of 4Print Date:

building.

CAMP LEJEUNE Asbestos Program Manager: Phone: (910) 451-5837

Monday, April 6, 2020 Page 3 of 4Print Date:

SAMPLES COLLECTED

NO RECORDS AVAILABLE

Monday, April 6, 2020 Page 4 of 4Print Date:

CEMS Engineering

Comprehensive Interior/Exterior Asbestos Survey Report

HP510 - BEQ

Marine Corps Base Camp Lejeune, North Carolina

May 22, 2018

Comprehensive Interior/Exterior Asbestos Survey Report

HP510 – BEQ

Marine Corps Base Camp Lejeune, NC

Robert Elbertson NC AHERA Inspector relbertson@cceinc.biz

Prepared for:

Mr. Randy Alvar

Prepared by:

Crystal Coast Environmental, Inc.

10302 Bristow Center Dr.

Suite: 115

Bristow, VA 20136

Tel: 910.938.7998

Fax: 910.938.3441 www.cceinc.biz

Our Ref.:

18-5162

Date:

This document is intended only for the use of the individual or entity for which it was prepared and may contain information that is privileged, confidential and exempt from disclosure under applicable law.

Table of Contents

1. Introduction 1

2. Methodology 1

3. Analytical Methods 2

4. Findings 2

5. Conclusions and Recommendations 2

6. Additional Survey Limitations 4

APPENDICES

A Limitations and Service Constraints B Inspector Accreditations C Homogeneous Applications D Asbestos Sample Locations E Laboratory Report (NVLAP) – Asbestos Bulk Sample Results F Photograph Logs

Survey Report

Mr. Randy Alvar May 22, 2018

1. Introduction

As requested by Mr. Randy Alvar, Crystal Coast Environmental, Inc. (CCEI) conducted a Comprehensive Interior/Exterior Asbestos Survey (CIES) of the above-referenced building/project. The survey consisted of visually observing the interior and exterior, then collecting a representative number of samples for subsequent laboratory analyses as described below. The objective of the survey was to identify and quantify asbestos-containing building materials (ACBMs) for future planned renovations or demolition activity. The sampling shall be consistent with areas that have historically tested positive for ACBMs in previous BEQ surveys.

As directed by the client, destructive testing was performed on flooring material to identify materials which may be hidden or obstructed by layers of wood substrate.

Unless noted herein, no other destructive testing was conducted to expose other potentially hidden or obstructed material. Examples of other areas include, but are not limited to: interior wall cavities, pipe chases, spaces above fixed ceilings, grout/adhesive beneath ceramic tiles/marble tiles/granite, and adhesives behind wall mounted mirrors, etc.

The survey was conducted on May 4, 2018 by Mr. Robert Elbertson. A copy of inspector’s accreditation is provided in Appendix B.

2. Methodology

CCEI conducted the CIES in general accordance with ASTM E2356-09 Standard Practice for Comprehensive Building Asbestos Surveys. ASTM E2356-09 meets the applicable requirements of current Environmental Protection Agency (EPA) National Emission Standards for Hazardous Air Pollutants (NESHAP) Standard 40 CFR 61, Subpart M (Asbestos); EPA Asbestos Hazard Emergency Response Act (AHERA) Standard 40 CFR 763, Subpart E; and Occupational Safety and Health Administration (OSHA) asbestos survey and/or sampling regulations.

CCEI visually observed readily accessible areas for suspect ACBMs. Identified suspect materials were divided into "Homogeneous Applications" (HAs) - i.e., building materials which were determined by the inspector to be homogeneous based on their color, texture, and assumed date of installation.

Representative samples were then collected from selected HAs. The numbers of samples collected was based on CCEI’s in-house sampling protocol, which is based in part on the U.S. Environmental Protection Agency (U.S. EPA) Asbestos Hazard Emergency Response Act (AHERA) regulations. Each sample was assigned its own

Survey Report

Mr. Randy Alvar May 22, 2018 unique identification number, placed in 4 mil sealable plastic bags, and tightly sealed for subsequent shipment under a chain of custody protocol to EMSL located in Morrisville, North Carolina.

3. Analytical Methods

Material identification was performed by EMSL using Polarized Light Microscopy with Dispersion Staining (PLM/DS) method in accordance with the U.S. EPA Method 600/R-93/116. Asbestos content in each sample was evaluated based on a visual examination of each sample using a stereoscope.

EMSL is a member of the American Industrial Hygiene Association (AIHA) and accredited through the National Voluntary Laboratory Accreditation Program (NVLAP) administered by the National Institute of Standards and Technology (NIST).

The laboratory analytical report is provided in Appendix E.

4. Findings

A total of 13 HAs were identified throughout the Site, and a total of 27 suspect ACBM bulk samples were collected and submitted for laboratory analysis. A listing of HAs identified along with each HA material description, location, condition, asbestos content and estimated quantity are presented in Appendix C. Approximate sampling locations are shown in the Appendix D.

5. Conclusions and Recommendations

As presented in Appendix C and the laboratory data provided in Appendix E, the results of the asbestos survey did not identify ACBMs at the Site.

In accordance with current EPA National Emission Standards for Hazardous Pollutants (NESHAP) regulations, certain types of ACM must be removed prior to being disturbed by demolition or renovation activities. Current EPA NESHAP and Health Hazards Control Unit (HHC) of North Carolina Department of Health and Human Service (DHHS) regulations require that all Regulated ACMs (RACM) be removed prior to being disturbed. RACMs are defined as:

• Friable ACM.

• Non-Friable Category 1 ACM that has become friable.

• Non-Friable Category 1 ACM that has been or will be subjected to sanding, abrading, grinding, or cutting.

Survey Report

Mr. Randy Alvar May 22, 2018

• Non-Friable Category 2 ACM that has a high probability of becoming friable or crumbled, pulverized, or otherwise reduced to powder by the demolition or renovation activities.

In some cases, materials which may be ACBMs were identified as “Suspect ACM, Not Sampled” in the HAT. These include materials that could not safely be accessed during the survey, were labeled as PACM based on the inspector’s field determination. Until determined otherwise, suspect and not sampled materials have been assumed to be ACBMs and should be managed as asbestos-containing in accordance with the local, state, and federal regulations.

If other suspect materials that are not referenced in this report are identified during demolition and/or renovation activities, CCEI recommends that these materials be considered as ACBM until they are inspected by an appropriately licensed asbestos inspector and proven otherwise.

Prior to demolition activities and when it is safe to do so, CCEI recommends sampling the PACM identified in this survey. Should these materials prove to be non-ACMs this could result in significant cost savings.

Due to the inability to effectively separate some types of multi-layered ACBMs (i.e., floor tile/mastic, mastic/wood subflooring, gypsum board/joint compound, etc.) from non-ACMs these materials are considered “asbestos-contaminated” for the purposes of removal, and should be managed as ACBM.

ACBMs identified at the Site that may be disturbed during demolition activities, must be removed by a licensed asbestos abatement contractor utilizing industry standard work procedures in accordance with all federal, state and local regulations governing asbestos.

Asbestos waste must be disposed at an asbestos waste receiving facility that is duly permitted by the state and/or local municipality in which it resides. The asbestos waste should be disposed in a landfill with a NESHAP condition in the facility’s air permit that allows acceptance of RACM.

6. Additional Survey Limitations

CCEI’s asbestos survey is subject to the following limitations in addition to those presented in Appendix A:

Survey Report

Mr. Randy Alvar May 22, 2018

• Utilities/services, including electric were assumed to be active in the areas surveyed. Materials associated with electrical components and energized equipment, were not safely accessible and were not sampled.

• Subsurface investigations, including access to below grade structures, underground piping, conduits, building footings and extent of subsurface soil asbestos contamination if any was not accessible at the time of the survey.

Should you decide to remove/demolish below grade structures, an additional investigation may be warranted to determine if the below grade structures contain or are coated with ACMs.

Limitations and Service Constraints

The opinions, conclusions and recommendations presented in this report are limited to the information obtained during the performance of the specific scope of service identified in the report. To the extent that

Crystal Coast Environmental, Inc. (CCEI) relied upon any information prepared by other parties not under direct contract to CCEI, no representation as to the accuracy or completeness of such information is made. This report is an instrument of professional service and the services described in the report were performed in accordance with generally accepted standards and level of skill and care ordinarily exercised by members of the profession working under similar conditions including comparable budgetary and schedule constraints. No warranty, guarantee or certification express or implied, is intended or given with respect to CCIE’s services, opinions, conclusions or recommendations. This statement is in lieu of any other statement either expressed or implied.

CCEI’s observations, the results of testing and CCEI’s opinions, conclusions and recommendations apply solely to conditions existing at the specific times when and specific locations where CCEI’s investigative work was performed. Observation and testing activities such as those conducted by CCEI are inherently limited and do not represent a conclusive or complete characterization. Conditions in other parts of the project site, building or area may vary from conditions at the specific locations where observations were made and where testing was performed by CCEI. Additionally, other building material hazards which were not identified by CCEI, may also be present in the indoor air, un-accessed areas and in walls, ceilings, cavities and floors. Therefore, the extent of CCEI’s opinions, conclusions and recommendations are limited and 100% confidence in these opinions, conclusions and recommendations cannot reasonably be achieved. Nothing contained in this report shall relieve any other party of its responsibility to abide by contract documents and applicable laws, codes, regulations, or standards nor shall it be considered medical advice or consultation.

This report may document whether work conducted by CCEI or under CCEI’s observation was done so in accordance with applicable regulatory standards. In the absence of standards such as is often the case for microbial assessment and abatement, this report may not be construed as providing clearance, approval, or authorization for use or re-occupancy of a given structure. Actual site conditions and quantities should be field verified and unless expressly stated.

This report is expressly for the sole and exclusive use of the party for whom this report was originally prepared for and for the particular purpose outlined in the report. Only the party for whom this report was originally prepared and/or other specifically named parties have the right to make use of and rely upon this report. Reuse of this report or any portion thereof for other than its intended purpose, or if modified, or if used by third parties, shall be at the user’s sole risk.

Homogeneous Application Table BEQ HP510, Camp Lejeune, NC

Project No.: 18-5162

HA No. Material Type Primary Color Texture Description NESHAP Cat. Friable Rooms Location Condition Amt. Units Remarks

1 M - Ceiling Texture White Rough Spray-on Ceiling Texture Non-ACM, Sampled Yes Throughout Ceiling Good Non-ACM are not quantified 2 M - Ceiling Tile - 2' x 2' White Rough 2' x 2' Cellulose Ceiling Tile Non-ACM, Sampled Yes Hallways and Lounges Ceiling Good Non-ACM are not quantified

3 M - Gypsum Board (walls and ceilings) Gray Smooth Gypsum Board Non-ACM, Sampled No Dorm Rooms Wall Good Non-ACM are not quantified

4 M - Joint Compound (associated with wall/ceiling board/panels) White Rough Joint Compound Non-ACM, Sampled Yes Dorm Rooms Wall Good Non-ACM are not quantified

5 M - Cove Base Mastic Yellow Rough Mastic Associated with Brown Vinyl Cove Base Non-ACM, Sampled No Dorm Rooms Wall Good Non-ACM are not quantified

6 M - Cove Base Mastic Brown Rough Mastic Associated with Black Vinyl Cove Base Non-ACM, Sampled No Hallway and Lounges Wall Good Non-ACM are not quantified

7 M - Floor Tile - 12" x 12" Gray Smooth 1' x 1' Vinyl Floor Tile Non-ACM, Sampled No Dorm Rooms Floor Good Non-ACM are not quantified 8 M - Floor Tile - Mastic/Adhesive Black Rough Mastic Associated with HA-7 Non-ACM, Sampled No Dorm Rooms Floor Good Non-ACM are not quantified

M - Mastic/Skimcoat/Taping

Compounds on Duct Insulation Seams

Gray Rough HVAC Duct Mastic/Tape Non-ACM, Sampled No Mechanical Rooms Other Good Non-ACM are not quantified

10 M - Exterior - Expansion Joint Caulk/Sealant Brown Smooth Expansion Joint Caulk Non-ACM, Sampled No Exterior Floor Good Non-ACM are not quantified

11 M - Roof - Rubber Membrane Mastic/Sealant White Smooth Rubber Roofing Membrane Non-ACM, Sampled No Roof Roof Good Non-ACM are not quantified

12 M - Roof - Roof Penetration Mastic (Roof Vents/Pipes/etc.) Gray Smooth Vent Pipe Penetration Mastic Non-ACM, Sampled No Roof Roof Good Non-ACM are not quantified

13 M - Construction Mastics - Describe Not Visible Not Visible Mastic associated with shower pans Presumed ACM, Not No Dorm Rooms Floor Good 96 EA Quantities are an approximation

T = Thermal System Insulation (TSI) Material S - Surface Material M - Miscellaneous Material

Results of Sample Analyses BEQ HP510 Camp Lejeune, NC

Project No.: 18-5162

HA No. Material Type ID Location Content Type Sample Date Consultant Method Lab

1 M - Ceiling Texture 510-1-01 1st Floor Hallway ND 5/4/2018 CCEI PLM EMSL 1 M - Ceiling Texture 510-1-02 2nd Floor Lounge ND 5/4/2018 CCEI PLM EMSL 1 M - Ceiling Texture 510-1-03 3rd Floor Lounge ND 5/4/2018 CCEI PLM EMSL 2 M - Ceiling Tile - 2' x 2' 510-2-04 1st Floor Loung ND 5/4/2018 CCEI PLM EMSL 2 M - Ceiling Tile - 2' x 2' 510-2-05 3rd Floor Hallway ND 5/4/2018 CCEI PLM EMSL 3 M - Gypsum Board (walls and ceilings) 510-3-06 109 ND 5/4/2018 CCEI PLM EMSL 3 M - Gypsum Board (walls and ceilings) 510-3-07 224 ND 5/4/2018 CCEI PLM EMSL 4 M - Joint Compound (associated with wall/ceiling board/panels) 510-4-08 109 ND 5/4/2018 CCEI PLM EMSL 4 M - Joint Compound (associated with wall/ceiling board/panels) 510-4-09 224 ND 5/4/2018 CCEI PLM EMSL 5 M - Cove Base Mastic 510-5-10 1st Floor Hallway ND 5/4/2018 CCEI PLM EMSL 5 M - Cove Base Mastic 510-5-11 3rd Floor Hallway ND 5/4/2018 CCEI PLM EMSL 6 M - Cove Base Mastic 510-6-12 224 ND 5/4/2018 CCEI PLM EMSL 6 M - Cove Base Mastic 510-6-13 324 ND 5/4/2018 CCEI PLM EMSL 7 M - Floor Tile - 12" x 12" 510-7-14 109 ND 5/4/2018 CCEI PLM EMSL 7 M - Floor Tile - 12" x 12" 510-7-15 224 ND 5/4/2018 CCEI PLM EMSL 7 M - Floor Tile - 12" x 12" 510-7-16 324 ND 5/4/2018 CCEI PLM EMSL 8 M - Floor Tile - Mastic/Adhesive 510-8-17 109 ND 5/4/2018 CCEI PLM EMSL 8 M - Floor Tile - Mastic/Adhesive 510-8-18 224 ND 5/4/2018 CCEI PLM EMSL 8 M - Floor Tile - Mastic/Adhesive 510-8-19 321 ND 5/4/2018 CCEI PLM EMSL 9 M - Mastic/Skimcoat/Taping Compounds on Duct Insulation Seams 510-9-20 Mechanical Room 2 ND 5/4/2018 CCEI PLM EMSL 9 M - Mastic/Skimcoat/Taping Compounds on Duct Insulation Seams 510-9-21 Mechanical Room 4 ND 5/4/2018 CCEI PLM EMSL

10 M - Exterior - Expansion Joint Caulk/Sealant 510-10-22 Exterior ND 5/4/2018 CCEI PLM EMSL 10 M - Exterior - Expansion Joint Caulk/Sealant 510-10-23 Exterior ND 5/4/2018 CCEI PLM EMSL 11 M - Roof - Rubber Membrane Mastic/Sealant 510-11-24 Roof ND 5/4/2018 CCEI PLM EMSL 11 M - Roof - Rubber Membrane Mastic/Sealant 510-11-25 Roof ND 5/4/2018 CCEI PLM EMSL 12 M - Roof - Roof Penetration Mastic (Roof Vents/Pipes/etc.) 510-12-26 Roof ND 5/4/2018 CCEI PLM EMSL 12 M - Roof - Roof Penetration Mastic (Roof Vents/Pipes/etc.) 510-12-27 Roof ND 5/4/2018 CCEI PLM EMSL

T = Thermal System Insulation (TSI) Material S = Surfacing Material M - Miscellaneous Material

SHEET NO.

JOB NO.

ISSUE DATE

APPROVED

CHECKED

DESIGNED

DRAWN

SHEET TITLE

JOB TITLE

B

REVISIONS

C

A

17-0022

INTERIOR & EXTERIOR

REPAIRS TO BEQ HP510

AS101

05/15/18

Approver

Checker

Designer

Author

HAZARDOUS

MATERIALS

ABATEMENT FIRST

FLOOR PLAN

NO. DATE DESCRIPTION

SCALE: 1" = 30'-0"1

FIRST FLOOR PLAN

PLAN NORTH

Robert Callout 510-1-01(-)

Robert Callout 510-2-04(-)

Robert Callout 510-3-06(-) 510-4-08(-)

Robert Callout 510-5-10(-)

Robert Callout 510-7-14(-) 510-8-17(-)

Robert Callout 510-9-20(-)

Robert Callout 510-9-21(-)

Robert Callout 510-10-22(-)

Robert Callout 510-10-23(-)

ISSUE DATE

APPROVED

CHECKED

DESIGNED

DRAWN

SHEET TITLE

JOB TITLE

B

REVISIONS

C

A

17-0022

INTERIOR & EXTERIOR

REPAIRS TO BEQ HP510

AS102

05/15/18

Approver

Checker

Designer

Author

HAZARDOUS

MATERIALS

ABATEMENT SECOND

FLOOR PLAN

NO. DATE DESCRIPTION

SCALE: 1" = 30'-0"1

SECOND FLOOR PLAN

PLAN NORTH

Robert Callout 510-1-02(-)

Robert Callout 510-3-07(-) 510-4-09(-)

Robert Callout 510-6-12(-)

Robert Callout 510-7-15(-) 510-8-18(-)

ISSUE DATE

APPROVED

CHECKED

DESIGNED

DRAWN

SHEET TITLE

JOB TITLE

B

REVISIONS

C

A

17-0022

INTERIOR & EXTERIOR

REPAIRS TO BEQ HP510

AS103

05/15/18

Approver

Checker

Designer

Author

HAZARDOUS

MATERIALS

ABATEMENT THIRD

FLOOR PLAN

NO. DATE DESCRIPTION

SCALE: 1" = 30'-0"1

THIRD FLOOR PLAN

PLAN NORTH

Robert Callout 510-1-03(-)

Robert Callout 510-2-05(-)

Robert Callout 510-5-11(-)

Robert Callout 510-6-13(-)

Robert Callout 510-7-16(-) 510-8-19(-)

ISSUE DATE

APPROVED

CHECKED

DESIGNED

DRAWN

SHEET TITLE

JOB TITLE

B

REVISIONS

C

A

17-0022

INTERIOR & EXTERIOR

REPAIRS TO BEQ HP510

AS104

05/15/18

Approver

Checker

Designer

Author

HAZARDOUS

MATERIALS

ABATEMENT ROOF

PLAN

NO. DATE DESCRIPTION

SCALE: 1" = 30'-0"1

ROOF PLAN

PLAN NORTH

Robert Callout 510-11-24(-)

Robert Callout 510-11-25(-)

Robert Callout 510-12-26(-)

Robert

510-12-27(-)

EMSL Analytical, Inc.

2500 Gateway Centre Blvd., Suite 600 Morrisville, NC 27560

Tel/Fax: (919) 465-3900 / (919) 465-3950 http://www.EMSL.com / raleighlab@emsl.com

291803843EMSL Order:

Customer ID: BUFF52

Customer PO:

Project ID:

Attention: Phone:Robert Elbertson (910) 330-7410

Fax:Crystal Coast Environmental, Inc. (910) 938-3441

Received Date:10302 Bristow Center Drive 05/08/2018 10:15 AM

Analysis Date:#115 05/15/2018

Collected Date:Bristow, VA 20136 05/04/2018

Project: 18-5162 HP510 Samp Lejeune, NC

Test Report: Asbestos Analysis of Bulk Materials via EPA 600/R-93/116 Method using Polarized

Light Microscopy

Sample Description Appearance % Fibrous % Non-Fibrous

Non-Asbestos Asbestos

% Type

510-1-01

291803843-0001

None DetectedNon-fibrous (Other)100%White

Non-Fibrous

Homogeneous

Spray-On Ceiling

Texture

510-1-02

291803843-0002

None DetectedNon-fibrous (Other)100%White

Non-Fibrous

Homogeneous

Spray-On Ceiling

Texture

510-1-03

291803843-0003

None DetectedNon-fibrous (Other)100%White

Non-Fibrous

Homogeneous

Spray-On Ceiling

Texture

510-2-04

291803843-0004

None DetectedPerlite

Non-fibrous (Other)

15%

15%

Cellulose

Min. Wool

30%

40%

White/Beige

Fibrous

Homogeneous

2'x2' Ceiling Tile

510-2-05

291803843-0005

None DetectedPerlite

Non-fibrous (Other)

15%

15%

Cellulose

Min. Wool

30%

40%

Gray/White

Fibrous

Homogeneous

2'x2' Ceiling Tile

510-3-06

291803843-0006

None DetectedNon-fibrous (Other)80%Cellulose

Glass

15%

5%

Brown/Gray

Fibrous

Homogeneous

Gypsum Board

510-3-07

291803843-0007

None DetectedNon-fibrous (Other)77%Cellulose

Glass

20%

3%

Brown/Gray

Fibrous

Homogeneous

Gypsum Board

510-4-08

291803843-0008

None DetectedNon-fibrous (Other)98%Wollastonite2%White

Fibrous

Homogeneous

Joint Compound

510-4-09

291803843-0009

None DetectedNon-fibrous (Other)100%Wollastonite<1%White

Non-Fibrous

Homogeneous

Joint Compound

510-5-10

291803843-0010

None DetectedNon-fibrous (Other)98%Cellulose2%Brown

Fibrous

Homogeneous

Cove Base Mastic

(Brown)

510-5-11

291803843-0011

None DetectedNon-fibrous (Other)100%Cellulose<1%Brown

Non-Fibrous

Homogeneous

Cove Base Mastic

(Brown)

510-6-12

291803843-0012

None DetectedNon-fibrous (Other)98%Cellulose

Synthetic

2%

<1%

Yellow

Fibrous

Homogeneous

Cove Base Mastic

(Yellow)

510-6-13

291803843-0013

None DetectedNon-fibrous (Other)98%Cellulose2%Tan

Fibrous

Homogeneous

Cove Base Mastic

(Yellow)

510-7-14

291803843-0014

None DetectedNon-fibrous (Other)100%Beige

Non-Fibrous

Homogeneous

1'x1' Vinyl Floor Tile

510-7-15

291803843-0015

None DetectedNon-fibrous (Other)100%Beige

Non-Fibrous

Homogeneous

1'x1' Vinyl Floor Tile

510-7-16

291803843-0016

None DetectedNon-fibrous (Other)100%Tan

Non-Fibrous

Homogeneous

1'x1' Vinyl Floor Tile

Initial report from: 05/15/2018 10:14:32

Page 1 of 3ASB_PLM_0008_0001 - 1.78 Printed: 5/15/2018 10:14 AM

EMSL Analytical, Inc.

2500 Gateway Centre Blvd., Suite 600 Morrisville, NC 27560

Tel/Fax: (919) 465-3900 / (919) 465-3950 http://www.EMSL.com / raleighlab@emsl.com

291803843EMSL Order:

Customer ID: BUFF52

Customer PO:

Project ID:

Test Report: Asbestos Analysis of Bulk Materials via EPA 600/R-93/116 Method using Polarized

Light Microscopy

Sample Description Appearance % Fibrous % Non-Fibrous

Non-Asbestos Asbestos

% Type

510-8-17

291803843-0017

None DetectedNon-fibrous (Other)97%Cellulose3%Black

Fibrous

Homogeneous

Floor Tile Mastic

510-8-18

291803843-0018

None DetectedNon-fibrous (Other)97%Cellulose3%Black

Fibrous

Homogeneous

Floor Tile Mastic

510-8-19

291803843-0019

None DetectedNon-fibrous (Other)95%Cellulose5%Black

Fibrous

Homogeneous

Floor Tile Mastic

510-9-20-Mastic

291803843-0020

None DetectedNon-fibrous (Other)97%Wollastonite3%White

Fibrous

Homogeneous

HVAC Duct

Mastic/Tape

510-9-20-Tape

291803843-0020A

None DetectedNon-fibrous (Other)45%Cellulose

Glass

45%

10%

Brown/Silver

Fibrous

Homogeneous

HVAC Duct

Mastic/Tape

510-9-21-Mastic

291803843-0021

None DetectedNon-fibrous (Other)95%Cellulose

Wollastonite

3%

2%

White

Fibrous

Homogeneous

HVAC Duct

Mastic/Tape

510-9-21-Tape

291803843-0021A

None DetectedNon-fibrous (Other)35%Cellulose

Glass

45%

20%

Brown/Silver

Fibrous

Homogeneous

HVAC Duct

Mastic/Tape

510-10-22

291803843-0022

None DetectedNon-fibrous (Other)98%Cellulose2%Gray

Fibrous

Homogeneous

Expansion Joint Caulk

Sample bag does not match COC.

510-10-23

291803843-0023

None DetectedNon-fibrous (Other)100%Gray

Non-Fibrous

Homogeneous

Expansion Joint Caulk

Sample bag does not match COC.

510-11-24-Membrane

291803843-0024

None DetectedNon-fibrous (Other)90%Synthetic10%Gray/White/Blue

Fibrous

Homogeneous

Rubber Roofing

Membrane

510-11-24-Mastic

291803843-0024A

None DetectedNon-fibrous (Other)98%Cellulose2%Yellow

Fibrous

Homogeneous

Rubber Roofing

Membrane

510-11-25-Membrane

291803843-0025

None DetectedNon-fibrous (Other)85%Synthetic15%White/Blue

Fibrous

Homogeneous

Rubber Roofing

Membrane

510-11-25-Mastic

291803843-0025A

None DetectedNon-fibrous (Other)98%Cellulose2%Yellow

Fibrous

Homogeneous

Rubber Roofing

Membrane

510-12-26

291803843-0026

None DetectedNon-fibrous (Other)100%White

Non-Fibrous

Homogeneous

Vent Pipe Penetration

510-12-27

291803843-0027

None DetectedNon-fibrous (Other)100%White

Non-Fibrous

Homogeneous

Vent Pipe Penetration

Initial report from: 05/15/2018 10:14:32

Page 2 of 3ASB_PLM_0008_0001 - 1.78 Printed: 5/15/2018 10:14 AM

18-5162 Page 1 of 3

View of the Front of the Building HA-1: Spray-on Ceiling Texture

HA-2: 2’x 2’ Cellulose Ceiling Tile HA-3: Gypsum Board

HA-4: Joint Compound HA-5: Cove Base Mastic

18-5162 Page 2 of 3

HA-6: Cove Base Mastic HA-7: 1’ x 1’ Vinyl Floor Tile

HA-8: Mastic Associated with HA-7 HA-9: HVAC Duct Insulation Mastic

HA-10: Exterior Expansion Joint Caulk HA-11: Rubber Roofing Membrane/Mastic

18-5162 Page 3 of 3

No Photo Available

HA-12: Penetration Mastic HA-13: Mastic Associated with Shower Pans

Client:

Project Manager CEMS Engineering 320-C Midland Parkway Summerville, SC 29485

Submitted Electronically: ralvar@CEMS-ae.com

Project:

Lead Base Paint Inspection

BEQ HP510

Camp Lejeune, North Carolina

Dear Mr. Alvar:

Crystal Coast Environmental, Inc. (CCEI) was retained to conduct a lead base paint (LBP) inspection at the project identified above. The inspection consisted of visible and accessible interior and exterior surfaces coated with paint.

Background information on the Site and a summary of the inspection are provided below. CCEI’s services are subject to the Terms and Conditions to the Limitations and Service Constraints in Attachment A. The results of the inspection are presented in the attachments to this report.

LEAD SURVEY

CCEI conducted a LBP inspection to identify building components that may be impacted during scheduled renovations and may have lead-containing surface coatings.

The LBP inspection was performed on May 4, 2018, by Mr. Robert Elbertson of CCEI. The inspection was conducted by visually assessing areas of concern that may have surface coatings that are suspected to contain lead. Suspected materials coated with LBP were analyzed for total lead content (reported in total percent by weight) by Flame Atomic Adsorption Spectrometry (AAS) in accordance with U.S.

EPA Method 7420, SW 846-3050B/7000B. Strict Quality Control/Quality Assurance provisions were adhered to for analysis of all lead samples. from a wall, door frame, window sill, and baseboard. The results of the LBP inspection are presented in the attachments to this report as follows.

Crystal Coast Environmental, Inc.

10302 Bristow Center Dr.

Suite 115

Bristow, VA 20136

Tel: 910.938.7998

Fax: 910.938.3441 www.cceinc.biz

ENVIRONMENTAL

Date:

May 22, 2018

Contact:

Robert Elbertson

Phone:

910.330.7410

Email:

relbertson@cceinc.biz

Our ref:

18-5162

• Attachment A – CCEI Limitations and Service Constraints

• Attachment B – Laboratory Results

• Attachment C – Sampling Locations

• Attachment D – Photographic Log

FINDINGS

Based on the results of the investigation, the material identified does not contain

LBP.

If analysis was conducted by a laboratory: 0.5% by weight or 5,000 parts per million (ppm).

The Occupational Safety and Health Administration (OSHA) Lead in Construction standard does not define lead paint based on content. Any detectable lead in paint makes it lead paint for purposes of complying with OSHA regulations to determine worker exposure.

CONCLUSIONS

Based upon the results of the inspection, the samples are reported as not containing detectable quantities of lead. The scope of this lead screening survey was limited to only assessing building components located areas or rooms identified by the client. If areas outside the scope of assessment for this survey may be disturbed, additional assessment may be required

The remaining samples are reported as not containing detectable quantities of lead.

The scope of this lead screening survey was limited to only assessing building components located areas or rooms identified by the client. If areas outside the scope of assessment for this survey may be disturbed, additional assessment may be required.

CLOSING

Should you have any questions regarding this report, or if CCEI can be of further assistance, please feel free to contact CCEI at (910) 938-7998.

Sincerely, Crystal Coast Environmental, Inc.

Robert Elbertson Operations Manager

Attachments A. CCEI Limitations and Service Constraints B. Laboratory Results C. Sampling Locations D. Photographic Log

Limitations and Service Constraints

The opinions, conclusions and recommendations presented in this report are limited to the information obtained during the performance of the specific scope of service identified in the report. To the extent that Crystal Coast Environmental, Inc. (CCEI) relied upon any information prepared by other parties not under direct contract to CCEI, no representation as to the accuracy or completeness of such information is made. This report is an instrument of professional service and the services described in the report were performed in accordance with generally accepted standards and level of skill and care ordinarily exercised by members of the profession working under similar conditions including comparable budgetary and schedule constraints. No warranty, guarantee or certification express or implied, is intended or given with respect to CCIE’s services, opinions, conclusions or recommendations. This statement is in lieu of any other statement either expressed or implied.

CCEI’s observations, the results of testing and CCEI’s opinions, conclusions and recommendations apply solely to conditions existing at the specific times when and specific locations where CCEI’s investigative work was performed. Observation and testing activities such as those conducted by CCEI are inherently limited and do not represent a conclusive or complete characterization. Conditions in other parts of the project site, building or area may vary from conditions at the specific locations where observations were made and where testing was performed by CCEI. Additionally, other building material hazards which were not identified by CCEI, may also be present in the indoor air, un-accessed areas and in walls, ceilings, cavities and floors. Therefore, the extent of CCEI’s opinions, conclusions and recommendations are limited and 100% confidence in these opinions, conclusions and recommendations cannot reasonably be achieved. Nothing contained in this report shall relieve any other party of its responsibility to abide by contract documents and applicable laws, codes, regulations, or standards nor shall it be considered medical advice or consultation.

This report may document whether work conducted by CCEI or under CCEI’s observation was done so in accordance with applicable regulatory standards. In the absence of standards such as is often the case for microbial assessment and abatement, this report may not be construed as providing clearance, approval, or authorization for use or re-occupancy of a given structure. Actual site conditions and quantities should be field verified and unless expressly stated.

This report is expressly for the sole and exclusive use of the party for whom this report was originally prepared for and for the particular purpose outlined in the report. Only the party for whom this report was originally prepared and/or other specifically named parties have the right to make use of and rely upon this report. Reuse of this report or any portion thereof for other than its intended purpose, or if modified, or if used by third parties, shall be at the user’s sole risk.

Weight

Attn:

Address: 10302 Bristow Center Dr Order #: 259774

#115

Project: HP510 CLNC

Bristow, VA 20136

Crystal Coast Environmental (3425)Customer:

18-5162Number: PO Number:

Received 05/09/18

Matrix Paint

% / Wt. RL*Total µg

Cust. Sample ID

Parameter

Sample ID Location

Schneider Laboratories Global, Inc 2512 W. Cary Street • Richmond, Virginia • 23220-5117 804-353-6778 • 800-785-LABS (5227) • Fax 804-359-1475

05/10/18

Location: Camp Lejeune

Analyzed

05/10/18Reported

Sample Date

Conc.Method

Analysis Report

Door/Door Frame 05/04/18510-Pb-01259774-001 341 mg

<0.00294 % 29.3 mg/kg<10.0 µgEPA 7000B / 3050B

Duplicate sample failed due to the inhomongeneity of the sample. Sample results are not affected by the failure and are accurate.

<29.4 mg/kgLead

Interior Walls 05/04/18510-Pb-02259774-002 301 mg

0.00663 % 33.2 mg/kg19.9 µgEPA 7000B / 3050B 66.3 mg/kgLead

Analyst: RW

259774-05/10/18 06:31 PM

Analyst

Reviewed By: Eric Broaddus

Federal Lead Paint Statute

Location UnitClearance

Lead in paint by weight < 0.50 %

Lead in paint as PPM < 5000 mg/kg

Minimum reporting limit: 10.0 µg. Concentration and *Reporting Limit (RL) based on weights provided by client. All internal QC parameters were met. Unusual sample conditions, if any, are described. Values are reported to three significant figures. PPM = mg/kg | PPB = µg/kg. The test results reported relate only to the samples submitted. AIHA-LAP, LLC accredited for Lead.

SCHNEIDER LABORATORIES GLOBAL, INC.

2512 West Cary Street, Richmond, V,irginia 23220-5117 804-353-6778 • 800-785-LABS (5227) • Fax 804-359-1475 www.slabinc.com e-mail: info@slabinc.com

LabWO# Phone

259;r74 s 2

1111111 1111~1~!~~!1!~111 ~111111 fghre1izi 5/B/20181:~ J:OO FM Federal ElmE3SS 81208l13423l57

10302 Bristow Center Drive. Suite #115

02 hours*

Osameday*

0 1 business day*

0 2 business day* lff3 business days*

0 5 business days*

0 Full TCLP (10d)

0Weekend*

* not available for all tests

All samples on form should be of SAME matrix type. Use additional forms as needed.

OAir

0Aqueous

O Solid

O Waste

0 Bulk 0 Wastewater

O Hi-Val Filter (PM10) O Water,Drinking

O Hi-Val Filter (TSP) Compliance

Ooil Wipe

Wipe, Composite

Special Instructions [include requests for special reporting or data packages]

0 ~CM (NIOSH 7400) 0 PLM (EPA 600IR-931116)

0 TEM (AHERA) 0 PLM (EPA Point Count)

O TEM (EPA Level II) O PLM (Qualitative only)

11'0:::!.:;;'====:;::=~=-----lO NYELAP 198.11.41.6

0 RCRA Metals

0------f-'----"-'=====-====-~--10 CAELAP (EPA Interim) Metals-Extract .

0 Total Dust (NIOSH 0500)

0 Resp. Dust (NIOSH 0600)

0 Silica - FTIR (NIOSH 7602)

0 TEM (Chatfield) 0 TCLP I Lead f.!::0~=======---10 TCLP I RCRA Metals

FOR ASBESTOS AIR: 0 TCLP I Full (wl organics)

0 Silica- XRD (NIOSH 7500) TYPE OF RESPIRATOR Others

0 FX

0HD

WB:

ISSUE DATE

APPROVED

CHECKED

DESIGNED

DRAWN

SHEET TITLE

JOB TITLE

B

REVISIONS

C

A

17-0022

INTERIOR & EXTERIOR

REPAIRS TO BEQ HP510

AS101

05/15/18

Approver

Checker

Designer

Author

HAZARDOUS

MATERIALS

ABATEMENT FIRST

FLOOR PLAN

NO. DATE DESCRIPTION

SCALE: 1" = 30'-0"1

FIRST FLOOR PLAN

PLAN NORTH

ISSUE DATE

APPROVED

CHECKED

DESIGNED

DRAWN

SHEET TITLE

JOB TITLE

B

REVISIONS

C

A

17-0022

INTERIOR & EXTERIOR

REPAIRS TO BEQ HP510

AS102

05/15/18

Approver

Checker

Designer

Author

HAZARDOUS

MATERIALS

ABATEMENT SECOND

FLOOR PLAN

NO. DATE DESCRIPTION

SCALE: 1" = 30'-0"1

SECOND FLOOR PLAN

PLAN NORTH

Robert

510-Pb-01

ISSUE DATE

APPROVED

CHECKED

DESIGNED

DRAWN

SHEET TITLE

JOB TITLE

B

REVISIONS

C

A

17-0022

INTERIOR & EXTERIOR

REPAIRS TO BEQ HP510

AS103

05/15/18

Approver

Checker

Designer

Author

HAZARDOUS

MATERIALS

ABATEMENT THIRD

FLOOR PLAN

NO. DATE DESCRIPTION

SCALE: 1" = 30'-0"1

THIRD FLOOR PLAN

PLAN NORTH

Robert

510-Pb-02

ISSUE DATE

APPROVED

CHECKED

DESIGNED

DRAWN

SHEET TITLE

JOB TITLE

B

REVISIONS

C

A

17-0022

INTERIOR & EXTERIOR

REPAIRS TO BEQ HP510

AS104

05/15/18

Approver

Checker

Designer

Author

HAZARDOUS

MATERIALS

ABATEMENT ROOF

PLAN

NO. DATE DESCRIPTION

SCALE: 1" = 30'-0"1

ROOF PLAN

PLAN NORTH

18-5162 Page 1 of 1

View of the Front of the Building Pb-01: Door/Door Frame

Pb-02: Interior Walls

N4008518B0042 HAZRPT 1
N4008518B0042Comprehensive Interior-Exterior Asbestos Survey
AS101 - HAZARDOUS MATERIALS ABATEMENT FIRST FLOOR PLAN
AS102 - HAZARDOUS MATERIALS ABATEMENT SECOND FLOOR PLAN
AS103 - HAZARDOUS MATERIALS ABATEMENT THIRD FLOOR PLAN
AS104 - HAZARDOUS MATERIALS ABATEMENT ROOF PLAN
Lead Base Paint Inspection Report
AS101 - HAZARDOUS MATERIALS ABATEMENT FIRST FLOOR PLAN
AS102 - HAZARDOUS MATERIALS ABATEMENT SECOND FLOOR PLAN
AS103 - HAZARDOUS MATERIALS ABATEMENT THIRD FLOOR PLAN
AS104 - HAZARDOUS MATERIALS ABATEMENT ROOF PLAN