THIS PAGE INTENTIONALLY LEFT BLANK
Repair BEQ HP510 18-0042
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 12 00 CUTTING AND PATCHING
01 14 00 WORK RESTRICTIONS
01 20 00 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT
MANAGEMENT SYSTEM
01 31 50 TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY
01 32 16 CONSTRUCTION PROGRESS DOCUMENTATION
01 33 00 SUBMITTAL PROCEDURES
01 35 29 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 10
01 50 00 TEMPORARY FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 60 00 REQUIREMENTS FOR PESTICIDE AND HERBICIDE COORDINATION
01 78 00 CLOSEOUT PROCEDURES
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 30.00 22 GIS DATA DELIVERABLES
01 91 13 GENERAL COMMISSIONING REQUIREMENTS
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 DEMOLITION
02 82 16 02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs
AND MERCURY
DI VI SI ON 03 - CONCRETE
03 01 30.71 CONCRETE REHABILITATION
03 30 50 CAST-IN-PLACE CONCRETE
DI VI SI ON 04 - MASONRY
04 20 00 UNIT MASONRY
DI VI SI ON 05 - METALS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 33 METAL LADDERS
05 52 00 STEEL RAILINGS
DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES
06 20 00 FINISH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 11 13 BITUMINOUS DAMPPROOFING
07 21 13 BOARD AND BLOCK INSULATION
PROJECT TABLE OF CONTENTS Page 1
07 21 16 MINERAL FIBER BLANKET INSULATION
07 21 23 LOOSE FILL THERMAL INSULATION
07 61 00 SHEET METAL AND CLADDING
07 61 15.00 20 ALUMINUM STANDING SEAM ROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 11 13 STEEL DOORS AND FRAMES
08 31 00 ACCESS DOORS AND PANELS
08 33 23 OVERHEAD COILING DOORS
08 58 01 BLAST MITIGATION OPERABLE ALUMINUM WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DI VI SI ON 09 - FI NI SHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 67 23.13 STANDARD RESINOUS FLOORING
09 90 00 PAINTS AND COATINGS
DI VI SI ON 10 - SPECI ALTI ES
10 14 00.20 INTERIOR SIGNAGE
10 28 13 TOILET ACCESSORIES
10 52 20 FIRE EXTINGUISHERS AND CABINETS
DI VI SI ON 11 - EQUI PMENT
11 24 24 HORIZONTAL LIFELINE ROOFTOP FALL PROTECTION SAFETY SYSTEMS
DI VI SI ON 12 - FURNI SHI NGS
12 21 00 WINDOW BLINDS
DI VI SI ON 21 - FI RE SUPPRESSI ON
21 13 13.00 20 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DI VI SI ON 22 - PLUMBI NG
22 00 00 PLUMBING, GENERAL PURPOSE
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 INSULATION OF MECHANICAL SYSTEMS
23 09 23.13 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC
23 52 43.00 20 LOW PRESSURE WATER HEATING BOILERS (UNDER 800,000 BTU/HR
OUTPUT)
23 73 33 HEATING, VENTILATING, AND COOLING SYSTEM
PROJECT TABLE OF CONTENTS Page 2
DI VI SI ON 26 - ELECTRI CAL
26 00 00 BASIC ELECTRICAL MATERIALS AND METHODS
26 06 00 GROUNDING AND BONDING
26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
DI VI SI ON 27 - COMMUNI CATI ONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 54 00.00 20 COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DI VI SI ON 31 - EARTHWORK
31 00 00 EARTHWORK
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
32 17 23 PAVEMENT MARKINGS
32 92 19 SEEDING
DI VI SI ON 33 - UTI LI TI ES
33 11 00 WATER DISTRIBUTION
33 30 00 SANITARY SEWERS
33 40 00 STORM DRAINAGE UTILITIES
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 3
PROJECT TABLE OF CONTENTS Page 4
INDEX OF DRAWINGS
REPAIRS BEQ HP510
# OF TOTAL NAVFAC NO. SHEET NO. SHEET TITLE
GENERAL
1 60023959 G-001 COVER SHEET
2 60023960 LS101 BUILDING CODE ANALYSIS
3 60023961 LS102 LIFE SAFETY PLAN
4 60023962 H-101 ABATEMENT PLANS
5 60023963 H-102 ABATEMENT ROOF PLAN
CIVIL
6 60023964 C-001 LEGEND AND GENERAL NOTES
7 60023965 VF101 EXISTING TOPOGRAPHIC SURVEY
8 60023966 CD101 DEMOLITION / EROSION CONTROL PLAN
9 60023967 CS101 SITE PLAN
10 60023968 CP101 PLANTING PLAN
11 60023969 C-501 EROSION CONTROL DETAILS
12 60023970 C-502 DETAILS
13 60023971 C-503 DETAILS
STRUCTURAL
14 60023972 S-001 GENERAL NOTES AND DESIGN LOADS
15 60023973 SD101 DEMOLITION PLANS
16 60023974 SD401 ENLARGED DEMOLITION PLAN
17 60023975 S-101 CATWALK FRAMING PLANS
18 60023976 S-102 ROOF FRAMING PLANS
19 60023977 S-103 FLOOR PLANS
20 60023978 S-104 MECHANICAL YARD PLANS
21 60023979 S-105 DUMPSTER ENCLOSURE PLAN
22 60023980 S-301 FRAMING SECTIONS AND DETAILS
23 60023981 S-302 CMU SECTIONS AND DETAILS
24 60023982 S-303 MECHANICAL OPENING SECTIONS AND DETAILS
25 60023983 S-401 ENLARGED PLANS
26 60023984 S-501 ROOF FRAMING DETAILS
27 60023985 S-502 SECTIONS AND DETAILS
28 60023986 S-503 SECTIONS AND DETAILS
ARCHITECTURAL
29 60023987 A-001 GENERAL NOTES AND LEGENDS
30 60023988 AD101 DEMOLITION FLOOR PLANS
31 60023989 AD102 DEMOLITION REFLECTED CEILING PLANS
32 60023990 AD103 DEMOLITION ROOF PLAN
33 60023991 AD201 DEMOLITION ELEVATIONS
34 60023992 AD401 DEMOLITION ENLARGED CORE FLOOR PLAN
35 60023993 AD402 DEMOLITION ENLARGED CORE REFLECTED CEILING PLANS
36 60023994 AD403 DEMOLITION ENLARGED SLEEPING ROOM PLAN, RCP, AND ELEVATIONS
37 60023995 AD501 DEMOLITION DETAILS
38 60023996 AD901 DEMOLITION PHOTOS
39 60023997 A-101 FLOOR PLANS
40 60023998 A-102 REFLECTED CEILING PLANS
41 60023999 A-103 ROOF PLAN
42 60024000 A-104 MECHANICAL YARD FLOOR, REFLECTED CEILING, AND ROOF PLAN
43 60024001 A-201 BUILDING ELEVATIONS
44 60024002 A-202 ENLARGED BUILDING ELEVATIONS
45 60024003 A-203 MECHANICAL YARD EXTERIOR ELEVATIONS, SECTIONS, AND DETAILS
46 60024004 A-301 BUILDING SECTIONS
47 60024005 A-302 WALL SECTIONS
48 60024006 A-401 ENLARGED CORE FLOOR PLANS
49 60024007 A-402 ENLARGED CORE REFLECTED CEILING PLANS
50 60024008 A-403 ENLARGED SLEEPING ROOM FLOOR PLAN AND REFLECTED CEILING PLANS
51 60024009 A-404 ENLARGED SLEEPING ROOM ELEVATIONS AND DETAILS
52 60024010 A-405 ENLARGED TOILET ROOM PLANS AND ELEVATIONS
53 60024011 A-501 DETAILS
54 60024012 A-502 ROOF DETAILS
55 60024013 A-503 RAILING DETAILS
56 60024014 A-504 CASEWORK DETAILS
57 60024015 A-601 FINISH SCHEDULE AND DETAILS
58 60024016 A-602 DOOR SCHEDULE AND DETAILS
59 60024017 A-603 DOOR DETAILS
60 60024018 A-604 DOOR DETAILS
61 60024019 A-605 WINDOW SCHEDULE AND DETAILS
62 60024020 A-606 SIGNAGE PLANS
63 60024021 A-607 SIGNAGE SCHEDULE
64 60024022 A-608 SIGNAGE TYPES
FIRE PROTECTION
65 60024023 FA001 FIRE ALARM GENERAL NOTES, LEGENDS, AND DIAGRAMS
66 60024024 FA002 FIRE ALARM/MASS NOTIFICATION LEGEND AND RISER DIAGRAM
67 60024025 FD101 FIRE ALARM DEMOLITION PLANS
68 60024026 FA101 FIRE ALARM/MASS NOTIFICATION PLANS
69 60024027 FA401 ENLARGED FIRE ALARM/MNS PLANS
70 60024028 FX001 FIRE PROTECTION LEGEND, DETAILS, AND RISER DIAGRAM
71 60024029 FX101 FIRE PROTECTION PLANS
PLUMBING
72 60024030 P-001 LEGEND, DETAILS, AND SCHEDULES
73 60024031 PD101 DEMOLITION PLANS
74 60024032 PD401 ENLARGED DEMOLITION PLANS
75 60024033 PD402 ENLARGED DEMOLITION PLANS
76 60024034 PD403 ENLARGED DEMOLITION PLANS
77 60024035 P-101 SANITARY PIPING PLANS
78 60024036 P-102 DOMESTIC PIPING PLANS
79 60024037 P-103 ATTIC PIPING PLAN
80 60024038 P-104 MECHANICAL BUILDING PLUMBING PLANS
81 60024039 P-401 ENLARGED SANITARY PIPING PLANS
82 60024040 P-402 ENLARGED DOMESTIC PIPING PLANS
83 60024041 P-403 ENLARGED PIPING PLANS
84 60024042 P-404 ENLARGED PIPING PLANS
85 60024043 P-501 DETAILS
86 60024044 P-502 DETAILS
87 60024045 P-601 MECHANICAL BUILDING SCHEDULES
88 60024046 P-701 ISOMETRIC VIEWS
MECHANICAL
89 60024047 M-001 GENERAL NOTES AND LEGENDS
90 60024048 MS101 SITE PIPING DEMOLITION PLAN
91 60024049 MS102 SITE PIPING PLAN
92 60024050 MD101 DEMOLITION PLANS
93 60024051 MD102 ROOF DEMOLITION PLAN
94 60024052 MD401 ENLARGED DEMOLITION PLANS
95 60024053 MD402 ENLARGED DEMOLITION PLAN
96 60024054 MD403 ENLARGED DEMOLITION PLANS
97 60024055 MH101 FLOOR PLANS
98 60024056 MH102 ATTIC PLAN
99 60024057 MH401 ENLARGED PLANS
100 60024058 MH402 ENLARGED PLANS AND SECTIONS
101 60024059 MH403 ENLARGED PLANS
102 60024060 MP101 FLOOR PLANS
103 60024061 MP401 ENLARGED PLANS
104 60024062 M-101 MECHANICAL BUILDING PLAN AND SECTIONS
105 60024063 M-501 DETAILS
106 60024064 M-502 DETAILS
107 60024065 M-503 DETAILS
108 60024066 M-504 DETAILS AND SECTIONS
109 60024067 M-601 SCHEDULES
110 60024068 M-602 MECHANICAL BUILDING SCHEDULES
111 60024069 MI001 CONTROLS LEGEND
112 60024070 MI002 CONTROLS AND OPERATION
113 60024071 MI101 CENTER ROOM AHU CONTROLS AND OPERATION
114 60024072 MI102 DOAS CONTROLS AND OPERATION
115 60024073 MI103 EF CONTROLS AND OPERATION
116 60024074 MI104 PTAC CONTROLS AND OPERATION
117 60024075 MI105 CHW CONTROLS AND OPERATION
118 60024076 MI106 HHW CONTROLS
119 60024077 MI107 HHW SEQUENCE OF OPERATION
120 60024077A MI108 DHW CONTROLS AND OPERATION
ELECTRICAL
121 60024078 E-001 GENERAL NOTES AND LEGEND
122 60024079 ES101 SITE DEMOLITION PLAN
123 60024080 ES102 SITE PLAN
124 60024081 ED101 DEMOLITION PLANS
125 60024082 ED102 ROOF DEMOLITION PLAN
126 60024083 ED401 ENLARGED DEMOLITION PLANS
127 60024084 ED402 ENLARGED DEMOLITION PLANS
128 60024085 E-101 FLOOR PLANS
129 60024086 E-102 ATTIC PLAN
130 60024087 E-103 MECHANICAL BUILDING 510A PLANS
131 60024088 E-401 ENLARGED PLANS
132 60024089 E-402 ENLARGED PLANS
133 60024090 E-403 ENLARGED PLANS
134 60024091 E-501 LIGHTING DETAILS AND SCHEDULE
135 60024092 E-502 DETAILS
136 60024093 E-503 DETAILS
137 60024094 E-601 PANEL SCHEDULES
138 60024095 E-602 PANEL SCHEDULES
139 60024096 E-603 PANEL SCHEDULES
140 60024097 E-604 PANEL SCHEDULES
141 60024098 E-605 ELECTRICAL RISER DIAGRAM
142 60024099 E-606 MECHANICAL BUILDING ELECTRICAL RISER DIAGRAM
143 60024100 E-701 LIGHTNING PROTECTION PLAN AND DETAILS
TOTAL: 143
SECTION 01 11 00
SUMMARY OF WORK
09/08
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work includes a complete replacement of the electrical system.
Construction of a new sloped standing seam metal roof with metal-truss roof system. Upgrades conforming to Minimum Antiterrorism Standards for Buildings. Renovation and reconfiguration of the first lounge into a laundry room. Construction of a new mechanical building, new chiller enclosure, and incidental related work.
1.1.2 Location
The work shall be located at the Marine Corps Base, Camp Lejeune, North Carolina, BB255 approximately as shown. The exact location will be indicated by the Contracting Officer.
1.2 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.3 LOCATION OF UNDERGROUND FACILITIES
The Contractor will be responsible for obtaining the services of a professional utility locator to scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.3.1 Notification Prior to Excavation
Notify the Contracting Officer 48 hours prior to starting excavation work in order to permit making arrangements with public works personnel to scan the area for unmarked utilities. Obtain station digging permits prior to
SECTION 01 11 00 Page 1 starting excavation work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 12 00
CUTTING AND PATCHING
01/07
PART 1 GENERAL
1.1 CUTTING
Shall be done by sawing along straight lines. The amount cut out shall be the minimum necessary to accommodate the new work. No flame cutting will be permitted without written permission of the Officer in Charge of Construction.
1.2 HOLES
Shall be rotary drilled. The size shall be the minimum necessary to accommodate the new work.
1.3 PATCHING
Shall be done with materials which match the existing in color, quality and surface texture when finished.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 12 00 Page 1
SECTION 01 12 00 Page 2
SECTION 01 14 00
WORK RESTRICTIONS
01/07
PART 1 GENERAL
1.1 CONTRACTOR ACCESS AND USE OF PREMISES
1.1.1 Station Regulations
Ensure that Contractor personnel employed on the Station become familiar with and obey Station regulations. Keep within the limits of the work and avenues of ingress and egress as directed. Do not enter restricted areas unless required to do so and until cleared for such entry. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.
1.1.2 Working Hours
Regular working hours shall consist of an eight and one-half hour period established by the Contracting Officer, Monday through Friday, excluding Government holidays.
1.1.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Provide written request at least 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.
1.1.4 Occupied and Existing Buildings
The Contractor shall be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
The existing buildings and their contents shall be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
The Government will remove and relocate other Government property in the areas of the buildings scheduled to receive work.
1.1.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone
SECTION 01 14 00 Page 1 service, electric service, air conditioning, heating, fire alarm, compressed air, and CATV shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
This time limit includes time for deactivation and reactivation.
d. Operation of Station Utilities: The Contractor shall not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor shall notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.2 SECURITY REQUIREMENTS
Contract Clause "FAR 52.204-2, Security Requirements and Alternate II," "FAC 5252.236-9301, Special Working Conditions and Entry to Work Area".
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 14 00 Page 2
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
04/12
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP-1110-1-8 (2009) Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Submit the following in accordance with Section 01 33 00,"Submittal Procedures."
SD-01 Preconstruction Submittals
Schedule of prices
1.3 SCHEDULE OF PRICES
1.3.1 Data Required
Within 15 calendar days of notice of award, prepare and deliver to Contracting Officer a schedule of prices (construction contract) on the forms furnished by the Government. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices therefore. Schedule of prices shall be separated by individual building numbers with subtotals for each building.
1.3.2 Schedule Instructions
Payments will not be made until the schedule of prices has been submitted to and approved by the Contracting Officer. Identify the cost for site work, and include incidental work to the 5 foot line. Identify costs for the building(s), and include work out to the 5 foot line. Workout to the 5 foot line shall include construction encompassed within a theoretical line 5 feet from the face of exterior walls and shall include attendant construction, such as cooling towers, placed beyond the 5 foot line.
1.3.3 Schedule Requirements for HVAC TAB
The field work Section 23 05 93, "TESTING, ADJUSTING, AND BALANCING FOR HVAC" shall be broken down in the Schedule of Prices and in the Construction Progress Documentation by separate line items which reflect measurable deliverables. Specific payment percentages for each line item shall be determined on a case by case basis for each contract. The line items shall be as follows:
a. Approval of Design Review Report: The TABS Agency is required to
SECTION 01 20 00 Page 1 conduct a review of the project plans and specifications to identify any feature, or the lack thereof, that would preclude successful testing and balancing of the project HVAC systems. The resulting findings shall be submitted to the Government to allow correction of the design. The progress payment shall be issued after review and approval of the report.
b. Approval of the pre-field engineering report: The TABS Agency submits a report which outlines the scope of field work. The report shall contain details of what systems will be tested, procedures to be used, sample report forms for reporting test results and a quality control checklist of work items that must be completed before TABS field work commences.
c. Season I field work: Incremental payments are issued as the TABS field work progresses. The TABS Agency mobilizes to the project site and executes the field work as outlined in the pre-field engineering report. The HVAC water and air systems are balanced and operational data shall be collected for one seasonal condition (either summer or winter depending on project timing).
d. Approval of Season I report: On completion of the Season I field work, the data is compiled into a report and submitted to the Government. The report is reviewed, and approved, after ensuring compliance with the pre-field engineering report scope of work.
e. Completion of Season I field QA check: Contract QC and Government representatives meet the TABS Agency at the jobsite to retest portions of the systems reported in the Season I report. The purpose of these tests are to validate the accuracy and completeness of the previously submitted Season I report.
f. Approval of Season II report: The TABS Agency completes all Season II field work, which is normally comprised mainly of taking heat transfer temperature readings, in the season opposite of that under which Season I performance data was compiled. This data shall be compiled into a report and submitted to the Government.
On completion of submittal review to ensure compliance with the pre-field engineering report scope, progress payment is issued.
Progress payment is less than that issued for the Season I report since most of the water and air balancing work effort is completed under Season I.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause "DFARS 252.236-7000, Modification Proposals-Price Breakdown," and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates shall be based upon the applicable provisions of the EP-1110-1-8 .
1.5 CONTRACTOR'S PAYMENT REQUEST
1.5.1 Proper Payment Request
A proper request for payment/invoice shall comply with all requirements specified in this Section and the contract payment clauses. If any invoice does not comply with these requirements, it shall be returned with a statement of the reasons why it was not a proper invoice. A proper
SECTION 01 20 00 Page 2 payment request/invoice includes the following information, completed forms, and number of copies indicated. Upon request, the Contracting Officer will furnish copies of Government forms.
a. Contractor's Invoice on NAVFAC Form 7300/30, which shall show the basis for arriving at the amount of the invoice. Submit one original and two copies.
b. Contractor's Monthly Estimate for Voucher (LANTNAVFACENGCOM Form 4-4330/110. Submit original and two copies.
c. Payment Certification. Furnish as specified in "FAR Clause 52.232-5 (c) Payments under Fixed-Price Construction Contracts."
Submit one original.
d. QC Invoice Certification. Furnish as specified in Section 01 45 10, "Quality Control." Submit one original.
1.5.1.1 Progress Payments
In addition to the requirements stated in Paragraph 1.5.1, "Proper Payment Request" above, the Contractor's request for progress payments shall include the following:
a. Updated Progress Schedule: Furnish an updated progress schedule as specified in contract clause FAR 52.236-15 "Schedules for Construction Contracts" and Section 01 32 16, "Construction Progress Documentation." Submit one copy.
1.5.1.2 Final Payments
The request for final payment is submitted after completion and acceptance of all work and all other requirements of the contract. Before submitting the final invoice the Contractor shall meet with the appropriate Government representatives to determine the final invoice amount, including the assessment of liquidated damages, if any, and to make sure the final release is complete and accurate. In addition to the requirements in Paragraph 1.5.1, "Proper Payment Request" above, the Contractor's request for final payment shall include the following:
a. A final release executed on the standard form provided by the Contracting Officer. Submit two originals with final payment request.
b. NC Tax certified statement and report for the prime and each subcontractor (FAR 52.229-7). Submit two copies.
c. As-built drawings (if applicable).
d. Warranties (if applicable).
e. O&M manuals (if applicable).
f. Final payrolls (FAR 52.222-6).
g. A release for an assignment of claims (if applicable). Submit three originals.
SECTION 01 20 00 Page 3
1.5.2 Procedures for Submitting Payment Request
a. The Contractor may submit only one invoice for payment each month as the work progresses.
b. The invoice shall be delivered to the ROICC Office, Administrative Branch, between five calendar days before and five calendar days after the contract award date. Invoices received outside this schedule shall be returned to the Contractor unprocessed. The Contractor will have to wait until the following month to submit their next invoice.
c. Invoices shall be delivered during normal work hours from 7:30 AM up to 4:00 PM (EST), Monday through Friday, excluding holidays.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of a proper payment request/invoice by the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to the following:
a. Reasonable retention and/or deductions due to defects in material or workmanship; potential liquidated damages; and/or failure to comply with any other requirements of the contract.
b. Claims which the Government may have against the Contractor under or in connection with this contract; and
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor.
d. Failure to provide up to date record drawings not current as stated in Contract Clause "FAC 5252.236-9310, Record Drawings"; NC State tax certified statement and report in accordance with FAR 52.229-2; labor payrolls in accordance with FAR 52.222-6; as-built drawings in accordance with Section 01 45 10, "Quality Control";
warranties and O&M manuals; and any other requirements in the contract.
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed preparatory work, and off- site materials to be considered for progress payment shall be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment considerations include, but are not limited to, structural steel, SECTION 01 20 00 Page 4 non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/ prestressed concrete products, plastic lumber (e.g. fender piles/ curbs), and high-voltage electrical cable. Materials no acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation shall be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Earned Value Report requirement of this contract. Requests for progress payment considerations for such items shall be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Provide a written consent from the surety company with each payment request for offsite materials.
f. Materials to be considered for progress payments prior to installation shall be stored in the Continental United States.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 20 00 Page 5
SECTION 01 20 00 Page 6
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
02/13
PART 1 GENERAL
1.1 SUBMITTALS
Submit the following in accordance with the Section 01 33 00, "Submittal Procedures."
SD-01 Preconstruction Submittals
List of contact personnel
1.2 MINIMUM INSURANCE REQUIREMENTS
Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:
a. Comprehensive general liability: $500,000 per occurrence
b. Automobile liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage
c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws,
d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers,
e. Others as required by State law.
1.3 ELECTRONIC MAIL (E-MAIL)
a. The Contractor is required to establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats.
b. Within 10 days after contract award; the Contractor shall provide the Contracting Officer a single (only one) e-mail address for the ROICC office to send communications related to this contract correspondence. The ROICC office may also use e-mail to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc.
c. Multiple e-mail addresses are not authorized.
d. It is the Contractor's responsibility to make timely distribution of all ROICC e-mail within its own organization, including field office(s).
e. The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to their e-mail address.
SECTION 01 30 00 Page 1
1.4 CONTRACTOR PERSONNEL REQUIREMENTS
1.4.1 Subcontractors and Personnel
Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.4.2 Identification Badges
Identification badges will be furnished without charge. Application for and use of badges will be as directed below. Immediately report instances of lost or stolen badges to the Contracting Officer. Employees are required to resubmit a complete 50 state criminal records check in order to renew their contractor badge.
1.4.3 Business Access Security Requirements
1.4.3.1 Business Access Definition
Contractor/subcontractor employees requiring installation access to MCB, Camp Lejeune or MCAS New River, N.C. must obtain a Business Access Identification Badge for that particular installation. Regularly scheduled delivery personnel, to include FEDEX, UPS, Pick-up and deliveries, should, also, follow the Business Access guidelines described below. Personnel requiring Business Access Identification Badges shall submit all documentation listed below. Badges are not required if the contracted position requires the employee to obtain a Common Access Card (CAC) which will be identified separately within the Government contract.
1.4.3.2 Installation Security Access Requirements
Contractor shall accomplish the security requirements below within 10 days after award or prior to performance under the contract.
1.4.3.3 Business Access Identification Badge Requirement
In order to obtain a Business Access Identification Badge for access to MCB, Camp Lejeune, and satellite activities, or MCAS New River, NC, all personnel providing services under this contract shall be required to present the documentation below to the following offices, as applicable:
MCB, Camp Lejeune, NC and its satellite activities. Report as follows:
a. Identification Card Center, 60 Molly Pitcher Road for badge (910-450-8444).
MCAS New River, NC. Report as follows:
a. Pass and Identification Office, Bldg AS-187 for badge (910-449-7695) and vehicle pass (910-449-5513).
1.4.3.4 Proof of Employee Citizenship or Legal Alien Status
Employers may participate in the E-verify program (1-888-464-4218, www.DHS.gov/e-verify) allowing U.S. employers to verify name, DOB, and SSN along with immigration information for non-citizens, against federal databases in order to verify the employment eligibility of both citizens
SECTION 01 30 00 Page 2 and non-citizen new hires.
1.4.3.5 Proof of Criminal Records Check
Commercial and contract employees must provide proof a complete 50 state criminal records check on an annual basis. The record check may be obtained from any of the following Internet investigative services: Kroll (former Infolink Screening Services) at www.kroll.com, Castle Branch at www.castlebranch.com, or any other investigative services company that provides records checks for all 50 states. These services also validate social security card numbers. All criminal history checks must be completed no more than 30 days prior to start date of contract. (Note:
These Internet screening services are listed as possible sources for obtaining a criminal background check. The United States government and the United States Marine Corps do not endorse nor are they affiliated with any of these services).
1.4.3.6 Letter Provided By Contracting Officer Indicating Contract
Letter provided by Contracting Officer indicating contract, contract period and prime contractor. Proof of employment on a valid Government contract (e.g., a letter on company letterhead from the prime contractor including contract number and term).
1.4.3.7 Photo ID
Valid state or federal issued picture identification card. Acceptable documents include state drivers license, DMV issued photo identification, or alien registration card.
1.4.3.8 National Crime Investigation Center (NCIC) Check
Provost Marshals are authorized to conduct a national crime information center (NCIC) check of all persons entering the installation, if/where applicable, the NCIC check may include drivers's license query, wants and warrants, and criminal history.
1.4.4 Denial of Access
Installation access shall be denied if it is determined that an employee:
a. Is on the National Terrorist Watch List
b. Is illegally present in the United States.
c. Is subject to an outstanding warrant.
d. Has knowingly submitted an employment questionnaire with false or fraudulent information.
e. Has been issued a debarment order and is currently banned from military installations.
f. Is a Registered Sexual Offender.
g. Has been convicted of a felony or a drug crime within the past five years.
h. Individuals who have received a DUI/DWI in the last year may be
SECTION 01 30 00 Page 3 allowed access to the installation, but will not be permitted to drive on the installation.
i. Any reason the Installation Commander deems reasonable for the good order and discipline.
1.4.5 Appeal Process
All appeals should be directed to the Base Inspector's Office for any individual that has been denied access to the Base.
1.4.6 Display of Badges
Contractors/subcontractors shall prominently display their badges on their person at all times. Upon completion/termination of this contract or an individual's employment, the Contractor shall collect and turn in to the Pass & ID Office all badges. If the Contactor fails to obtain the employee's badge, the Pass & ID Office will be notified within 24 hours.
Immediately report instances of lost or stolen badges to the Contracting Officer.
1.4.7 Contractor and Subcontractor Vehicle Requirements
Each vehicle to be used in contract performance shall show the Contractor's or subcontractor's name so that it is clearly visible and shall always display a valid state license plate and safety inspection sticker. To obtain a vehicle decal, which will be valid for one year or contract period, whichever is shorter, Contractor or subcontractor vehicle operators shall provide to the Vehicle Registration Office, 60 Molly Pitcher Road (910-451-1158) or to MCAS, Building AS-187 (910-449-5513) for vehicle decal:
a. An installation sponsor request forwarded to provost Marshall office
b. A valid form of Federal or state government I.D.
c. If driving a motor vehicle, a valid driver's license, vehicle registration and proof of insurance
Upon completion/termination of this contract or an individual's employment, the Contractor shall collect and turn in to Vehicle Registration all Government vehicle decals. If any are not collected, the Contractor shall notify the Vehicle Registration Office within 24 hours.
1.4.8 Security Checks
Contractor personnel and vehicles shall only be present in locations relevant to contract performance. All Contractor personnel entering the base shall conform to all Government regulations and are subject to such checks as may be deemed necessary to ensure that violations do not occur.
Employees shall not be permitted on base when such a check reveals that their presence would be detrimental to the security of the base. Subject to security regulations, the Government will allow access to an area for servicing equipment and/or performing required services. Upon request, the Contractor shall submit to the Contracting Officer questionnaires and other forms as may be required for security purposes.
SECTION 01 30 00 Page 4
1.4.9 Subcontractor Special Requirements
1.4.9.1 Space Temperature Control, HVAC TAB, and Apparatus Inspection
All contract requirements of Section 23 09 23.13, BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC," Section 23 05 93, "TESTING, ADJUSTING, AND BALANCING FOR HVAC," and shall be accomplished directly by a first tier subcontractor. No work required by these sections shall be accomplished by a second tier subcontractor.
1.4.9.2 Telecommunication and High Voltage Work
When telecommunications and high voltage work is required, all work associated with telecommunications and high voltage shall be accomplished by a first tier subcontractor. The contractor must possess a valid North Carolina Public Utility - Electrical, contractor's license and be insured to do such work in the State of North Carolina.
1.4.9.3 Paving Associated with Utility Cuts
All pavement repairs associated with utility cuts shall be completed within 14 days of completing work within paved area.
1.5 DISCLOSURE OF INFORMATION
Contactor shall comply as follows:
a. The Contractor shall not release to anyone outside the Contractor's organization any unclassified information, regardless of medium (e.g., film, tape, document), pertaining to any part of this contract or any program related to this contact, unless -
(1) The Contracting Officer has given prior written approval; or
(2) The information is otherwise in the public domain before the date of release.
b. Requests for approval shall identify the specific information to be released, the medium to be used, and the purpose for the release. The Contractor shall submit its request to the Contracting Officer at least 45 days before the proposed date for release.
c. The Contractor agrees to include a similar requirement in each subcontract under this contract. Subcontractors shall submit requests for authorization to release through the prime contractor to the Contracting Officer.
1.6 SUPERVISION
Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (CQ) representative is required on the contract, then that individual shall also have fluent English communication skills.
NOTE: If training and experience requirements of Section 01 45 10, "Quality Control" and 01 35 29, "Safety and Occupational Health Requirements" have been met the supervisor may also serve as QC Manager and
SECTION 01 30 00 Page 5
Site Safety and Health Officer (SSHO).
1.7 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices, shop drawings, and other submittals, scheduling programming, and prosecution of the work.
Major subcontractors who will engage in the work shall also attend.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 30 00 Page 6
SECTION 01 31 23.13 20
ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM
05/17
PART 1 GENERAL
1.1 CONTRACT ADMINISTRATION
Utilize the Naval Facilities Engineering Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or e-mail submission, including originals or copies, of the documents identified in Table 1 are not permitted, except where eCMS is unavailable, non-functional or specifically requested in addition to electronic submission. Contact the Contracting Officer's Representative (COR) regarding availability of eCMS training and reference materials.
1.2 USER PRIVILEGES
The Contractor will be provided access to eCMS. All technical submittals and documents must be transmitted to the Government via the COR. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.
1.3 SUBMITTALS
Provide all submittals in accordance with Section 01 33 00 SUBMITTAL PROCEDURES and the submittal register.
SD-01 Preconstruction Submittals
List of Contractor's Personnel
1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY
1.4.1 General
The eCMS requires a web-browser (platform-neutral) and Internet connection. Obtain from an approved vendor an External Certification Authority (ECA), Primary Key Infrastructure (PKI) certificate, or other similar digital identification to support two-factor authentication and access to eCMS. Provide and maintain computer hardware and software for the eCMS access throughout the duration of the contract for all Contractor-designated users. Provide connectivity, speed, bandwidth, and access to the Internet to ensure adequate functionality. Neither upgrading of the Contractor's computer system nor delays associated from the usage of the eCMS will be justification or grounds for a time extension or cost adjustment to the Contract.
1.4.2 Contractor Personnel List
Within 20 calendar days of contract award, provide to the Contracting Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing and management of electronic technical
SECTION 01 31 23.13 20 Page 1 submittals and documents and will require access to the eCMS. Project personnel roles to be filled in the eCMS include the Contractor's Project Manager, Superintendent, Quality Control (QC) Manager, and Site Safety and Health Officer (SSHO). Personnel must be capable of electronic document management. Notify the COR immediately of any personnel changes to the project. The Contracting Officer reserves the right to perform a security check on all potential users. Provide the following information:
First Name Last Name E-mail Address Office Address Project Role (e.g. Project Manager, QC Manager, Superintendent)
1.5 SECURITY CLASSIFICATION
In accordance with Department of Navy guidance, all military construction contract data are unclassified, unless specified otherwise by a properly designated Original Classification Authority (OCA) and in accordance with an established Security Classification Guide (SCG). Refer to the project's OCA when questions arise about the proper classification of information.
The eCMS and tablet computer must only be used for the transaction of unclassified information associated with construction projects. In conformance with the Freedom of Information Act (FOIA), Department of Defense Manual 5200.01-V4: DoD Information Security Program: Controlled Unclassified Information (CUI), and DoD requirements, any unclassified project documentation uploaded into the eCMS must be designated either "U
- UNCLASSIFIED" (U) or "FOUO - UNCLASSIFIED-FOR OFFICIAL USE ONLY" (FOUO).
1.6 ECMS UTILIZATION
Establish, maintain, and update data and documentation in the eCMS throughout the duration of the contract.
Personally Identifiable Information (PII) transmittal is not permitted in the eCMS.
1.6.1 Information Security Classification/Identification
The eCMS must be used for the transmittal of the following documents.
This requirement supersedes conflicting requirements in other sections), however, submittal review times in Section 01 33 00 SUBMITTAL PROCEDURES remain applicable. Table 1 - Project Documentation Types provides the appropriate U and FOUO designations for various types of project documents. Construction documents requiring FOUO status must be marked accordingly. Apply the appropriate markings before any document is uploaded into eCMS. Markings are not required on U documents.
Table 1 also identifies which eCMS application is to be used in the transmittal of data (these are subject to change based on the latest software configuration). If a designated application is not functional within 4 hours of initial attempt, defer to the Submittal application and submit the required data as an uploaded portable document (e.g. PDF), word processor, spreadsheet, drawing, or other appropriate format. Hard copy or e-mail submission of these items is acceptable only if eCMS is documented to be not available or not functional. After uploading documents to the Submittal application, transmit the submittals and
SECTION 01 31 23.13 20 Page 2 attachments to the COR via the Transmittal application. For Submittals, select the following:
Preparation by = Contractor personnel assigned to prepare the submittal Approval by = Contracting Officer Representative (COR) Returned by = Design Lead/Manager Forwarded to = Contractor project manager
Table 1 - Project Documentation Types
SUBJECT/NAME CLASS REMARKS ECMS APPLI CATI ON
As-Built Drawings U Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Submittals and Transmittals
Building Information Modeling (BIM)
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
Construction Permits U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
Construction Schedules (Activities and Milestones)
U After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Submittals, Transmittals and Scheduling App
Construction Schedules (Cost-Loaded)
FOUO After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Submittals, Transmittals and Scheduling App
Construction Schedules (3-Week Lookahead)
U Import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Scheduling App
DD 1354 Transfer of Real Property
U Submittals and Transmittals
SECTION 01 31 23.13 20 Page 3
SUBJECT/NAME CLASS REMARKS ECMS APPLI CATI ON
Daily Production Reports
FOUO Provide weather conditions, crew size, man-hours, equipment, and materials information
Daily Report
Daily Quality Control (QC) Reports
FOUO Provide QC Phase, Definable Features of Work Identify visitors
Daily Report
Designs and Specifications
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
Environmental Notice of Violation (NOV), Corrective Action Plan
U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
Environmental Protection Plan (EPP)
FOUO Submittals and Transmittals
Invoice (Supporting Documentation)
FOUO Applies to supporting documentation only. Invoices are submitted in Wide-Area Workflow (WAWF)
Submittals and Transmittals
Jobsite Documentation, Bulletin Board, Labor Laws, SDS
U Submittals and Transmittals
Meeting Minutes FOUO Meeting Minutes
Operations & Maintenance Support Information (OMSI/eOMSI), Facility Data Worksheet
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
Photographs U Subject to base/installation restrictions
Submittals and
SECTION 01 31 23.13 20 Page 4
QCM Initial Phase Checklists
FOUO Checklists (Site Management)
QCM Preparatory Phase Checklists
FOUO Checklists (Site Management)
Quality Control Plans FOUO Submittals and Transmittals
QC Certifications U Submittals and Transmittals
QC Punch List U Punch Lists (Testing Logs)
Red-Zone Checklist U Checklists (Site Management)
Rework Items List FOUO Punch Lists (Testing Logs)
Request for Information (RFI) Post-Award
FOUO RFIs
Safety Plan FOUO Daily Report
Safety - Activity Hazard Analyses (AHA)
FOUO Daily Report
Safety - Mishap Reports
FOUO Daily Report
SCIF/SAPF
Accreditation Support Documents
FOUO Note: Some Construction Security plans may be classified as Secret.
Classified information must not be uploaded into eCMS. Refer to the Site Security Manager, as applicable.
Submittals and Transmittals
Shop Drawings U Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Submittals and
SECTION 01 31 23.13 20 Page 5
Storm Water Pollution Prevention (Notice of Intent - Notice of Termination)
U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
Submittals and Submittal Log
U Submittals and Transmittals
Testing Plans, Logs, and Reports
FOUO Submittals and Transmittals
Training/Reference Materials
U Submittals and Transmittals
Training Records (Personnel)
FOUO Submittals and Transmittals
Utility Outage/Tie-In Request/Approval
FOUO Submittals and Transmittals
Warranties/BOD Letter FOUO Submittals and Transmittals
Quality Assurance Reports
FOUO Checklists (Government initiated)
Non-Compliance Notices
FOUO Non-Compliance Notices (Government initiated)
Other Government-prepared documents
FOUO GOV ONLY
All Othere Documents FOUO Refer to FOIA guidelines and contact the FOIA official to determine whether exemptions exist
As applicable
1.6.2 Markings on FOUO documents
a. Only FOUO documents being…