OHARNG Sol W91364-23-B-0005.pdf

PDF 666 KB Posted

Attached to
FY23 OHARNG CJAG Demolition Project
Solicitation number
W91364-23-B-0005
Issued by

About this file

This solicitation is for a firm fixed price demolition contract for the Ohio Army National Guard (OHARNG). The scope of work involves demolishing multiple building facilities at the Camp James A. Garfield Joint Military Training Center in Ravenna, Ohio, including hazardous material abatement. The base bid consists of demolishing eleven buildings in Area 3. There are also six optional locations that may be exercised, including demolishing additional buildings in Areas 1 and 8. Offerors must provide all labor, materials, equipment, and supervision to complete the demolition work in accordance with the statement of work and specifications. The period of performance is 365 days from notice to proceed. This is a total service-disabled veteran-owned small business set-aside with a NAICS code of 237310 and size standard of $39.5 million. The disclosure of magnitude is between $1-5 million. Offers are due by 11:00 AM on September 7, 2023 and will be evaluated for award based on lowest price technically acceptable.

View the file

Other files

File Type Posted
W91364-23-B-0005-0002 Ack.pdf PDF
W91364-23-B-0005 Q-A.docx DOCX document
W91364-23 B 0005 CJAG Demo 2023 MFR.pdf PDF
limited-asbestos-roof-survey-grp8-bldg-23jan2018.pdf PDF
grp-8-white-painted-exterior-facia-trim-doors-feb2018.pdf PDF
ABS_GA_63-838_02_99F.pdf PDF
crjmtc_hazassmt_sep2018.pdf PDF
ABS_GA_61-851_02_99F.pdf PDF
W91364-23-B-0005 Q-A.docx DOCX document
ABS_GA_69-853_02_99F.pdf PDF
ABS_GA_61-852_02_99F.pdf PDF
ABS_GA_69-854_02_99F.pdf PDF
FY23 Demo-Pav -Site Visit Sign In 2023.08.22.pdf PDF
FY23 Demo - Site Visit Sign In 2023.08.15.pdf PDF
W91364-23-B-0005 Q-A.docx DOCX document
OHARNG Sol W91364-23-B-0005-0002.pdf PDF
W91364-23-B-0005 Q-A.docx DOCX document
Wage Determiation.pdf PDF
WageDetermination-.pdf PDF
Instructions to Bidders.docx DOCX document
OHARNG Sol W91364-23-B-0005-0001.pdf PDF
FY23 Demo PWS 3922013.pdf PDF
RFI-Form.pdf PDF
Bid Form CJAG Demo.docx DOCX document
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W9136423B0005 08-Aug-2023

b. TELEPHONE NUMBER

614-336-7465

8. OFFER DUE DATE/LOCAL TIME

11:00 AM 07 Sep 2023

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W913649. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

HERBERT L. BROWN

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

0011952335

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESS

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

USPFO FOR OHIO

2825 WEST DUBLIN-GRANVILLE ROAD

COLUMBUS OH 432352788

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE W917DP 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

W8BR OHARNG ELEMENT, JF HQ

ARNG STAFF ELEMENT, JOINT FORCE HEA

3990 EAST BROAD STREET

BLDG 5

COLUMBUS OH 43213-1152

TEL: 614-336-7235 FAX:

FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

X 8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$19,000,000

NAICS:

238910

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF73

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W9136423B0005

Section SF 1449 - CONTINUATION SHEET

ATTACHMENT A

FAR 52.212-1 ADDENDUM

INSTRUCTIONS TO BIDDERS

OHARNG Sol# W91364-23-B-0005 Camp James A. Garfield Joint Military Training Center (CJAG) FY23 Demolition Project

The Ohio Army National Guard (OHARNG) has a requirement to award a firm fixed price (FFP) contract for the demolition of multiple building facilities throughout Area 3 throughout of the Camp James A. Garfield Joint Military Training Center (CJAG); located at 8451 State Route 5 Ravenna, OH. 44266. This demolition service will include hazard material removal and abatement. The base bid will consist of eleven buildings (BA400, BA401, BA402, BA 403, BA404, BA405, BA406, BB407, BB409, BB410, BB413 BC414, BC415, BC416, BC418, BC419 and BC420).

There will be six additional option locations (outlined in the SOW). The number of optional locations that will be exercised at the time of award. The optional locations will be dependent on available funds.

Alternate Options:

There are six additional demolition site locations outlined in the statement of work. Each of the individual locations will be individually priced as optional line items and will be exercised at the time of award.

Option# 1: Demolition of TT Barracks Building AB157 Option# 2: Demolition of Controlled Humidity Warehouse Building 838 Option# 3: Demolition of Controlled Humidity Warehouse Building 854 Option# 4: Demolition of Controlled Humidity Warehouse Building 853 Option# 5: Demolition of Controlled Humidity Warehouse Building 852 Option# 6: Demolition of Controlled Humidity Warehouse Building 851

This solicitation is a Total Veterans Service-Disabled Small Business Set-Aside NAICS: 237310 Small Business Size Standard $39,500,000.00: Disclosure of Magnitude is between $1,000,000.00 and $5,000,000.00

The award will be made to the responsible bidder with the lowest price technically acceptable in accordance with the criteria set forth in the SOW.

Site Visit Information: There will be two scheduled site visits.

Site Visit 1: August 15, 2023, at 9:00 am Site Visit 2: August 22, at 9:00 am Potential Contractors will be escorted to the construction sites.

Notification to gain access to CJAG must be made at 24 hours prior to arrival. Please contact Mr. Grant Stoner to schedule access:

Phone: 614-336-6580 Email: grant.m.stoner.mil@army.mil Bid Opening Information:

Bids will need to be submitted in a sealed envelope at CJAGJMTC Building 1068, 8451 State Route 5 Ravenna, Ohio 44266 on September 7th, 2023, at 11:00 am Bids may be submitted in person only.

Questions/Answers All questions concerning this solicitation must be submitted to the contract office at herbert.l.brown24.civ@army.mil or Bradley.a.wahl.civ@army.mil no later than August 25th, 2023.

Answers to all questions will be posted on SAM.gov no later than August 31st, 2023.

ATTACHEMENT B

TABLE OF CONTENTS

ARTICLE 1 - PROPOSAL GENERAL

INFORMATION

ARTICLE 2 - DESCRIPTION OF

SITE

ARTICLE 3 - STATEMENT OF WORK

ARTICLE 4 - GENERAL

ARTICLE 5 - REFERENCES

ARTICLE 6 - ENVIRONMENTAL PROCEDURES 25 JAN 2018

CAMP RAVENNA WASTE MANAGEMENT GUIDELINES

ARTICLE 1 - CJAG WASTE MANAGEMENT

GUIDELINES

CJAG WEEKLY NON HAZARDOUS & HAZARDOUS WASTE SHEET

CONSTRUCTION/DEMOLITION DIVERSION AND WASTE DISPOSAL FORM…….

ENVIRONMENTAL PROCEDURES

25JAN2018………

ENVIRONMENTAL WORK PLAN GUIDE

. 46

PROJECT SITE & MAIN GATE

PROJECT LOCATION MAP

AREA 3 SITE

TTB BARRACKS BUILDING AB157

AREA 8 BUILDINGS

MEMORANDUM FOR RECORD (MFR)

ARTICLE 1 - PROPOSAL GENERAL INFORMATION

1.1 Proposal Project Title:

1.1.1 PN 3922013 Camp James A. Garfield Joint Military Training Site (CJAGJMTC) Base Wide Demolition – FY

1.2 Project Scope:

1.2.1 The Scope of Service is for the demolition of multiple facilities to include Hazardous Materials abatement.

Contractor will furnish all labor, materials, tools, equipment, supplies, transportation, supervision, inspections and testing in strict accordance with the Statement of Work, Requirements, and Specifications described within this proposal necessary to ensure that the specified demolition of the Base Bid Area 3 Buildings BA400, BA401, BA402 BA 403, BA404, BA405, BA406, BB407, BB409, BB410, and BB413, BC414, BC415, BC416, BC418, BC419 and BC420. Options to the Bid will include Area 1 Building AB157 TT Barracks and Area 8 Controlled Humidity Warehouse Buildings 838, 851, 852, 853, and 854. Work activities shall include but is not limited to properly removing and disposing of all structures, abatement and disposal of hazardous materials/waste, removal of trash, rubbish, waste, basement walls, foundations, footers, contaminated water and all exterior parking areas, sidewalks, and underground utilities within 10 foot of the structure.

1.3 Recommended Performance Period:

1.3.1 365 Days from Notice to Proceed

1.4 Base Bids Base Bid

1.4.1.1 Base Bid — Demolition of Buildings BA400, BA401, BA402, BA 403, BA404, BA405, BA406, BB407, BB409, BB410, BB413 BC414, BC415, BC416, BC418, BC419 and BC420.

1.5 Options

1.5.1 Option 1—Demolition of TT Barracks Building AB157.

1.5.2 Option 2—Demolition of Controlled Humidity Warehouse Building 838.

1.5.3 Option 3— Demolition of Controlled Humidity Warehouse Building 854.

1.5.4 Option 4— Demolition of Controlled Humidity Warehouse Building 853.

1.5.5 Option 5— Demolition of Controlled Humidity Warehouse Building 852.

1.5.6 Option 6— Demolition of Controlled Humidity Warehouse Building 851.

ARTICLE 2 - DESCRIPTION OF SITE

2.1 Project Location:

2.1.1 Project site is located on the Camp James A. Garfield Joint Military Training Center (CJAGJMTC), 8451 State Route 5, Ravenna, Ohio 44266.

2.1.1.1 Area 3 Buildings BA404, BA405, BA406, BB407, BB409, BB410, BB413, BA400, BA401, BA402 BA 403, BC414, BC415, BC416, BC418, BC419 and BC420. The buildings are a concrete and block foundation and structure with a steel framed transit roof and transit interior ceiling.

ARTICLE 3 - STATEMENT OF WORK

3.1 Statement of Work:

3.1.1 DESCRIPTION OF DEMOLITION REQUIREMENTS. The contractor shall provide all management, tools, supplies, equipment and labor necessary to ensure that the specified demolition performed at the Camp James A Garfield Joint Military Training Center, shall be in accordance with applicable federal, state, local, building, environmental and safety codes and regulations.

3.1.2 DOCUMENTATION AND SITE INSPECTION:

3.1.2.1 The building demolition and debris removal process will not begin until:

.1 Submittal and approval of all required regulatory agency notifications (to include an Ohio Environmental Protection Agency (EPA) Notification of Demolition and Renovation Form), Storm Water Pollution Prevention Plan (SWP3) and permit, and Contractors environmental work plan .2 The facility has been inspected by Environmental Office, the Contractor, Contracting Officer Representative (COR) and Contracting Authority, and all are in agreement, that all environmental protections are in-place, confirmation that no federally listed species and/or nesting birds are present and that all connecting utilities are shut down, disconnected, or isolated to the facility in a manner satisfactory for demolition to begin.

3.1.3 RESTRICTIVE ACCESS WARNING BARRIERS. The contractor is required within ten (10) days of the notice to proceed to provide restrictive access warning barriers around the facilities scheduled for abatement and demolition. The barriers shall have posted warnings against unauthorized entry and be placed around the site perimeter to provide reasonable, safe clearance, and restricted access on all sides (where practical) for equipment movement, demolition of existing structures, components, and equipment and for the entry/exit of trucks (recommend 50’ x 50’ secure staging/loading area) hauling debris or equipment. The restrictive access barrier will be installed prior to any demolition or salvage efforts within/around the facility. The area within the restrictive warning barriers as well as within the facility being demolished/constructed is designated as a ‘Hard Hat’, “PPE”, and “Authorized Personnel Only” zone. Signs shall be posted indicating limited/controlled access (every 100- 150’), hard hat and PPE zone (at entrances), all permits/notices and supervisory personnel’s names and contact numbers shall be posted at the primary entry/exit, shall be protected from weather, and shall remain posted until final acceptance of the completed project.

3.1.4 SALVAGE & RELOCATABLE ITEMS AND BUILDING CONTENTS: Currently, some of the buildings have contents and at the time of demolition and contractor acceptance of the building may still have some contents.

All salvageable items and building contents shall be removed prior to the destruction of any portions of the facility unless the items shall be extricated from imbedded construction within the facility that renders the items unusable.

Items designated as salvageable or building contents shall be stored, stacked, or piled and removed from the site on a weekly basis. The OHARNG retains the right to claim any salvageable, building contents and relocatable items. A list of these items shall be presented to the Project Manager for approval before removal from the site. Any items not salvaged and kept by the OHARNG will be the responsibility of the contractor and shall be disposed of following the OHARNG Environmental Procedures.

3.1.5 ABATEMENT: The Contractor is required to follow all requirements set forth in the Environmental Work Plan which will be developed by the Contractor and reviewed and approved by the OHARNG prior to the start of demolition activities. The Contractor will coordinate access and staging locations for purposes of abatement and equipment delivery with site personnel prior to any demolition work. The Contractor will provide the Project Manager detailed drawings/information indicating specific location(s) of and material type(s) requiring abatement for the entire facility, approximate time required for abatement, and personnel listing/contact information and licensure prior to starting work. All environmental hazards and substrates identified in the Pre-Demolition Environmental Hazards Assessment, and Memorandum for Record shall be properly removed, handled, containerized, managed and disposed of in accordance with applicable Federal, State, Army, and local regulations as specified in the Environmental Work Plan. The Environmental Work Plan shall include the contractor’s methods of abating the materials referenced in the Memorandum for Record that is included in Appendix J. If additional environmental hazards are identified during demolition, the contractor shall stop work and consult with the Environmental Office and the State Project Manager. Once a course of action is agreed upon the Contractor will properly remove, characterize and dispose of the hazard in accordance with federal, state, Army and local regulations. The Contractor is required to inspect all waste stored onsite on a weekly basis and document it on the OHARNG Waste Inspection Form. The form shall be submitted to the Environmental Office on a weekly basis. All waste profiles and hazardous and TSCA waste manifests shall be signed by a representative of the OHARNG Environmental Office prior to waste being shipped offsite. All municipal waste, hazardous waste, asbestos waste, and construction and demolition waste manifests must be signed by an owner representative. The contractor is required to track all wastes and recyclables on the OHARNG Demolition Diversion and Waste Disposal Form. The form, along with all waste tickets and manifests, shall be turned in to the OHARNG Environmental Office every two weeks. Additional details regarding Environmental Requirements are provided in Appendix D.

3.1.6 DISPOSAL OF CONTAMINATED WATER: Any sump water encountered within the buildings must be pumped out and disposed of at a licensed treatment facility.

3.1.7 APPLIANCES: Remove and dispose of appliances and other items that may contain refrigerants in accordance with 40 CFR, Part 82.

3.1.8 DEMOLITION OF WALLS, CEILINGS, FLOORS, AND ROOFING: The Contractor will demolish the walls, ceilings, floors, and roofing within the designated footprint of the facility (demolition area). All concrete and brick/block material shall be hauled off site and the contractor will provide the OHARNG with documents showing the concrete was crushed for recycling/reuse. All materials to be removed will be adequately wetted prior to removal to control dust and spread of demolished materials and to comply with Environmental Protection Agency (EPA) clean air standards. The Contractor shall bring water in for use on the Project (from a municipal source). All storm drains in the area adjacent to the facility shall have filtration/protection to prevent infiltration of dirt/debris into the storm drainage system. All removed materials shall be transported to a designated disposal facility or recycling center on the same or following day the material is demolished/removed from the building. The Contractor is responsible for the proper disposal/discharge of any standing water in accordance with applicable federal, State, local and Army regulations. The Contractor shall provide details regarding sampling, characterization and disposal/discharge of standing water in the Environmental Work Plan to be submitted for the project.

3.1.9 FOOTINGS, FOUNDATIONS AND CONCRETE PADS: All non-hazard, unpainted brick, block, and concrete used for footings, foundations, pads, supports, and walls shall be removed. Any concrete suitable for recycling shall be cleaned of all rebar or other metals and crushed. All recycling shall be done off site, the contractor will provide the OHARNG with documents showing the concrete was crushed for recycling/reuse.

3.1.10 UTILITIES: The Contractor is responsible for coordinating and ensuring utility disconnections. The Contractor will remove all wiring, conduit, piping, and connectors for the utilities connected to facility back to their respective source/main point of disconnection.

3.1.11 CONCRETE SLABS AND PARKING AREAS: The Contractor will remove all concrete slabs, asphalt, surface obstructions, masonry slabs, and appurtenances. Any concrete suitable for recycling shall be cleaned of all rebar or other metals and crushed. All recycling shall be done off site, the contractor will provide the OHARNG with documents showing the concrete was crushed for recycling/reuse.

3.1.12 RETAINING WALLS: Retaining walls or curbs near the perimeter will be removed in their entirety including foundations. Any concrete suitable for recycling shall be cleaned of all rebar or other metals and crushed.

All recycling shall be done off site, the contractor will provide the OHARNG with documents showing the concrete was crushed for recycling/reuse.

3.1.13 BARRIERS and SIGNAGE: Fences, guardrails, bumpers, signs, and similar facilities will be completely removed from the site. All support posts will be pulled out or dug up as to be entirely removed.

3.1.14 VEGETATION: The Contractor will remove all dead trees, trees identified for removal, stumps, all trees which are determined not to be an asset to the property by OHARNG, bushes, vegetation, brush and weeds, whether standing or falling, unless stated otherwise by the Project Manager or COR in writing. The vegetation clearing shall be within a 100 foot diameter of the Building site. This shall include any clearing needed to access the Buildings on the old Rail Beds outside of the ditch lines. The Contractor will protect all trees not removed from damage by the demolition operation. Tree cutting restrictions are in place from 1 April to 30 September as indicated in General Environmental Procedures. Final disposition of trees and vegetation removed must be discussed in the Environmental Work Plan and coordinated with the Environmental Office.

3.1.15 PARTIALLY BURIED OBJECTS: All piping, posts, reinforcing bars, anchor bolts, railings and other partly buried objects protruding from the ground shall be removed within a 100 foot diameter of each building. The remaining void shall be filled with soil and compacted in accordance with this statement of work.

3.1.16 SITE WORK: Comply with ODOT standards for backfilling and compacting procedures for soils used to fill. Fill material for basements, crawl spaces, depressions, voids, etc. shall conform to the definition of satisfactory soil material as defined in AASHTO M 145, Soil Classification Groups A-1, A-2-4, A-2-5 and A-3. All required “clean” fill material shall be brought from off site at the Contractors expense. The backfill source must be identified in the Work Plan and approved by the OHARNG. The OHARNG may require sampling and analysis for contaminants to confirm backfill is clean. In addition, fill material shall be free from roots and other organic matter, trash, debris, frozen materials and stones larger the 1 inch in any dimension. Proposed fill material shall be sampled and tested by an approved soil testing laboratory. Place backfill and fill materials in layers not more than 8 inches in loose depth for material compacted by heavy compaction equipment and not more than 4 inches in loose depth for material compacted by hand-operated tampers. Grade the area to provide for positive drainage for the entire site including removal of excess material if needed to maintain the site appearance if requested by the OHARNG. The Contractor will also include grading of the existing rail beds and Randall Road from Smalley to Remalia for access to the demo sites using 3 inch layer of ODOT 304 as a final cover.

3.1.17 Compaction Testing: Backfill shall be compaction tested at each lift, and compaction results of each lift shall be recorded and reported on the day of compaction, and no further lifts may be completed until the previous lifts compaction results are approved by the Project Manager.

3.1.17.1 All testing and laboratory analyses shall be performed by a qualified independent laboratory (conforming to American Society for Testing and Materials standards) selected and paid for by the Contractor.

3.1.17.2 Compact soil materials to not less than the following percentages of maximum dry unit weight according to ASTM D 698: Under turf or unpaved areas, re-compact top 6 inches below subgrade and compact each layer of backfill or fill soil material at 92 percent.

3.1.17.3 The Contractor shall notify Project Manager when testing is to be performed and must report the results of testing immediately to Project Manager.

3.1.18 Type of compaction: The use of Heavy compaction equipment or hand-operated tampers shall be recorded and reported the day of compaction and testing.

3.1.19 SEEDING: The Contractor will follow the seed mix requirements in Appendix D – OHARNG Environmental Procedures.

3.1.20 PERMITTING: A General Construction Storm Water Permit will be required for this project. A permit shall be obtained.

3.1.21 CONTRACTOR QUALIFICATIONS:

.1 Contractor will have a minimum of 5 years of experience.

.2 The contractor shall provide trained and qualified personnel resources, materials and equipment to fulfill the requirements of this contract.

3.1.22 WARRANTY:

3.1.22.1 All hardware and workmanship will be warranted for one year from installation. The warranty shall cover all materials and labor necessary to resolve any problems resulting from defects in material or labor. Warranty will not cover hardware which has been misused, abused or damaged by acts of God.

3.1.23 SCHEDULING AND INSTALLATION:

3.1.23.1 The contractor will provide coverage at the specified site from 7:00 a.m. to 5:00 p.m. MON through FRI, excluding weekends and Federal holidays.

3.1.24 All listed products are suggested items. The contractor shall provide a proposed item list/submittal that is equal or better than the listed item. All items must be approved by the end user prior to purchase and installation.

3.1.24.1 The contractor is free to propose alternate configurations and products as long as they are compatible with the current suggestions.

3.1.25 Contractor will provide 5% shelf stock (Not Applicable).

3.2 Submittals Required

3.2.1 Prior to start of work.

3.2.1.1 Project Schedule

3.2.1.2 Environmental Work Plan (Appendix E).

3.2.1.3 Demolition and Engineering Work Plan if needed.

3.2.1.4 Paying all fees and acquiring all applicable permits or regulatory approvals associated with the work to be performed.

3.2.1.5 Approval of all materials to be used.

3.2.2 Site Supervisor Resume.

3.2.3 Warranty Documents at completion of the project.

3.2.4 Closeout Documents at completion of the project.

ARTICLE 4 - GENERAL

4.1 General Requirements:

4.1.1 Before submitting a Proposal, Contractor must:

4.1.1.1 Examine all Contract Documents thoroughly.

4.1.1.2 Visit the site to become familiar with local conditions that may in any manner affect cost, progress of or performance of the work.

4.1.1.3 Be proficient with federal, state, local, ordinances, rules and regulations that may in any manner affect cost, progress or performance of the work.

4.1.1.4 Study and carefully correlate Contractor’s observations with the Proposal Documents. Request clarification via means of a RFI prior to submitting proposal.

4.2 Field Inspection Visit:

4.2.1 The Contractor shall thoroughly examine existing field conditions affecting the work.

4.2.2 The Contractor shall verify all measurements affecting the work and be responsible for the same.

4.3 Requests for Information (RFIs):

4.3.1 Immediately on discovery of the need for information/interpretation of the Contract Documents, and if not possible to request interpretation at Project Meeting, prepare and submit an RFI. Allow 10 (ten) working days for Governments Response (does not apply during proposal period).

4.4 Work Scheduling:

4.4.1 Normal base work hours for the Contractor will be between the hours of 7:00 am through 5:00 pm, excluding Saturdays, Sundays, and State and Federal Holidays. The normal work hours for National Guard personnel are 7:00 am to 5:00 pm, Monday through Friday. If the Contractor desires to work during periods other than above, Contractor must notify the Contracting Authority 5 working days in advance of Contractors intention to work during other periods to allow assignment of additional inspection forces and for notification of fire, security and safety.

When the Contracting Authority determines that they are reasonable, Contracting Authority may authorize the Contractor to perform work during periods other than normal duty hours/days. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the Contractor, the actual cost of the inspection, at overtime rates, will be charged to the Contractor and will be deducted from the final payment of the Contract amount.

4.4.2 The following Federal/State legal Holidays are observed by this site:

4.4.2.1 New Year’s Day 1 January

4.4.2.2 Martin Luther’s King’s Birthday Third Monday of January

4.4.2.3 President’s Day Third Monday of February

4.4.2.4 Memorial Day Last Monday of May

4.4.2.5 Juneteenth-19 June

4.4.2.6 Independence Day 4 July

4.4.2.7 Labor Day First Monday in September

4.4.2.8 Columbus Day Second Monday in October

4.4.2.9 Veteran’s day 11 November

4.4.2.10 Thanksgiving Day Fourth Thursday in November

4.4.2.11 Christmas Day 25 December

.1 Note: Any of the above Holidays falling on a Saturday will be observed the preceding Friday, holidays falling on a Sunday will be observed on the following Monday.

4.4.3 Prior to commencing work on the job initially, resumption of work after prolonged interruption (7 calendar days or more) commencement of any warranty work, and upon completion of warranty work, the Contractor must notify the Contracting Authority. Notification should be by personal contact; however, advance notification may be by telephone, or in writing, and should be accomplished sufficiently in advance to allow scheduling of inspection forces. The above precautions are to ensure construction inspection and recording of work proceedings.

4.5 Government Facilities:

4.5.1 The Contractor is reminded that smoking within buildings on a Government facility is prohibited. A designated smoking area for employees, shall be established and will be coordinated will the authority having jurisdiction

(AHJ).

4.6 Utilities:

4.6.1 The Contractor shall be responsible for all coordination with Utility provider(s) or AHJ (Authority having Jurisdiction) before the adjustment, relocation or disconnection of existing utility structures, utility poles, lines, services, or other utility appurtenances located in or affected by construction. The OHARNG shall be notified of all communication between the Contractor and Utility provider(s) or Authority having jurisdiction.

4.6.2 The Contractor’s progress schedule shall include preliminary listing of all proposed shutdown dates. Every effort shall be made to make all shutdowns as brief as possible and as limited in extent as possible.

4.6.3 The Contractor shall provide notice to the OHARNG not less than 48 hours in advance of proposed utility interruptions.

4.6.4 The Contractor will provide an emergencies plan, with names of personnel to accomplish the repairs in the event of utility and/or communications emergencies.

4.7 Unauthorized Personnel:

4.7.1 The Contractor shall inform all personnel (including subcontractor and visiting supplier personnel) that access to areas outside of the immediate work area excluding, direct haul and access routes, and point of supply and storage, is prohibited. Circulation of said personnel will be limited to official business only.

4.8 Environmental:

4.8.1 The Contractor is required to follow the Ohio Army National Guard’s Environmental Procedures and to use the Ohio National Guard’s Waste Management Guidelines as specified within Appendix J.

4.9 Hazardous Material Usage:

4.9.1 The Contractor shall establish hazardous material (HM) storage and distribution system when HM is to be used. The Contractor HM Identification Form will be provided to the Contractor at or prior to the Preconstruction.

4.9.2 The Contractor shall maintain Contractor HM Identification Form for HM on the jobsite for inspection/verification.

4.9.3 The Contractor shall establish HM storage and issue location that complies with Federal, State, and Local environmental regulations. Materials issued shall be tracked for quantities used. Unused materials shall be inventoried and removed from the installation prior to close out of the Contract or expiration date of the HM.

Reports of material delivered, used and removed from the installation shall be submitted to the Contracting Authority monthly and prior to Contract Closeout.

4.9.4 The Contractor shall comply with all Federal, state and local environmental standards, including OSHA HazCom and COE 385-1-1.

4.9.5 The Contractor shall accompany the Contracting Authority and the Installation Environmental Manager (EM) on Project closeout inspection to ensure all used and unused HM has been removed from the installation. This requirement shall not be a punch list item and must be accomplished prior to the Government accepting beneficial occupancy of the facility or construction item.

4.9.6 Any material suspected of being hazardous that is encountered during performance of a project shall immediately be brought to the attention of the Contracting Authority, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Authority directs the Contractor to perform tests and/or the material is found to be of a hazardous nature requiring additional protective measures, a modification may be required, subject to equitable adjustment under the terms of the contract.

4.10 Pollution Abatement:

4.10.1 All work shall be performed in a manner minimizing pollution of air, water and land as required.

4.10.2 Transporting materials to and from the site shall be accomplished in a manner preventing materials or particles from becoming airborne. Earth materials shall be wetted or otherwise protected. Gravel, sand and concrete shall be contained within vehicles to prevent spillage. Tarpaulins must be fastened over load before entering surrounding streets. Removal of any materials dropped or blown off vehicles shall be the responsibility of the Contractor.

4.10.3 Stream beds, lakes, drainage ways, sanitary and storm sewers, etc., shall not be polluted by fuels, oils, bitumen, acids or other harmful materials. All HM shall be stored on secondary containment and storage areas must be identified in the Environmental Work Plan and SWPPP. The Contractor is required to inspect HM storage areas on a weekly basis and do a daily check of vehicles and equipment for leaks or maintenance issues in order to minimize or eliminate spills into the environment. Grading shall be accomplished to prevent from draining onto adjacent areas.

4.10.4 Flushing mortar, plaster or drywall materials shall not be disposed of on Government property. Water utilized for plastering or drywall equipment shall be disposed of in accordance with the instructions of the Contracting Authority, and under no circumstances shall water be disposed of in areas which are planted or scheduled to be planted.

4.11 Regulations:

4.11.1 The Contractor shall comply with all applicable Federal, State, Local, DOD, National Guard Bureau, Army and Installation regulations pertaining to safety, traffic control, fire prevention, and OHARNG Environmental Requirements.

4.11.2 The Contractor, employees, and subcontractors are subject to, and shall abide by and comply with all relevant statutes, ordinances, laws and regulations of the United States (including Executive Orders of the President) and any State (or other public authority now or hereafter in force). The Contractor agrees to observe and comply with all applicable State and Federal requirements regarding social security, workman’s compensation, unemployment insurance and any other matters concerning employment applicable to the performance of this Contract or rules, regulations, directions and order not inconsistent herewith as may from time to time be issued by the Government.

The unilateral act of any governmental body against any employee of the Contractor for the violation of a State or Federal law or regulation shall not excuse the Contractor from full compliance with the terms and conditions of this Contract.

4.11.3 The Contractor, employees, and subcontractors shall become familiar with and obey the regulations of the installation including fire, traffic, safety environmental and security regulations while on the military installation.

Those driving motor vehicles shall observe and obey all speed limits posted throughout the installation. Personnel should not enter restricted areas unless required to do so and only upon prior approval. All Contractor and subcontractor employees shall carry proper personal identification with them at all times.

4.11.4 Contractor’s equipment shall be conspicuously marked for identification and parked or placed within approved areas only, out of the way of driveways, emergency access roads, and traffic. The Contractor shall ensure that all of the facility where work is being performed is adequately protected. The Contractor shall comply with all security regulations imposed by the base/post commander against vandalism and theft.

4.12 Permits:

4.12.1 The Contractor is responsible for paying all fees and acquiring all applicable permits, inspections, licenses, capacity charges, tap fees, or regulatory approvals as required by the local authorities having jurisdiction. Depending upon the permit/notification, it may need to be issued in the OHARNG’s name. Coordination will be done with the OHARNG to determine this and the contractor will complete the application/notification for OHARNG signature and submit the application and associated fees. All permit submittals will be coordinated and approved by the OHARNG regardless who signs the application.

4.12.2 The Contractor shall secure all permits before proceeding with any work.

4.13 Burning of any material is strictly prohibited.

4.14 Safety Precautions and Programs:

4.14.1 OSHA Requirements:

4.14.1.1 The Contractor shall perform all work in the contract with due regard to the safety and health of the employees and of the public. The Contractor shall comply with 29 CFR 1926, Safety and Health Regulations for Construction, administered by the Federal Occupational Safety and Health Administration (OSHA) regarding the safety and protection of persons employed in construction and demolition work.

4.14.1.2 The Contractor shall develop and submit to the OHARNG a project specific Health and Safety Plan covering all aspects of demolition and construction operations proposed by the Contractor for this project. Said project specific Health and Safety Plan shall address all aspects of 29 CFR 1926 as related to the Contractor’s proposed operations.

4.14.1.3 Provide adequate barricades, railings, overhead protection, safety nets, etc., to safeguard the public and workman from debris. Provide proper signs and written notification to all personnel and property owners in immediate and surrounding affected areas, notifying them of duration of construction operations.

4.15 Method of Carrying on the work:

4.15.1 All work under the Contract shall be arranged and carried on in such a manner as to complete work in the least possible time.

4.15.2 Activities in the vicinity of this Project may be kept in full or partial operation during construction. The Contractor shall coordinate with the Contracting Authority and schedule construction activities.

4.16 Misplaced Materials:

4.16.1 Any material that is deposited elsewhere than areas designated as approved by the Contracting Authority shall be re-handled and deposited where directed. No payment will be made for re-handling such material.

4.17 Inspections and Tests:

4.17.1 Inspections and tests are for the sole benefit of the Government and shall not relieve the Contractor of the responsibility of providing quality control measures to ensure that the work strictly complies with the Contract Requirements. No inspection or test by the Government shall be construed as constituting or implying acceptance.

4.18 Quality Control/Tests:

4.18.1 Where work is required to be in conformity with Standard Specifications of the American Society for Testing Materials (ASTM), or with State/Federal Specifications or with specifications of highly recognized technical and trade organizations, but no tests are specifically stipulated in connection herewith, the Contractor shall furnish and pay for any tests or certification required by the OHARNG to verify that the proposed materials meet with the applicable requirements.

4.18.2 The Contractor shall submit a written certification from any recognized testing agency, adequately equipped and competent to perform such services, that the material or equipment has been tested and conforms to the standards, including the methods of testing used.

4.18.3 Wherever testing or analysis of material is required, such testing unless otherwise noted will be made at the Contractor’s expense.

4.18.4 Tests shall be made in accordance with the specified testing procedures and/or methods and otherwise as required to provide compliance with all Contract requirements. Tests shall be made by independent, commercial testing laboratories approved in writing by the Contracting Authority.

4.18.5 Results of all tests shall be recorded on certified test reports of the commercial testing laboratories. Reports shall include a statement that the materials tested do or do not meet the requirements of the Contract Documents.

Two copies of all reports shall be forwarded directly to the Contracting Authority for approval within 5 days of the actual performance of the test. The testing agency shall notify (verbally) the Contracting Authority of any tests, which indicated failure to meet the Contract requirements.

4.18.6 Any item, for which test reports show failure to meet all Contract requirements, shall be retested as often as required to show full compliance with Contract requirements, at the Contractor’s expense.

4.19 Site Cleanup:

4.19.1 The Contractor shall maintain the construction site in as clean and orderly condition as possible. All refuse and/or salvage material shall be gathered and disposed of periodically to maintain the site in this condition. All roadways, and roadway areas within the work area, or used by the Contractor, shall be kept free of construction debris, and associated mud, dirt, sand, or gravel that may be tracked from the construction work area by cleaning daily to assure safe operation of vehicles. The method of cleaning and equipment employed shall be subject to the approval of the Contracting Authority.

4.19.2 Following completion of the work, the Contractor shall clean the entire area from any debris and/or excess of misplaced material due to the Contractor’s operation and obtain the Contracting Authority’s approval of this finished work.

4.20 Refuse and Salvage Materials:

4.20.1 All refuse, debris, and construction waste shall be legally disposed of off Post at the Contractor’s expense.

Accumulations of refuse on the site will not be permitted.

4.20.2 All salvage property removed and not reinstalled under this Contract shall be returned to the Government at a place on base designated by the Contracting Authority, or properly disposed of when directed by the Government.

4.20.3 Nonhazardous solid waste must be diverted to recycling, through appropriate means available to the Contractor, if such diversion is less than or equal to the equivalent cost of landfill or incineration.

4.20.4 Prior to Contract closeout the Contractor must supply a report, including the following:

4.20.4.1 Amount (in tons) of nonhazardous solid waste, including construction and demolition debris, that is composted, mulched, recycled, reused, donated or otherwise diverted from a disposal facility.

4.20.4.2 Amount (in tons) of solid waste (including construction and demolition debris) transferred to a disposal facility (landfill).

4.20.4.3 The Contractor shall complete the Construction/Demolition and Waste Disposal Form. (See Appendix C)

4.21 Storage:

4.21.1 No secure storage space will be provided by the Government. The Government will not be responsible for property belonging to, or under the present control of the Contractor. The Contracting Authority will designate an unsecured, open area for storage of construction equipment and materials during the period covered by this Contract.

4.22 Damages, Repairs:

4.22.1 All damages by the Contractor’s operations shall be repaired, or replaced, at the Contractor’s expense, as directed by the Contracting Authority. Any Government property damaged as a result of the work, materials, or operations of the Contractor shall be restored at no additional expense to the Government.

4.22.2 All existing sidewalks, curbs, fencing, and pavement disturbed, broken or removed or otherwise damaged by the Contractor during performance of the work under this Contract shall be replaced by the Contractor at the Contractor’s own expense. Replaced sidewalks, curbs and pavements shall be smooth, shall blend into the existing work, and shall not present depressions or humps.

4.23 Special Conditions:

4.23.1 Any Contractor’s equipment that causes or generates electro-magnetic disturbances or interference shall be removed from service until properly repaired. The Contracting Authority may also require repositioning or removal of the equipment from the Post.

4.24 Security Requirements:

4.24.1 The CONTRACTOR shall ensure all personnel AT Level I training. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 15 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable.

The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website:

4.24.2 The CONTRACTOR shall ensure all personnel complete the Defense Security Service (DSS) computer based course, OPSEC Awareness for Military Members, DoD Employees and Contractors (GS130.16training). This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete the OPSEC awareness training identified within 15 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training by all employees and subcontractor personnel. OPSEC Awareness for Military Members, DoD Employees and Contractors (GS130.16) at:

https://securityawareness.usalearning.gov/opsec/index.htm

4.24.3 The Contractor shall ensure that all parts of the facility where work is being performed are adequately protected against vandalism and theft.

4.25 Work by Government:

4.25.1 The Government reserves the right to undertake performance by Government forces, for the same type or similar work as contracted herein, as the Government deems necessary or desirable, and to do so will not breach or otherwise violate this contract.

ARTICLE 5 - REFERENCES

5.1 Design Guides and References to be included but are not limited to:

5.1.1 CRJMTC Environmental Specifications for SOWs, 25 Jan 2018.

5.1.2 Section 303 Ohio Building Code

5.1.3 OSHA 29 CFR-1926, “Safety and Health Regulations for Construction.”

5.1.4 29 CFR 1910.25 Portable Wood Ladders.

5.1.5 29 CFR 1910.26 Portable Metal Ladders.

5.1.6 29 CFR 1910.28 Safety Requirements for Scaffolding.

5.1.7 29 CFR 1910.29 Manually Propelled Ladder Stands and Scaffolds (Towers).

5.1.8 29 CFR 1910.106/29 CFR 1926.152 Flammable and Combustible Liquids.

5.1.9 29 CFR 1910. 146 Permit-Required Confined Spaces.

5.1.10 29 CFR 1910.151 Medical Services and First Aid.

5.1.11 29 CFR 1910. 1200/29 CFR 1926.59 Hazard Communication.

ARTICLE 6 - Environmental Procedures 25 Jan 2018 See Appendix D for current version of Environmental Procedures.

http://jko.jten .mil.

CAMP RAVENNA WASTE MANAGEMENT GUIDELINES

ARTICLE 1 - CJAG WASTE MANAGEMENT GUIDELINES

1.1 PURPOSE: Guidelines to be followed by contractors working at CJAG who are generating/shipping Hazardous, Non-Hazardous, Special or Universal Waste.

1.2 POLICY: The policy at CJAG is to comply with all local, state, federal and installation requirements.

Contractor is responsible for waste minimization and is required to recycle materials if possible.

1.3 Restoration Program POC: Katie Tait (614) 336-6136 Military & Non-Restoration POC: Brad Kline

(614) 336-4918

1.4 Coordination:

1.4.1.1 Coordinate all waste generation and shipments with the appropriate CJAG POC listed above or the Environmental Supervisor in their absence at (614) 336-6568.

1.4.1.2 Notify CJAG POC prior to waste sampling for characterization. Details about sampling activities must be included (i.e., number of sample, analytical, etc.).

1.4.1.3 All Hazardous and Non-Hazardous waste management storage locations must be pre-approved prior to generation.

1.4.1.4 Ensure all labels include: Date, Contractor, and Waste Type.

1.4.1.5 When contractors have waste onsite, a weekly Inspection inventory must be completed and submitted to the appropriate POC in the CJAG environmental office.

1.4.1.6 All wastes shall be tracked and logged throughout the duration of the project. Contractor will provide CJAG POC with a monthly rollup report of all waste and recycled streams generated by no later than the 10th day of the following month.

1.5 Hazardous Waste Treatment, Storage and Disposal Facilities and Waste Haulers:

1.5.1 Contractors are required to utilize hazardous waste haulers and Treatment, Storage, and Disposal Facilities on the latest Defense Reutilization Marketing Office (DRMO) approved list. The current qualified waste hauler and TSDF list can be viewed by following the “Qualified Facilities” and “Qualified Transporters” links found on the DLA Hazardous Waste Disposal Homepage, http://www.dispositionservices.dla.mil/newenv/hwdisposal.shtml.

1.6 Hazardous or Non-Hazardous manifest form, the following must be included:

1.6.1 Military and non-restoration operations waste Site Name = Camp Ravenna Joint Military Training Center.

Mailing and Site address: CJAG ENV, 1438 State Route 534 SW, Newton Falls, Ohio 44444, (614) 336-4918. Ohio

EPA ID # – OHD981192925.

1.6.2 Restoration Program waste Site Name = Former Ravenna Army Ammunition Plant. Mailing address is same as address above. Site address: 8451 State Route 5, Ravenna, Ohio 44266, (614) 336-6136. Ohio EPA ID # –

OH5210020736.

1.6.3 Contractor’s shipping Hazardous Waste must provide a Land Disposal Restriction (LDR) in accordance with 40 CFR Part 268.

1.6.4 Profiling:

1.6.4.1 The required shipping documentation (i.e. waste profile and executive summary of lab reports (if available)) need to be submitted to appropriate CJAG POC or designee(s) for approval and signature prior to shipping.

1.6.4.2 Results of characterization must be submitted to appropriate CJAG POC within 30 days after collecting sample.

1.6.5 Manifests - Hazardous and Non-Hazardous:

1.6.5.1 The waste carrier/transporter provides appropriate manifest to the contractor.

1.6.5.2 The contractor is required to:

.1 Ensure that CJAG POC or designee(s) is available to sign the manifest on the scheduled day of shipment;

.2 Verify that each manifest is properly…