REVISED_Section_1025_Measurement_and_Payment.pdf

PDF 144 KB Posted

Attached to
Septic to Sewer Zones O & P
Solicitation number
B-7-25-57
Issued by
Brevard County, Florida

About this file

This document is a Measurement and Payment section (Section 01025) from a contract specification for a construction project involving gravity sewer improvements. The document details payment terms for various bid items, including mobilization/demobilization, insurance and bonds, preconstruction video, survey layout, project documentation, erosion and sediment control, maintenance of traffic, gravity sewer installation, and site restoration. The project scope includes installing six sewer manholes, one drop manhole, one doghouse manhole, 1,477 linear feet of 8" PVC sewer pipe, six concrete support cables, and associated site restoration work such as asphalt overlay, concrete walkways, driveways, and sidewalks.

The payment structure is based on lump sum prices for each bid item, with periodic payments made based on percent completion and less retainage. The contractor will be compensated for furnishing all labor, equipment, materials, and performing all work as specified in the contract documents. Pricing includes all costs associated with the project, such as taxes, transportation, permits, safety requirements, and compliance with regulatory agencies. The bid items cover comprehensive project elements from initial mobilization through final site restoration, ensuring full compensation for all aspects of the gravity sewer improvement project.

View the file

Other files

File Type Posted
B-7-25-57_Notice_of_Award.pdf PDF
Bid_Tabulation_-_Intent_to_Award.pdf PDF
Addendum_4.pdf PDF
REVISED_ZONE_P_Price_Sheet.pdf PDF
Addendum_3.pdf PDF
Addendum_2.pdf PDF
Addendum_1.pdf PDF
PRINTING_INSTRUCTIONS.pdf PDF
Plan_set_-_Zone_P.PDF PDF
Attachment_C_-_Specifications_Zone_P.pdf PDF
Attachment_B_-_Specifications_Zone_O.pdf PDF
B-7-25-57_Inv_&_Specs.pdf PDF
Attachment_A_-_Draft_Contract.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 01025 Page 83

SECTION 01025

MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.01 SCOPE

A. Payment for the various items of the Bid Schedule, as further specified herein, will include all compensation to be received by the Contractor for furnishing all tools, equipment, supplies, and manufactured articles, and for all labor, operations, and incidentals appurtenant to the items of work being described, as necessary to complete the various items of the Work, all in accordance with the requirements of the Contract Documents, including all appurtenances thereto, and including all costs of permits and cost of compliance with the regulations of public agencies having jurisdiction, including Safety and Health Requirements of the Occupational Safety and Health Administration of the U.S. Department of Labor (OSHA). The Contractor shall accept the compensation in full payment for all loss or damages arising from the nature of the work, or from any discrepancy between the actual quantities of work and quantities herein estimated by the Engineer, or from the action of the elements or from any unforeseen difficulties which may be encountered during the prosecution of the work until the final acceptance by the Owner. No separate payment will be made for any item that is not specifically set forth in the Bid Schedule, and all costs therefor will be included in the prices named in the Bid Schedule for the various appurtenant items of the completed work.

B. The prices stated in the Bid include all costs and expenses for taxes, labor, equipment, materials, commissions, transportation charges and expenses, patent fees and royalties, labor for handling materials during inspection, together with any and all other costs and expenses for performing and completing the work as shown on the Drawings and specified herein. The basis of payment for an item, task or procedure, at the unit or lump sum price shown in the Bid Schedule, shall be in accordance with the description of that item in this Section.

C. The Contractor's attention is called to the fact that the quotations for the various items of work are intended to establish a total price for completing the work in its entirety. Should the Contractor feel that the cost for any item of work has not been established by the Bid Schedule or Payment Items, the Contractor shall include the cost for that work in some other applicable bid item, so that the proposal for the project reflects the Contractor’s total price for completing the work in its entirety.

1.02 MEASUREMENT

A. Where indicated for measurement, the quantities for payment under this Contract shall be determined by actual measurement of the completed items, in place, ready for service and accepted by the Owner, in accordance with the applicable method of measurement therefore contained herein. A representative of the Contractor shall witness all field measurements.

Section 01025 Page 84

B. Subject to all other Contract requirements, the Contractor shall be paid for "as-built" quantities of work for which a unit price is given in the bid.

C. Where payment limit lines are shown on the Contract Drawings, or specified herein, measurements of a payment item quantity will be made up to, but not beyond such lines.

D. Where the actual work of a payment item falls short of the payment limit line, measurement will be made to the line of the actual work.

E. No measurement for payment will be made for quantities outside of payment limit lines unless authorized in writing by the Owner.

1.03 MOBILIZATION/DEMOBILIZATION (Bid Item No. 1)

A. Periodic payment will be made for these items based upon percent complete, less retainage.

B. Payment for Mobilization, demobilization, will be made at the lump sum price named in the Bid Schedule under Bid Item No. 1, which price shall constitute full compensation for mobilizing and demobilizing, in accordance with the requirements of the Contract Documents.

1.04 INSURANCE AND BONDS (Bid Item No. 2)

Payment for Insurance, and Bonds will be made at the lump sum price named in the Bid Schedule under Bid Item No. 2, which price shall constitute full compensation for providing all required insurance and performance, payment and maintenance bonds in accordance with the requirements of the Contract Documents.

1.05 PRECONSTRUCTION VIDEO (Bid Item No. 3)

A. Periodic payment will be made for this item based upon percent complete, less retainage.

B. Payment for performing the Preconstruction Video recording, including all field work, written narrative and submission of required DVD recordings will be made at the lump sum price named in the Bid Schedule under Bid Item No. 3, which price shall constitute full compensation for all such work performed in accordance with the requirements of the Contract Documents.

1.06 SURVEY LAYOUT, PROJECT DOCUMENTATION & AS-BUILTS (Bid Item No. 4)

B. Payment for performing the Survey Layout of the work, for maintaining the Project

Documentation, and for preparing and delivering the As-built drawings to the Engineer of Record, will be made at the lump sum price named in the Bid Schedule under Bid Item No. 4, which price shall constitute full compensation for all such work performed in accordance with

Section 01025 Page 85 the requirements of the Contract Documents.

1.07 EROSION & SEDIMENT CONTROL (Bid Item No. 5)

B. Payment for Erosion & Sediment Control including installation of all necessary erosion & sediment control Best Management Practices (BMP’s) devices as necessary for project construction will be made at the lump sum price named in the Bid Schedule under Bid Item No.

5, which price shall constitute full and total compensation for furnishing, installing BMP’s as indicated on the Drawings and as required in these Contract Documents.

1.08 MAINTENANCE OF TRAFFIC (Bid Item No. 6)

B. Payment for Maintenance of Traffic including installation of traffic control devices, vehicular and pedestrian detour routes, road closures, and flagging operations will be made at the lump sum price named in the Bid Schedule under Bid Item No. 6, which price shall constitute full compensation for furnishing, installing the traffic control devices, and performing and maintaining temporary traffic control as indicated on the Drawings and as required in these Contract Documents.

1.09 GRAVITY SEWER (Bid Item Nos. 7-20)

B. Payment for the Gravity Sewer improvements will be made at the lump sum price named in the

Bid Schedule under Bid Item No. 7 based on the sub-items Nos. 8-20 as listed in the Bid Schedule, which price shall constitute full compensation for furnishing and installing the new Gravity Sewer improvements including Six (6)Sewer Manholes, One (1) Drop Manhole, One (1) Doghouse manhole, 1477 Linear Feet 8” PVC Sewer pipe, Six (6) Concrete Support Cables, testing, and any other materials & labor as indicated on the Drawings and as required in these Contract Documents.

1.10 CLEAN UP/SITE RESTORATION (Bid Item No. 21-31)

C. Payment for keeping the sites clean, for final Clean-Up, and for Site Restoration for the Gravity Sewer Improvements will be made at the lump sum price named in the Bid Schedule under Bid Item No. 21 based on the sub-items Nos. 22-31 as listed in the Bid Schedule, which price shall constitute full compensation for providing all clean-up and site restoration, to include but not limited to, Site Clean-up, 600 Square Yards of 2” Asphalt, 700 Square Yards of Non-excavatable Flowable Fill, Milling of 2840 Square Yards of Existing Asphalt, 2840 Square Yards of Asphalt Overlay, 80 Square Yards Paver Walkway, 72 Square Yards Concrete Driveway, 45 Square Yards Concrete Sidewalk, &0 Linear Feet Miami Curb,1800 Square

Section 01025 Page 86

Yards Bahia Sod, and any other materials & Labor as indicated on the drawings, and required in the contract documents.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION