This document is a Specification Section (01 57 19) for Temporary Environmental Controls, detailing comprehensive environmental protection requirements for a construction project. The specification outlines the contractor's obligations to control environmental pollution and damage across air, water, and land resources, including management of visual aesthetics, noise, solid waste, radiant energy, and radioactive materials. Key requirements include identifying and protecting land resources, minimizing soil exposure, reducing noise levels, maintaining specific decibel limitations during construction activities, and implementing noise abatement measures such as using sound-deadening devices, physical barriers, and efficient mufflers on equipment.

The document provides detailed guidelines for environmental protection, including: marking work area limits, protecting landscape features like trees and shrubs, constructing diversion ditches to control runoff, limiting construction noise to specific time frames and sound levels (ranging from 70-85 decibels depending on duration), and requiring sound level measurements every five working days. The contractor must also submit a comprehensive Environmental Protection Plan that includes details on personnel responsibilities, hazardous waste management, training programs, applicable laws and permits, protection methods for natural and cultural resources, and environmental monitoring plans. Upon project completion, the contractor must restore any damaged property and leave the construction area in a clean, satisfactory condition.

View the file

Other files

File Type Posted
S05 - RFIs - 02022026 - Bldg 73 - Minneapolis.pdf PDF
S06 - Amend 0002 - 02022026 - 36C77626R0016 - Bldg 73 - Minneapolis.pdf PDF
S05 - RFIs - 02022026 - Bldg 73 - Minneapolis.pdf PDF
36C77626R0016 0001.docx DOCX document
RFP - Att 13 - SOW - Att 13a - Infra Stnd for TeleComm Spaces - Bldg 73 Reno - MN.pdf PDF
RFP - Att 20 - Limitations on Subcontracting - Constr - Bldg 73 Reno - MN.docx DOCX document
RFP - Att 05 - SOW - Att 05 - 01 42 19 Ref Standards - Bldg 73 Reno - MN.pdf PDF
RFP - Att 21 - PPQ - Bldg 73 Reno - MN.docx DOCX document
RFP - Att 13 - SOW - Att 13b - Infra Stnd for TeleComm Spaces - Bldg 73 Reno - MN.pdf PDF
RFP - Att 06 - SOW - Att 06 - 01 45 00 QC - Bldg 73 Reno - MN.pdf PDF
RFP - Att 15 - SOW - Att 15 - VA Revit - Bldg 73 Reno - MN.pdf PDF
RFP - Att 04 - SOW - Att 04 - 01 35 26 Safety Req - Bldg 73 Reno - MN.pdf PDF
RFP - Att 17 - Wage Rates - DBA - Hennepin - 01022026 - Bldg 73 - Minneapolis.pdf PDF
RFP - Att 08 - SOW - Att 08 - DWG - Site Plan - Bldg 73 Reno - MN.pdf PDF
RFP - Att 12 - SOW - Att 12 - HVAC Design Man - Bldg 73 Reno - MN.pdf PDF
RFP - Att 09 - SOW - Att 09 - 01 33 24 Ele Submittal - Bldg 73 Reno - MN.pdf PDF
RFP - Att 02 - SOW - Att 02 - 01 33 23 Submittals - Bldg 73 Reno - MN.pdf PDF
RFP - Att 11 - SOW - Att 11 - PG 18 10 - Bldg 73 Reno - MN.pdf PDF
RFP - Att 03 - SOW - Att 03 - 01 32 1616 Prj Sch - Bldg 73 Reno - MN.pdf PDF
RFP - Att 14 - SOW - Att 14 - BIM Worksheet - Bldg 73 Reno - MN.pdf PDF
RFP - Att 22 - Division Cost Breakdown - Bldg 73 Reno - MN.xlsx XLSX spreadsheet
S02 - RFP - 36C77626R0016_1 - 01162026 FINAL - Bldg 73 Reno - Minneapolis.docx DOCX document
RFP - Att 18 - Wage Rates - SCA - Hennepin - 12032025 - Bldg 73 - Minneapolis.pdf PDF
RFP - Att 10 - SOW - Att 10 - DWG - Furniture RVD - Bldg 73 Reno - MN.pdf PDF
RFP - Att 19 - SOW - RVD - Final - 11242025 - Bldg 73 Reno - Minneapolis.pdf PDF
RFP - Att 01 - SOW - Att 01 - Spec 00 01 00 - 10212025 - Bldg 73 Reno - MN.pdf PDF
RFP - Att 16 - SOW - Att 16 - MN Design Stnd - Bldg 73 Reno - MN.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01-01-21

01 57 19 -1

SECTION 01 57 19

TEMPORARY ENVIRONMENTAL CONTROLS

PART 1 - GENERAL

1.1 DESCRIPTION

This section specifies the control of environmental pollution and damage that the Contractor must consider for air, water, and land resources. It includes management of visual aesthetics, noise, solid waste, radiant energy, and radioactive materials, as well as other pollutants and resources encountered or generated by the Contractor.

The Contractor is obligated to consider specified control measures with the costs included within the various contract items of work.

Environmental pollution and damage is defined as the presence of chemical, physical, or biological elements or agents which:

1. Adversely effect human health or welfare,

2. Unfavorably alter ecological balances of importance to human life,

3. Effect other species of importance to humankind, or;

4. Degrade the utility of the environment for aesthetic, cultural, and historical purposes.

Definitions of Pollutants:

1. Chemical Waste: Petroleum products, bituminous materials, salts, acids, alkalis, herbicides, pesticides, organic chemicals, and inorganic wastes.

2. Debris: Combustible and noncombustible wastes, such as leaves, tree trimmings, ashes, and waste materials resulting from construction or maintenance and repair work.

3. Sediment: Soil and other debris that has been eroded and transported by runoff water.

4. Solid Waste: Rubbish, debris, garbage, and other discarded solid materials resulting from industrial, commercial, and agricultural operations and from community activities.

5. Surface Discharge: The term "Surface Discharge" implies that the water is discharged with possible sheeting action and subsequent soil erosion may occur. Waters that are surface discharged may terminate in drainage ditches, storm sewers, creeks, and/or "water of the United States" and would require a permit to discharge water from the governing agency.

01 57 19 -2

6. Rubbish: Combustible and noncombustible wastes such as paper, boxes, glass and crockery, metal and lumber scrap, tin cans, and bones.

7. Sanitary Wastes:

a. Sewage: Domestic sanitary sewage and human and animal waste.

b. Garbage: Refuse and scraps resulting from preparation, cooking, dispensing, and consumption of food.

1.2 QUALITY CONTROL

Establish and maintain quality control for the environmental protection of all items set forth herein.

Record on daily reports any problems in complying with laws, regulations, and ordinances. Note any corrective action taken.

1.3 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. National Archives and Records Administration (NARA):

33 CFR 328....................Definitions

1.4 SUBMITTALS

In accordance with Section, 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, furnish the following:

1. Environmental Protection Plan: After the contract is awarded and prior to the commencement of the work, the Contractor shall meet with the Contracting Officer’s Representative (COR) to discuss the proposed Environmental Protection Plan and to develop mutual understanding relative to details of environmental protection. Not more than 20 days after the meeting, the Contractor shall prepare and submit to the Contracting Officer // for approval, a written and/or graphic Environmental Protection Plan including, but not limited to, the following:

a. Name(s) of person(s) within the Contractor's organization who is

(are) responsible for ensuring adherence to the Environmental

Protection Plan.

b. Name(s) and qualifications of person(s) responsible for manifesting hazardous waste to be removed from the site.

c. Name(s) and qualifications of person(s) responsible for training the Contractor's environmental protection personnel.

d. Description of the Contractor's environmental protection personnel training program.

01 57 19 -3

e. A list of Federal, State, and local laws, regulations, and permits concerning environmental protection, pollution control, noise control and abatement that are applicable to the

Contractor's proposed operations and the requirements imposed by those laws, regulations, and permits.

f. Methods for protection of features to be preserved within authorized work areas including trees, shrubs, vines, grasses, ground cover, landscape features, air and water quality, fish and wildlife, soil, historical, and archeological and cultural resources.

g. Procedures to provide the environmental protection that comply with the applicable laws and regulations. Describe the procedures to correct pollution of the environment due to accident, natural causes, or failure to follow the procedures as described in the

Environmental Protection Plan.

h. Permits, licenses, and the location of the solid waste disposal area.

i. Drawings showing locations of any proposed //temporary excavations or embankments for haul roads, // stream crossings, // material storage areas, structures, sanitary facilities,// and stockpiles of excess or spoil materials. Include as part of an

Erosion Control Plan approved by the District Office of the U.S.

Soil Conservation Service and the Department of Veterans Affairs.

j. Environmental Monitoring Plans for the job site including land, water, air, and noise.

k. Work Area Plan showing the proposed activity in each portion of the area and identifying the areas of limited use or nonuse. Plan should include measures for marking the limits of use areas. This plan may be incorporated within the Erosion Control Plan.

l. Inclusion of “best management practices” and methodologies.

Approval of the Contractor's Environmental Protection Plan will not relieve the Contractor of responsibility for adequate and continued control of pollutants and other environmental protection measures.

1.5 PROTECTION OF ENVIRONMENTAL RESOURCES

Protect environmental resources within the project boundaries and those affected outside the limits of permanent work during the entire period of this contract. Confine activities to areas defined by the specifications and drawings.

01 57 19 -4

Protection of Land Resources: Prior to construction, identify all land resources to be preserved within the work area. Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and landforms without permission from the COR.

Do not fasten or attach ropes, cables, or guys to trees for anchorage unless specifically authorized, or where special emergency use is permitted. Provide erosion control plans, in phases where required.

1. Work Area Limits: Prior to any construction, mark the areas that require work to be performed under this contract. Mark or fence isolated areas within the general work area that are to be saved and protected. Protect monuments, works of art, and markers before construction operations begin. Convey to all personnel the purpose of marking and protecting all necessary objects.

2. Protection of Landscape: Protect trees, shrubs, vines, grasses, land forms, and other landscape features shown on the drawings to be preserved by marking, fencing, or using any other approved techniques.

a. Box and protect from damage existing trees and shrubs to remain on the construction site.

b. Immediately repair all damage to existing trees and shrubs by trimming, cleaning, and painting with antiseptic tree paint.

c. Do not store building materials or perform construction activities closer to existing trees or shrubs than the farthest extension of their limbs.

3. Reduction of Exposure of Unprotected Erodible Soils: Plan and conduct earthwork to minimize the duration of exposure of unprotected soils. Clear areas in reasonably sized increments only as needed to use. Form earthwork to final grade as shown.

Immediately protect side slopes and back slopes upon completion of rough grading.

4. Temporary Protection of Disturbed Areas: Construct diversion ditches, benches, and berms to retard and divert runoff from the construction site to protected drainage areas approved under paragraph 208 of the Clean Water Act.

Reduction of Noise: Minimize noise using every action possible. Perform noise-producing work in less sensitive hours of the day or week as directed by the COR. Maintain noise-produced work at or below the decibel levels and within the time periods specified.

01 57 19 -5

1. Perform construction activities involving repetitive, high-level impact noise only between 7:00 a.m. and 6:00 p.m. unless otherwise permitted by local ordinance or the COR. Repetitive impact noise on the property shall not exceed the following dB limitations:

Time Duration of Impact Noise Sound Level in dB

More than 12 minutes in any hour 70

Less than 30 seconds of any hour 85

Less than three minutes of any hour 80

Less than 12 minutes of any hour 75

SPEC WRITER NOTE: Insert additional information as needed when unique to a particular VA Medical Center site.

2. Provide sound-deadening devices on equipment and take noise abatement measures that are necessary to comply with the requirements of this contract, consisting of, but not limited to, the following:

a. Maintain maximum permissible construction equipment noise levels at 15 meter (50 feet) (dBA):

EARTHMOVING MATERIALS HANDLING

FRONT LOADERS 75 CONCRETE MIXERS 75

BACKHOES 75 CONCRETE PUMPS 75

DOZERS 75 CRANES 75

TRACTORS 75 DERRICKS IMPACT 75

SCAPERS 80 PILE DRIVERS 95

GRADERS 75 JACK HAMMERS 75

TRUCKS 75 ROCK DRILLS 80

PAVERS, STATIONARY 80 PNEUMATIC TOOLS 80

PUMPS 75 BLASTING //__//

GENERATORS 75 SAWS 75

COMPRESSORS 75 VIBRATORS 75

b. Use shields or other physical barriers to restrict noise transmission.

c. Provide soundproof housings or enclosures for noise-producing machinery.

d. Use efficient silencers on equipment air intakes.

01 57 19 -6

e. Use efficient intake and exhaust mufflers on internal combustion engines that are maintained so equipment performs below noise levels specified.

f. Line hoppers and storage bins with sound deadening material.

g. Conduct truck loading, unloading, and hauling operations so that noise is kept to a minimum.

3. Measure sound level for noise exposure due to the construction at least once every five successive working days while work is being performed above 55 dB(A) noise level. Measure noise exposure at the property line or 15 m (50 feet) from the noise source, whichever is greater. Measure the sound levels on the A weighing network of a

General Purpose sound level meter at slow response. To minimize the effect of reflective sound waves at buildings, take measurements at

900 to 1800 mm (three to six feet) in front of any building face.

Submit the recorded information to the COR noting any problems and the alternatives for mitigating actions.

Restoration of Damaged Property: If any direct or indirect damage is done to public or private property resulting from any act, omission, neglect, or misconduct, the Contractor shall restore the damaged property to a condition equal to that existing before the damage at no additional cost to the Government. Repair, rebuild, or restore property as directed or make good such damage in an acceptable manner.

Final Clean-up: On completion of project and after removal of all debris, rubbish, and temporary construction, Contractor shall leave the construction area in a clean condition satisfactory to the COR.

Cleaning shall include off the station disposal of all items and materials not required to be salvaged, as well as all debris and rubbish resulting from demolition and new work operations.

- - - E N D - - -

SECTION 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
PART 1 - GENERAL
1.1 DESCRIPTION
1.2 QUALITY CONTROL
1.3 references
1.4 Submittals
1.5 PROTECTION OF ENVIRONMENTAL RESOURCES

File details come from the government source that posted it. Updated .