REQUEST_FOR_PROPOSAL_CHANGE.pdf
PDF 38 KB Posted
- Attached to
- 25-STR-01 106th St Bridge Repair
- Solicitation number
- IFB-2024-018
- Issued by
- Hamilton County, Indiana
About this file
This document is a Request for Proposal (RFP) Change form issued by the City of Carmel, designed to facilitate potential modifications to an existing contract. The form provides a structured template for proposing changes to a contract, requiring the contractor to submit a detailed proposal within fifteen (15) calendar days, including four (4) copies of a comprehensive breakdown of quantities, material costs, equipment, labor, overhead, and profit. The document explicitly states that submission of this request does not authorize proceeding with the proposed work or halting previously scheduled work, and that a Contract Change Order and Notice to Proceed will be issued upon approval.
The form requires the contractor to outline the description of the proposed change, the reason for the change, and to specify the potential impact on the project's Substantial Completion and Final Completion dates. While specific details are not filled in on this template, it is associated with the 25-STR-01 106th St Bridge Repair project in Carmel, Hamilton County, Indiana, which involves bridge repair work including replacement of damaged beams, railing, sidewalk, pier and end bent diaphragms, and other miscellaneous items. The form serves as a standardized mechanism for documenting and potentially implementing contract modifications, ensuring transparent and structured communication between the city and the contractor.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF CARMEL
TO: REQUEST FOR PROPOSAL NO
DATE:
PROJECT NAME:
PROJECT NO.:
Specification Reference:
Drawing Reference: _____________ Drawing Date:____________
Identification of Attachments:
Please submit within fifteen (15) calendar days of this request date a proposal showing increase, decrease or no change in Contract Price and/or Contract Time. Proposal shall be accompanied by four (4) copies of breakdown showing quantities, cost of material, equipment, labor, overhead, profit and basis for the additional time if any.
DESCRIPTION OF PROPOSED CHANGE COVERED BY THIS REQUEST:
REASON FOR CHANGE:
SPECIAL INSTRUCTIONS:
THIS REQUEST DOES NOT AUTHORIZE YOU TO PROCEED WITH THE ABOVE WORK
NOR STOP PREVIOUSLY SCHEDULED WORK. Upon approval a Contract Change Order and a Notice To Proceed will be issued.
Please state in your proposal the effect the acceptance of this Request will have on the Project’s Substantial Completion and Final Completion, if accepted within ___ days of proposal due date.
YOUR PROPOSAL DUE DATE: _____________________________________
By: _____________________________________ _________________ Engineer Date
Approved By: _________________________________ Owners Representative
File details come from the government source that posted it. Updated .