This is a Request for Proposal (RFP) issued by the U.S. General Services Administration (GSA) for an elevator modernization project at the Gerald R. Ford Federal Building & U.S. Courthouse in Grand Rapids, Michigan. The solicitation is set aside exclusively for small businesses, with an estimated project cost range between $3,500,000 and $4,500,000. The project involves comprehensive modernization of three passenger elevators and one service elevator, including demolition, replacement of hoisting machines, control panels, electrical systems, mechanical equipment, lighting, cab interiors, and associated fire alarm and sprinkler system modifications.
Key proposal details include a solicitation release date of April 15, 2025, with proposals due by May 21, 2025 at 2:00 PM Eastern Time. The contract will require substantial completion within 587 calendar days from the Notice to Proceed, with an additional 45 days for punch list work and close-out documentation. A pre-proposal conference is scheduled for April 28, 2025, and prospective bidders must complete a registration form to attend. The contract will also include 12 months of service maintenance after construction completion. Interested small businesses must submit electronic proposals via email, including technical and price proposals, past performance questionnaires, representations and certifications, and a bid bond.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 47PF0025R0027_Amendment 0002.pdf | ||
| 47PF0025R0027_Amendment 0001.pdf | ||
| Preproposal Conf Agenda_GR Elevator Modernization.pdf | ||
| Preproposal Conf Sign In Sheet_GR Elevator Modernization.pdf | ||
| GR Passenger Elevators 1_2_4_Drawings.pdf | ||
| GR Service Elevator 3_Drawings.pdf | ||
| GR Passenger Elevator Spec_REV03.pdf | ||
| Preproposal Mtg Registration_GR Elevator.pdf | ||
| GR Service Elevator Spec_REV03.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GSA GSA GSA GSA GSA GSA GSA GSA GSA GSA GSA GSA
Request for Proposal (RFP)
U.S. GENERAL SERVICES
ADMINISTRATION
GREAT LAKES REGION
PUBLIC BUILDINGS SERVICE
Acquisition Management Division
PROJECT:
Elevator Modernization Gerald R Ford Federal Building & U.S. Courthouse 110 Michigan St, NW Grand Rapids, MI 49503
SOLICITATION NO: 47PF0025R0027
ISSUE DATE: April 15, 2025
CLOSING DATE & TIME:
May 21, 2025 2:00 PM (Eastern Time)
CONTRACT NO:
DATE OF AWARD:
ISSUED BY:
U.S. General Services Administration Great Lakes Region Public Buildings Service Acquisition Management Division
GSA GSA GSA GSA GSA GSA GSA GSA GSA GSA GSA GSA
GSA Solicitation No. 47PF0025R0027
Document: C201-SB GC/MAR 2025 (The Solicitation)
Construction Contract for: Elevator Modernization, Gerald R. Ford Federal Building, Grand Rapids, MI
The Solicitation
Table of Contents
I. General Information A. The Solicitation and Contract B. List of Solicitation Documents C. Authorized Representatives D. Pre-Proposal Conference E. Estimated Price Range F. FAR 52.228-1 Bid Guarantee G. FAR 52.236-27 Site Visit – Construction H. Receipt of Offers
II. Proposals
A. Proposal Contents B. Proposal Format C. Price Proposal D. Technical Proposal E. Other Information to be Submitted with Proposal
III. General Provisions A. Availability of Funds B. Requests for Clarification or Interpretation C. Notice to Small Business Firms D. Information Concerning the Disclosure of Solicitation Results E. Affirmative Procurement Program F. Notice Concerning Preparation of Proposals G. Bond Requirements H. Contractor Performance Information I. Safeguarding and Dissemination of Controlled Unclassified Information
(CUI) Building Information
IV. FAR/GSAR Solicitation Provisions A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of
Federal Specifications, Standards and Commercial Item Descriptions, FPMR 101-29
B. FAR 52.216-1 Type Of Contract C. FAR 52.222-5 Construction Wage Rate Requirements-Secondary Site of
Work D. FAR 52.222-10 Buy American Requirements E. Buy American Exceptions F. FAR 52.233-2 Service of Protest G. FAR 52.252-1 Solicitation Provisions Incorporated by Reference H. GSAR 552.102 Incorporating Provisions and Clauses by Reference I. GSAR 552.252-5 Authorized Deviations in Provisions (Nov
2021)(DEVIATION FAR 52.252-5)
V. Instructions to Offerors and Clauses A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition
VI. Method Of Award
A. Evaluation of Offers B. Determination of Responsibility C. Price Reasonableness D. Unbalanced Price E. Total Evaluated Price F. Non-Price Factors
I. General Information
I.A. The Solicitation and Contract
(1) This Solicitation is set-aside for Small Businesses, in accordance with FAR 19. This Solicitation sets forth requirements for proposals for a Contract to construct the Project described in the attached Agreement. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein.
The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.
(2) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.
(3) The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer. No contract shall be formed unless and until the Contracting Officer has countersigned the SF 1442 submitted by an Offeror, and delivered to the Contractor a copy of the SF 1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.
Notice 1: Clause and provision deviations dated February 2025 do not affect the following:
1. Any FAR subparts that are based on statute or are not covered by E.O.
11246 such as:
a. FAR subparts 22.13, Equal Opportunity for Veterans and its related clauses and provisions; and
b. FAR subpart 22.14, Employment of Workers and Disabilities.
2. Existing U.S. laws on civil rights, nondiscrimination, or any laws that generally apply to a company regardless of whether it is a government contractor.
End of Notice
Notice 2:
System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations, including FAR 52.222- 25, Affirmative Action Compliance, 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals—Representation and paragraph (t) of FAR 52.212-3, Offeror Representations and Certifications— Commercial Products and Commercial Services.
GSA will not consider or use these representations. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.
End of Notice
Notice 3: February 2025 clause or provision deviations are available in class deviations CD-2025-04 (February 15, 2025) and CD-2025-05 with Supplement 1 (March 7, 2025), available at https://www.gsa.gov/policy-regulations/policy/acquisiti2on-policy/acquisition-policy-library-and-resources#tab--Class-deviations)
End of Notice
I.B. List of Solicitation Documents The Solicitation Documents are comprised of:
(1) The Solicitation
(2) Offeror Representations and Certifications Form
(3) Standard Form (SF) 1442 – Solicitation Offer and Award
(4) The Agreement and Attachments to the Agreement
(5) Other Forms Required For Submission with Proposals
I.C. Authorized Representatives
The following individuals are designated as the authorized GSA representatives under this Solicitation:
Authorized Representative Information:
Contracting Officer’s Information
Name: Joseph Daniero
Address: 110 Michigan St, NW, Suite 293, Grand Rapids, MI 49503
Telephone: 616-283-0305
Email: joe.daniero@gsa.gov
Alternate POC Information
Name: N/A
Address: N/A
Telephone: N/A
Email: N/A https://www.gsa.gov/policy-regulations/policy/acquisition-policy/acquisition-policy-library-and-resources#tab--Class-deviations https://www.gsa.gov/policy-regulations/policy/acquisition-policy/acquisition-policy-library-and-resources#tab--Class-deviations https://www.gsa.gov/policy-regulations/policy/acquisition-policy/acquisition-policy-library-and-resources#tab--Class-deviations
I.D. Pre-Proposal Conference
Date: April 28, 2025 Time: 10:30am EST Location: Gerald Ford Federal Bld & US Courthouse, 110 Michigan St, NW, Grand Rapids, MI, 49503 NOTE: In order to attend, please complete the registration form included with the solicitation package on sam.gov and email the completed form to joe.daniero@gsa.gov.
I.E. Estimated Price Range The estimated price range for the Project is between $3,500,000 and $4,500,000.
I.F. FAR 52.228-1 Bid Guarantee (Sep 96)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids;
and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
I.G. FAR 52.236-27 Site Visit – Construction (Feb 95)
(1) The clauses at FAR 52.236-2, Differing Site Conditions, and FAR 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Offerors are urged and expected to inspect the site where the work will be performed.
(2) Additional site visits other than the one to be performed during the pre-proposal conference will be conducted by appointment only at the times and dates specified by the point of contact shown below. To arrange for a site visit, contact:
Name: Thomas Monaweck- Project Manager Address: 110 Michigan St, NW, Grand Rapids, MI 49503 Telephone: 616-304-2999 Email: thomas.monaweck@gsa.gov
(3) Site visits other than the one on April 28, 2025, cannot be guaranteed and are subject to the availability of the Project Manager. Participants must have a valid, Government issued picture identification, driver’s license preferred, to gain access for the pre-proposal conference and/or a separate site visit. You will be required to go through a screening process to enter the building.
I.H. Receipt of Offers
(1) In order to be considered for award, offers conforming to the requirements of the Solicitation must be received via email no later than 2:00 pm local time on the following date and at the following email address.
Date: May 21, 2025 Address: joe.daniero@gsa.gov
II. Proposals
II.A. Proposal Contents
Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:
1. Price Proposal- (Standard Form 1442 and Pricing Sheets)
2. Technical Proposal (Experience & Past Performance)
3. Representations and Certifications
4. Standard Form 24, Bid Bond
5. GSA Form 527 – Contractor’s Qualification and Financial Information https://www.acquisition.gov/far/part-52#FAR_52_236_2 https://www.acquisition.gov/far/part-52#FAR_52_236_3
6. Other Documents as Required (Acknowledged SF30 Amendments if not acknowledged on the SF1442)
II.B. Proposal Format Offerors shall submit one electronic proposal to the attention of the GSA Contracting Officer at joe.daniero@gsa.gov. The maximum size capacity for electronic transmissions to GSA is 25mb. Therefore, all submittal information for each email must be within the 25mb limitation. Offerors responding to the solicitation notice shall submit separate attached documents in their email as listed above. If an Offeror needs to send more than one email due to these size limitations, they shall identify in the subject and/or body of the text that the email is submission 1 of 3, 2 of 3, etc. All emails must be received by the due date and time.
II.C. Price Proposal
(1) Contents
The Price Proposal shall consist of the SF 1442 and the Agreement, with prices and/or rates indicated for each price element shown on the pricing form included in Section II of the Agreement. Indicate the Contract Price in Block 17 of the SF 1442, which must be fully executed by the Offeror.
(2) Qualifications, Exclusions and Conditions
If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.
(3) Additional Proposal Requirements
Amendments to the solicitation prior to the deadline for receipt of proposals will be posted and available on www.sam.gov under the announcement number of the solicitation. Offerors are encouraged to check the solicitation announcement regularly to verify issuance of amendments. Offerors shall acknowledge receipt of all amendments and provide confirmation upon submission of the offeror’s proposal in block 19 of the SF1442. Any unacknowledged amendments in the Offeror’s proposal will be considered a deficiency in the evaluation of the proposal. The offeror may also sign any SF 30 Amendment forms and submit with their proposal if they do not acknowledge them in block 19 of the SF 1442 form.
II.D. Technical Proposal
The Technical Proposal shall include the information requested below for the non-price factors described in Section VI.
(1) Experience in Providing Construction Services on Similar Projects
This factor considers the extent of the Offeror's experience as a firm in providing similar construction services. The Offeror must demonstrate successful experience as the prime construction contractor responsible for three "similarly complex" projects substantially completed within the past eight years. A similarly complex project is defined as a project that is comparable in nature, type, and complexity as defined by the following characteristics. (NOTE: This is not an all-inclusive list):
• Project involved an upgrade, renovation, or replacement of a comparably sized passenger and/or service elevator.
• Project was performed in an occupied and functioning office building, courthouse, or large-scale commercial facility.
• Collectively, the projects submitted demonstrate the following work: demolition, replacement, and the mechanical, fire protection, and telecom work related to elevator installation.
• The total project cost at award was not less than $1,000,000.
Greater weight will be given to experience more similar in scope to this project.
Submittal Requirements: The Offeror must submit the following information at a minimum:
Provide three similarly complex projects in the last eight years in which the Offeror was the prime contractor on a construction, firm-fixed price type contract. Current similar projects must be substantially complete to be considered relevant for this factor. For each project, describe in detail: the size, scope, complexity, phasing plan (how did you limit tenant disruptions or operations), delivery method, any FedRamp approved equipment installed, planned and actual budget, planned and actual schedule, schedule control, coordination, and experience in delivering the completed projects. Describe how you worked within a fixed schedule and within the prescribed budget. Relate those in type and scope to this project.
For each project submitted, at a minimum, you must provide a project description, number of elevators involved with floors / stops, type of elevator(s) (geared, gearless, hydraulic, etc), site conditions, project schedule (for any project not completed in the amount of days specified in the solicitation and contract, please provide justification for difference), safety record, and overall scope of the project. Additionally, please provide the awarded price at the start of construction and final contract value after adjustments.
If work was performed under a federal contract, please provide the contract/task order number for the award.
All submitted examples provided must also be projects in which the Offeror provided general construction services. The Offeror should provide written demonstration of their experience in providing project planning, problem/issue resolution, coordination, phasing plan development, site logistic planning, independent cost estimating, and development of subcontractor interest necessary to complete the project within the prescribed budget and a fixed schedule.
Standard for Evaluation: The standard is met when:
The Offeror has documented significant experience providing construction services for three similarly complex projects in the past eight years as the prime construction contractor. The Offeror has satisfactorily demonstrated its knowledge and experience in providing an upgrade, renovation or replacement of a comparably sized passenger and/or service elevator, and conditions comparable to those to be encountered in this project. The Offeror has documented its ability to deliver the completed projects within a fixed schedule and within the prescribed budget. The Offeror shows relevant experience working in an occupied office building, courthouse, or large-scale commercial facility.
(2) Past Performance in Providing Construction Services on Similar Projects
This factor considers the Offeror's Past Performance for the projects submitted under Evaluation Factor 1: Experience in Providing Construction Services on Similar Projects.
This factor will be evaluated based upon the responses from the references provided by the Offeror. Past performance can be described as how an Offeror performed on a job.
The Government intends for the Offeror to contact their references directly, and that the references respond with a completed Past Performance Questionnaire (PPQ). The PPQ can be found in the solicitation package on sam.gov. The completed questionnaires may be submitted back either with the Offeror's proposal or the reference can directly email them back to the Contracting Officer (CO), Joseph Daniero, at joe.daniero@gsa.gov. Regardless of method, the completed questionnaires must be received by the CO prior to the due date of proposals. The CO also reserves the right to contact those individuals who provide references for the Offeror to verify that the services provided comply with the similarity requirements of this RFP and to assist with the assessment of the quality of those services.
FAR 15.305(a)(2)(iv) states, "In the case of an Offeror without a record of relevant past performance or for whom information on past performance is not available, the Offeror may not be evaluated favorably or unfavorably on past performance." Therefore, failure of the Offeror to provide a minimum of three relevant past performance questionnaires, and/or the inability of the Government to complete a minimum of three reference checks after making a reasonable effort to do so, may result in the Offeror being rated as "neutral" on the past performance factor. The Government is not required to contact the three required references for each Offeror. However, in addition to the past performance questionnaires provided by the Offeror/Reference, the Government may solicit other sources to find references for other relevant, similar work performed by the Offeror.
The Government also reserves the right to use other government data available in its assessment of the Offeror. The quality of the reference information supplied will be considered. In accordance with FAR 15.306, If award will be made without conducting discussions, Offerors may be given the opportunity to clarify certain aspects of proposals (e.g., the relevance of an offeror's past performance information and adverse past performance information to which the offeror has not previously had an opportunity to respond) or to resolve minor or clerical errors.
Submittal Requirements: The Offeror must ensure submission of:
Three Past Performance Questionnaires (PPQ) for the projects submitted under Evaluation Factor 1: Experience in Providing Construction Services on Similar Projects.
References must have thorough knowledge of the details of the Offeror's performance (such as the Project Manager, Building Owner, or Contracting Official associated with the project) for the majority of the contract performance period, so that the reference may sufficiently respond to the questionnaire.
Please ensure correct phone numbers and email addresses are provided for the client point of contact. Offerors should follow up with clients/references to ensure timely submission of questionnaires under either method described above. In addition, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS/UEI numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror's proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), previously submitted PPQ information, and any other known sources not provided by the Offeror. While the Government may elect to consider data from a variety of sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror. GSA will not maintain a database of PPQ’s submitted by Offerors.
Standard for Evaluation: The standard is met when:
Responses are provided by three references for the projects outlined in Factor 1:
Experience in Providing Construction Services on Similar Projects, and provide favorable evaluations indicating that the projects have met or exceeded the customer's requirements as set forth in the construction contract documents (drawings and specifications) in a timely manner, and within established budgets.
II.E. Other Information to Submit with Proposal
(1) Representations and Certifications
Offerors are reminded their SAM registration status must be “Active”, at the time their offer is submitted, to be considered for award (see FAR 52.204-7). Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual Representations and Certifications in conjunction with required Entity registration in System for Award Management (SAM), accessed via System for Award Management.
Offerors shall also submit with their proposal, the Annual Representations and Certifications (FAR 52.204-8), using the attached Offeror’s Representations and Certifications (C301).
(2) Qualifications of Offerors
Offerors submitting a proposal in response to this Solicitation shall submit with their proposal evidence of their financial responsibility and capacity to perform the Contract.
Offerors shall submit this information on GSA Form 527 – Contractor’s Qualifications and Financial Information. Where applicable, point of contact, including names and telephone numbers, are required for all contracts listed.
III. General Provisions
III.A. Availability of Funds
Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the contract shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of contract award.
III.B. Requests for Clarification or Interpretation
The Government will attempt to answer all requests for clarifications or interpretations of https://www.sam.gov/ the Solicitation Documents prior to the date set for receipt of offers, but do not warrant that all such requests will be answered within 14 calendar days. Prospective Offerors should make such requests not less than 14 calendar days prior to the date set for receipt of offers.
III.C. Notice to Small Business Firms
A program for the purpose of assisting qualified small business concerns in obtaining certain bid, payment, or performance bonds that are otherwise not obtainable is available through the Small Business Administration (SBA) (Small Business Administration). For information concerning SBA's surety bond guarantee assistance, contact your SBA District Office.
III.D. Information Concerning the Disclosure of Solicitation Results
This acquisition is being conducted under the provisions of FAR Part 15 as a negotiated procurement. In accordance with FAR 3.104 and FAR 15.207, after receipt of proposals, no information regarding the identity of those submitting offers, the number of offers received, or the information contained in such offers will be made available until after award except as provided by FAR 15.503.
III.E. Affirmative Procurement Program
GSA has implemented an Affirmative Procurement Program (APP) intended to maximize the use of recovered materials, environmentally preferable, and bio-based products. Offerors should familiarize themselves with the requirements for using and reporting on the use of such materials in performance as set forth in the Agreement.
III.F. Notice Concerning Preparation of Proposals
Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.
III.G. Bond Requirements
If a bid guarantee is required to be submitted with your offer, any contract awarded will require a performance bond and payment bond as specified in the Agreement. Offerors who utilize individual sureties should note the requirement for a certified, audited, financial statement for each person acting as an individual surety under clause FAR http://www.sba.gov/ http://www.sba.gov/
52.228-1 Bid Guarantee and the requirements of clause FAR 52.228-11 Pledge of Assets.
III.H. Contractor Performance Information
(1) Evaluating Contractor Performance: The General Services Administration is using the Contractor Performance Assessment Reporting System (CPARS) module as the secure, confidential, information management tool to facilitate the performance evaluation process. CPARS enables a comprehensive evaluation by capturing comments from both GSA and the contractor. The website for CPARS is Contractor Performance Assessment
Completed CPARS evaluations may then be used by Federal acquisition community for use in making source selection decisions. CPARS assists acquisition officials by serving as the single source for contractor past performance data.
(2) CPARS Registration: Each award requiring an evaluation must be registered in CPARS. The contractor will receive several automated emails. Within thirty days of award, the contractor will receive an email that contains user account information, as well as the applicable contract and order number(s) assigned. Contractors will be granted one user account to access all evaluations.
(3) Contractor CPARS Training: Contractors may sign up for CPARS training. A schedule of classes will be posted to the CPARS training site (CPARS Training) and updated as needed.
(4) Contractor Representative (CR) Role: All evaluations will be sent the Contractor Representative (CR) named on your award. The CR will be able to access CPARS to review and comment on the evaluation. If your CR is not already in the CPARS system, the contracting officer will request the name and email address of the person that will be responsible for the CR role on your award.
Once an evaluation is ready to be released the CR will receive an email alerting them the evaluation is ready for their review and comment. The email will indicate the time frame the CR has to respond to the evaluation; however, the CR may return the evaluation earlier than this date.
GSA shall provide for review at a level above the contracting officer (i.e., contracting director) to consider any disagreement between GSA and the contractor regarding GSA’s evaluation of the contractor. Based on the review, the individual at a level above the contracting officer will issue the ultimate conclusion on the performance evaluation.
Copies of the evaluations, contractor responses, and review comments, if any, will be retained as part of the contract file.
III.I. Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information http://www.cpars.gov/ http://www.cpars.gov/ https://www.cpars.gov/lc.htm
Certain information contained in the Solicitation Documents may have been designated as Controlled Unclassified Information (CUI) building information. With respect to such information, Offerors shall agree to the terms for receipt of such information, as set forth in the provision “Administrative Matters” in Section III of the Agreement, as a condition of receipt of such information.
IV. FAR/GSAR Solicitation Provisions
IV.A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 (Sep 2023)
(a) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101–29, and copies of Federal specifications, standards, and product descriptions can be downloaded from the ASSIST website at https://assist.dla.mil.
(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained from the ASSIST website identified in paragraph (a) of this provision.
(End of provision)
IV.B. FAR 52.216-1 Type of Contract (APR 84) The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
IV.C. FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work (MAY 14)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.
https://assist.dla.mil/ https://assist.dla.mil/ https://assist.dla.mil/
IV.D. Buy American Requirements
FAR 52.225-10 Notice of Buy American Requirement-Construction Materials (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American-Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested-https://www.acquisition.gov/far/part-52#FAR_52_225_9 https://www.acquisition.gov/far/part-52#FAR_52_225_9 https://www.acquisition.gov/far/part-52#FAR_52_225_9 https://www.acquisition.gov/far/part-52#FAR_52_225_9 https://www.gsa.gov/forms-library/solicitation-offer-and-award-construction-alteration-or-repair https://www.acquisition.gov/far/part-52#FAR_52_225_9 https://www.acquisition.gov/far/part-52#FAR_52_225_9
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
IV.E. Buy American Exceptions
For Buy American exceptions, if any, see the applicable Buy American clause in Section IV of the Agreement
IV.F. FAR 52.233-2 Service of Protest (SEP 06)
(a) Protests, as defined in section 31.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from the Contracting Officer at the address provided in the provision “Receipt of Offers” in Section I (General Information).
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
IV.G. FAR 52.252-1 Solicitation Provisions Incorporated by Reference
(FEB 98)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this address:
Federal Acquisition Regulation
(End of Provision)
The following provisions are incorporated by reference:
NUMBER TITLE DATE
52.204-7 System for Award Management NOV 2024 52.204-22 Alternative Line Item Proposal JAN 2017
52.214-34 Submission of Offers in the English Language
APR 1991
52.215-16 Facilities Capital Cost of Money JUN 2003
NUMBER TITLE DATE
52.204-7 System for Award Management NOV 2024 52.236-28 Preparation of Proposals -
Construction
OCT 1997
IV.H. GSAR 552.102 Incorporating Provisions and Clauses
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.
IV.I. GSAR 552.252-5 Authorized Deviations in Provisions (Nov 2021)(DEVIATION
FAR 52.252-5)
(a) Deviations to FAR provisions. This solicitation identifies any authorized deviation to a Federal Acquisition Regulation (FAR) (48 CFR chapter 1) provision by—
(1) The addition of “(DEVIATION)” after the date of the FAR provision when an authorized deviation to a FAR provision is being used, and
(2) The addition of “(DEVIATION FAR (provision number))” after the date of the GSAR provision when a GSAR provision is being used in lieu of a FAR provision.
(b) Deviations to GSAR provisions. This solicitation identifies any authorized deviation to a General Services Administration Acquisition Regulation (GSAR) (48 CFR chapter
5) provision by the addition of “(DEVIATION)” after the date of the provision.
(c) “Substantially the same as” provisions. Changes in wording of provisions prescribed for use on a “substantially the same as” basis are not considered deviations.
V. Instructions and Clauses
V.A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition (NOV 2021)
(a) Definitions. As used in this provision-
Discussions are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer’s discretion, result in the offeror being allowed to revise its proposal.
In writing, "writing," or "written" means any worded or numbered expression that can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
Proposal modification is a change made to a proposal before the solicitation’s closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
Proposal revision is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
Time, if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(c) Submission, modification, revision, and withdrawal of proposals. (1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(2) The first page of the proposal must show–
(i) The solicitation number;
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation; and
(v) Name, title, and signature of person authorized to sign the proposal.
Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.
(3) Submission, modification, revision, and withdrawal of proposals. (i) Offerors are responsible for submitting proposals, and any modifications or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(ii) (A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is "late" and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and-
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government’s control prior to the time set for receipt of offers; or
(3) It is the only proposal received.
(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.
(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.
(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).
(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall-
(1) Mark the title page with the following legend:
This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed-in whole or in part-for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of-or in connection with-the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data https://www.acquisition.gov/far/52.215-5#FAR_52_215_5 https://www.acquisition.gov/far/52.225-17#FAR_52_225_17 subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
(2) Mark each sheet of data it wishes to restrict with the following legend:
Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
(f) Contract award. (1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.
(2) The Government may reject any or all proposals if such action is in the Government’s interest.
(3) The Government may waive informalities and minor irregularities in proposals received.
(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)).
Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.
(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government’s best interest to do so.
(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items.
https://www.acquisition.gov/far/15.306#FAR_15_306
Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.
(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.
(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:
(i) The agency’s evaluation of the significant weak or deficient factors in the debriefed offeror’s offer.
(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.
(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.
(iv) A summary of the rationale for award.
(v) For acquisitions of commercial products, the make and model of the product to be delivered by the successful offeror.
(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.
VI. Method of Award
VI.A. Evaluation of Offers
(1) The Government will award a contract resulting from this Solicitation to the responsible Offeror whose offer conforming to the Solicitation will be the best value to the Government, Total Evaluated Price and other factors considered. In addition to Total Evaluated Price, the following non-price factors shall be used to evaluate offers:
(a) Experience in Providing Construction Services on Similar Projects
(b) Past Performance in Providing Construction Services on Similar Projects
(2) Non-Price Factors, when combined, are significantly more important than Total Evaluated Price.
(3) Tradeoff Information- A tradeoff process is appropriate when it may be in the best interest of the Government to consider award to other than the lowest priced offeror or other than the highest technically rated offeror. This process permits tradeoffs among cost or price and non-cost factors and allows the Government to accept other than the lowest priced proposal. The perceived benefits of the higher priced proposal shall merit the additional cost.
VI.B. Determination of Responsibility In order to be considered responsible, an Offeror must demonstrate that it meets the requirements of FAR 9.104-1. The Contracting Officer's determination of an Offeror's responsibility or non-responsibility may be based upon any information obtained by the Contracting Officer, and is independent of the evaluation of offers set forth herein.
VI.C. Price Reasonableness The proposed prices will be evaluated for reasonableness.