This document is a template for a Request for Information form related to federal construction contracts. It outlines the standard information to be included when submitting an RFI, such as the contract and project numbers, drawings, specifications, cost impact, response and concurrence due dates. The form is intended to provide an efficient mechanism for contractors to request information from the government. It notes that submitting an RFI does not authorize work and that contractors should follow the proper procedures if they consider the response a change in scope or time.

The related federal opportunity is a solicitation from the Ohio Army National Guard for their FY23 OHARNG CJAG Demolition Project. No other details are provided about the required products or services.

View the file

Other files

File Type Posted
W91364-23-B-0005-0002 Ack.pdf PDF
W91364-23-B-0005 Q-A.docx DOCX document
W91364-23 B 0005 CJAG Demo 2023 MFR.pdf PDF
limited-asbestos-roof-survey-grp8-bldg-23jan2018.pdf PDF
grp-8-white-painted-exterior-facia-trim-doors-feb2018.pdf PDF
ABS_GA_63-838_02_99F.pdf PDF
crjmtc_hazassmt_sep2018.pdf PDF
ABS_GA_61-851_02_99F.pdf PDF
W91364-23-B-0005 Q-A.docx DOCX document
ABS_GA_69-853_02_99F.pdf PDF
ABS_GA_61-852_02_99F.pdf PDF
ABS_GA_69-854_02_99F.pdf PDF
FY23 Demo-Pav -Site Visit Sign In 2023.08.22.pdf PDF
FY23 Demo - Site Visit Sign In 2023.08.15.pdf PDF
W91364-23-B-0005 Q-A.docx DOCX document
OHARNG Sol W91364-23-B-0005-0002.pdf PDF
W91364-23-B-0005 Q-A.docx DOCX document
Wage Determiation.pdf PDF
WageDetermination-.pdf PDF
Instructions to Bidders.docx DOCX document
OHARNG Sol W91364-23-B-0005-0001.pdf PDF
FY23 Demo PWS 3922013.pdf PDF
OHARNG Sol W91364-23-B-0005.pdf PDF
Bid Form CJAG Demo.docx DOCX document
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT NUMBER:

REQUEST FOR INFORMATION

RFI NUMBER:

PROJECT NUMBER / CONTRACT TITLE:

PRIME CONTRACTOR: SUBCONTRACTOR/SUPPLIER:

SUBJECT/TITLE OF RFI:

DRAWING(S): DETAIL(S): SPECIFICATION: CPM ACTIVITY #:

PHONE: FAX: COST IMPACT:

YES NO

DATE SUBMITTED: RESPOND BY:

INFORMATION REQUESTED

By: Date:

RESPONSE

By: Date:

COR Concurrence: Date:

CO Concurrence: Date:

The RFI system is intended to provide an efficient mechanism for responding to contractor’s request for information ONLY. This system DOES NOT authorize the contractor to proceed with work - to do so, the contractor proceeds at his own risk. If the contractor considers the RFI response a change in conditions, scope of work or contract time, submit proposal request in accordance with FAR Clause 52.243-4 Changes or FAR Clause 52.236-2 Differing Site Conditions, as applicable.

CONTRACT NUMBER:
RFI NUMBER:
PROJECT NUMBER CONTRACT TITLE:
PRIME CONTRACTOR:
SUBCONTRACTORSUPPLIER:
SUBJECTTITLE OF RFI:
DRAWINGS:
DETAILS:
SPECIFICATION:
CPM ACTIVITY:
PHONE:
FAX:
COST IMPACT: Off
DATE SUBMITTED:
RESPOND BY:
INFORMATION REQUESTED:
By:
Date:
RESPONSE:
By_2:
Date_2:
COR Concurrence:
Date_3:
CO Concurrence:
Date_4:

File details come from the government source that posted it. Updated .