R-7291 Addendum 2~1.pdf

PDF 4 MB Posted

Attached to
R-7291 Alamitos Bay Entrance Channel Dredging REBID
Solicitation number
PW-26-744
Issued by
Los Angeles County, California

About this file

Alamitos Bay Entrance Channel Maintenance Dredging Project - Bid Addendum No. 2

This document is Bid Addendum No. 2 issued by the City of Long Beach Department of Public Works for the Alamitos Bay Entrance Channel Dredging and Beach Nourishment Project (R-7291). The project involves maintenance dredging of the Alamitos Bay Entrance Channel to maintain navigable vessel draft depths and replenishment of the Peninsula Beach nourishment area. The primary scope includes dredging up to 415,000 cubic yards of sediment from the entrance channel and placing dredged material on approximately 123 acres of Peninsula Beach. The addendum revises key project dates and requirements: the bid deadline has been extended from April 23, 2026 to April 29, 2026 at 3:00 p.m., with bids submitted through the City's online portal at https://longbeachbuys.buyspeed.com/. A mandatory pre-bid conference is scheduled for April 2, 2026 at 10:00 a.m. via Microsoft Teams, with an optional job-site walkthrough at the 72nd Place Parking Lot in Long Beach at 11:30 a.m. The work period is scheduled from September 16, 2026 through February 14, 2027 to avoid sensitive species breeding seasons, with a 152-calendar-day completion requirement. The addendum also updates the bid guarantee period from 90 to 120 calendar days, clarifies permit requirements including the finalized Coastal Development Permit (dated July 25, 2025) and Department of the Army Permit (issued August 15, 2025), and adds Section 01 71 23 Construction Surveying specifications.

The project is subject to a Citywide Project Labor Agreement requiring local hiring goals of 40 percent and provisions for transitional workers and veterans. Bidders must possess a valid California Class A Contractor license and demonstrate qualifications through three projects with a minimum cumulative value of five million dollars that include both dredging and beach nourishment experience. The City of Long Beach is the Owner and contracting entity, with the work covering various marinas, channels, and waterways under its jurisdiction. Required permits include the California Coastal Commission Coastal Development Permit (Application Number 5-24-0845) and the U.S. Army Corps of Engineers Department of the Army Permit (SPL-2023-00708-SME). The project is funded through State of California Tideland funds. All cost proposals and insurance requirements must comply with Division H specifications, and the contractor must provide bid security of not less than 10 percent of the bid amount, with performance and payment bonds each equal to 100 percent of the contract price upon award.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R-7291 Addendum 2

April 17, 2026

BID ADDENDUM NO. 2

PLANS AND SPECIFICATIONS NO. R-7291

ALAMITOS BAY ENTRANCE CHANNEL DREDGING

NOTICE TO HOLDERS OF PLANS AND SPECIFICATIONS

Please note the following changes, clarifications, and additions:

SPECIFICATIONS:

Changes to the specifications for the LOS ALAMITOS BAY ENTRANCE CHANNEL DREDGING (Specification Number R-7291):

• Division A NOTICE INVITING BIDS is replaced in its entirety with the attached document.

• Division B INSTRUCTIONS TO BIDDERS is replaced in its entirety with the attached document.

• Division F PERMITS AND ATTACHMENTS is hereby amended to include 1. Coastal Development Permit, dated July 25, 2025 (Permit Application Number: 5-24-0845) and 2.

Department of The Army Permit, date of Issuance, August 15, 2025 (Permit Number SPL-2023-

00708-SME)

• Division J CSI TECHNICAL SPECIFICATIONS is hereby amended to include Section 01 71 23 Construction Surveying

1. DIVISION A NOTICE INVITING BIDS

Replace Division A in its entirety.

a. RECEIPT OF BIDS:

o Previous: Bids will be accepted on behalf of the City, Owner of the work, until 3:00 p.m. on April 23, 2026, for ALAMITOS BAY ENTRANCE CHANNEL DREDGING, via the City’s online portal https://longbeachbuys.buyspeed.com/ keyword Project R-7291.

o Revision: Bids will be accepted on behalf of the City, Owner of the work, until 3:00 p.m. on April 29, 2026, for ALAMITOS BAY ENTRANCE CHANNEL DREDGING, via the City’s online portal https://longbeachbuys.buyspeed.com/ keyword Project R-7291.

2. DIVISION B INSTRUCTIONS TO BIDDERS

Replace Division B in its entirety.

a. CONTACT:

o Previous: Alma.Wagner@longbeach.com o Revision: Alma.Wagner@longbeach.gov

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383 https://longbeachbuys.buyspeed.com/ https://longbeachbuys.buyspeed.com/ mailto:Alma.Wagner@longbeach.com mailto:Alma.Wagner@longbeach.gov

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383

b. BIDS SHALL REMAIN OPEN:

o Previous: The Bidder shall guarantee the Total Bid Price for 90 calendar days after the bid opening.

o Revision: The Bidder shall guarantee the Total Bid Price for 120 calendar days after the bid opening.

(Reference is made to RFI #2.)

2. DIVISION C BID DOCUMENTS

a. BASE BID FORM o Previous: Duplicate Base Bid forms were included.

o Revision: Removes one set of Base Bid form.

(Reference is made to RFI #8.)

3. DIVISION F PERMITS AND ATTACHMENTS

Division F is hereby amended as follows:

a. Attachment A: California Coastal Commission Coastal Development Permit 5- 24-0845 o Previous: “Notice of Intent to Issue Permit” o Revision: Add “Coastal Development Permit, dated July 25, 2025 (Permit

Application Number: 5-24-0845)” (Reference is made to RFI #15.)

b. Attachment B: US Army Corps of Engineers 401 Permit SPL-2023-00708 o Previous: Standard Individual Permit o Revision: Add “Final - Department of The Army Permit, date of Issuance, August 15, 2025 (Permit Number SPL-2023-00708-SME)” (Reference is made to RFI #17.)

4. DIVISION J CSI TECHNICAL SPECIFICATIONS

Division J is hereby amended as follows:

a. Section 01 71 23 Construction Surveying o Previous: Specification omitted from original bid documents.

o Revision: Incorporate Section 01 71 23 Construction Surveying

DRAWINGS

1. SHEET G-02 EXISTING CONDITIONS

o Revision: Revised sheet with a revision to the note on temporary and overnight mooring.

RESPONSES TO REQUESTS FOR INFORMATION:

Bidders are reminded to acknowledge all addenda by signing the signature block in each and uploading them with Division C, Bid Documents. Refer to Addenda Acknowledgement, Division B – Instruction to Bidders.

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383

Question 1: Given the extreme fluctuation in the costs of fuel, will the city consider adding a bid item for fuel reimbursed at cost. This will protect the owner from paying today's high fuel costs plus contingency, if the price does go back down.

Response 1: Response to be issued on an upcoming Addendum.

Question 2: Can the city provide a date they intend to award the contract? The specs state that the bids remain valid for 90 days. If the full 90 days is used it will make it very difficult to adequately plan and prepare for the project start in September.

Response 2: "Revise Division B has been amended as follows:

BIDS SHALL REMAIN OPEN: The Bidder shall guarantee the Total Bid Price for 90 120 calendar days after the bid opening."

Question 3: Regarding the debris removal allowance item of 1 AL $250,000. Is the contractor expected to have suitable equipment to recover debris on site standing by for the duration of the contract? And if so, how is that paid? Or is the equipment to be brought in on an as needed basis depending on what is encountered, and all mobilization events paid under the 250k allowance?

Response 3: The City does not require the contractor to keep suitable equipment on site. If debris is located on site, the contractor should notify the City, work around the debris to maintain schedule, and mobilize the required equipment as needed.

Question 4: In Division C bid documents - there are two bid forms which are seemingly identical except item 6 on the second form is underlined. Please clarify if there are two bid schedules/ bid forms?

Response 4: Sheets C-1, C-2, and C-3 were duplicated. Revised Division C Base Bid Form is provided.

Question 5: Division C - Para 5.1.1: Requires three projects of similar scope with a minimum value of 2 million, defining similar scope as dredging and beach nourishment.

a. Will the city accept more than three projects which combine to meet all these experience items?

b. For example: 1 project with beach nourishment and no dredging over 2m, 1 project with dredging and no beach nourishment over 2m, 3 projects with dredging and beach nourishment but under 2m. 1 project that meets all 3. Or some similar combination.

Response 5: Yes. Three projects containing dredging and beach nourishment are required with a minimum cumulative value of $5M. The aggregate of submitted projects need to show ability to perform similar scope for both dredging and beach nourishment.

Question 6: Section 01 71 13 Paragraph 4.02 A. states that “Payment for Mobilization and Demobilization will be made at the Contract lump sum price listed in the Bid… but not to exceed a maximum of 10% of the combination of other Bid Items in the Base Bid (excluding mobilization and demobilization).” For a job where beach placement is required, a large portion of the expense is mobilizing and demobilizing the pipeline and equipment that is required for pumping off on the beach. Limiting the price may result in an unbalancing of bids, which is not suitable for this type of work. Please consider eliminating the requirement to limit the price of mobilization and demobilization so that prospective bidders may price the work according to their costs.

Response 6: No change to the mobilization and demobilization maximum percentage.

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383

Question 7: Paragraph 1.06 B. 1. of Section 35 20 23 lists possible incidences of debris to include abandoned vessels. Please confirm that there are no known derelict vessels currently in the dredging template.

Response 7: The City is not aware of the recorded presence of derelict vessels.

Question 8: The Division J – CSI Technical Specifications Table of Contents includes 01 71 23 Construction Surveying, but it appears that section was not provided. If required, please provide Section 01 71 23.

Response 8: Section 01 71 23 Construction Surveying is attached.

Question 9: In Section 01 71 23 Construction Surveying of the original solicitation, R-7246, there was a requirement for a Pre-Dredge Structure Condition Survey. If that will be included in this specification, please clarify the intention of the requirement. Should bidders provide vibration monitoring for the duration of the beach work?

Response 9: The intent of the Pre-Dredge Structure Condition Survey is to document the presence and general condition of existing structures prior to commencing the Work that may be impacted during the Work. This survey may include the area for the pipeline alignment over the rock jetty, any marine structures such as docks that Contractor equipment is moored to, and the staging area parking lot. Vibration monitoring is not required during the beach work.

Question 10: The sediment core logs provided in Division F of the Contract Documents indicate that hydrogen sulfide odors were detected in material samples collected throughout the dredge area. Despite this, the sampled material has been determined suitable for placement at the Beach Nourishment Area. However, the Contract Documents then place responsibility on the Contractor for controlling hydrogen sulfide odors at the Beach Nourishment Area by dictating in Paragraph 3.06 A. of Section 01 57 23 that “If odors exceed thresholds and community complaints are received, Contractor shall propose, for Owner approval, actions (and enact such actions at no additional cost to the Owner) to minimize the odors.” The Contractor should not be responsible for remediation if the dredge material, previously determined by regulatory agencies to be suitable for beach placement, is later determined to not be suitable for beach placement or is a nuisance or hazard to the public.

To reduce the need for pricing risks that cannot be quantified prior to work, please consider removing this language from the Specifications and instead including Standby Time to cover potential delays due to the Risk for Hydrogen Sulfide Odors.

Response 10: If odors exceed thresholds and community complaints are received, Contractor shall propose, for Owner approval, actions (and enact such actions at no additional cost to the Owner) to minimize the odors. Contractor to propose method and cost change order to minimize odors for City's approval prior to commencing odor mitigation work.

Question 11: Paragraph 1.01 B. of Section 35 20 23 indicates that the bid quantity is based on the July 12, 2023 survey provided in the Drawings. However, upon running take-offs of the survey data, it does not appear that there are 415,000 CY of material available in the template, even with all payable side slope and payable overdepth material included. Could the Owner and/or Engineer please re-evaluate the total quantity on the bid form and ensure consistency with the Drawings and Specifications?

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383

Response 11: The estimated quantity is based on the July 12, 2023 survey, and includes a 30% volume contingency. The basis for the contract measurement and payment will be the Pre-dredge Survey performed by an independent third-party surveyor.

Question 12: The Plan Drawings and Specification Section 35 20 23 Dredging and Sediment Placement contain contradictory language concerning side slope dredging. Understanding that the Owner would like as much material removed as possible and that the Owner intends to pay for material that has sloughed from above the defined slopes, contract language indicates that digging beyond the limits provided in the Drawings, which delineate the toe of slope, is not permitted and could undermine nearby structures (see Paragraph 1.02 Definitions of Dredging Limits and Excessive Dredging). However, other contract language states that side slope dredging is required. In order to prevent permit violation and to protect existing structures, will the Owner please consider removing language similar to that found in Section 35 20 23 Paragraph 3.03 C. 2., stating that “…the Contractor is required to dredge Side Slopes,” and Note #2 on Sheets C03 to C06, stating that “Contractor shall dredge the side slopes identified in the drawing.”

Response 12: "Dredging limits include the side slopes."

Question 13: Section 35 20 23 Paragraph 1.02 A. 4. states that “The Payable Overdepth does not apply to any areas where the pre-dredge surface elevation is already below the Required Dredge Elevation, where no dredging is necessary or permitted.” To clarify the intent of this language, is dredging outside of areas where the pre-dredge surface elevation is already below the Required Dredge Elevation actually prohibited in permits, or is it just not payable? If it is not prohibited, please consider allowing payment for this overdepth volume.

While we will not actively dredge areas that do not have any material above the required grade, there will be incidental overlap of dredge cuts that will dredge material within the overdepth template (specifically areas on the northernmost inside sections of channel where material is not above required grade).

Response 13: Dredging in areas below elevation -22' is not prohibited in the permits and not payable. No Change.

Question 14: Note 4 on Sheet C08 of the Contract Drawings states that “Contractor shall fully submerge the hydraulic pipeline portions located within the navigation channel for safe vessel passage.” Rather than requiring Contractor to submerge the pipeline, please allow Contractor to choose methods as appropriate for their operation, upon the condition that they provide safe vessel passage.

Response 14: Contractor means and methods for performing the work will be reviewed as part of the pre-construction submittals. Please submit requests for variance from contract drawings or specifications during the pre-construction submittal process.

Question 15: The California Coastal Commission Coastal Development Permit 5-24-0845, as provided in Division F, Attachment A, was issued as a “Notice of Intent to Issue Permit”, subject to satisfaction of special conditions. Can the Owner please provide the final CDP permit to bidders?

Response 15: Coastal Development Permit, dated July 25, 2025 (Permit Application Number: 5-24-0845) is attached.

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383

Question 16: "The California Coastal Commission Coastal Development Permit 5-24-0845, as provided in Division F, Attachment A, requires an Avian Monitoring & Avoidance Plan, which appears to be applicable only to sand placement activities occurring during western snowy plover breeding season (March 1 to August 31) and California least tern breeding season (April 1 to September 15). Please confirm that, due to the anticipated timing of this work, the Contractor will not be responsible for avian monitoring requirements under this Special Condition 4."

Response 16: The City is responsible for any avian monitoring and reporting required by Special Condition 4.

Question 17: Division F, Attachment A provides correspondence from the US Army Corps of Engineers regarding a Standard Individual Permit request. Can the Owner please provide the final Standard Individual Permit to bidders? What conditions of the permit will Contractor be responsible for?

Response 17: Department of The Army Permit, date of Issuance, August 25, 2025 (Permit Number SPL-2023-00708-SME) is attached.

Question 18: The pre-bid slides mentioned avoiding impacts to green sea turtles. Green sea turtles do not appear to be mentioned in the documents provided. Is the Contractor responsible for green sea turtle monitoring? If so, please provide applicable requirements.

Response 18: The Contractor shall be responsible for avoiding impacts to green sea turtle, including observing water-related activities for the presence of green sea turtle and complying with the requirements of the USACE Standard Individual Permit SPL-2023-00708-SME.

Question 19: Paragraph 3.03 B. 2. of Section 35 20 23 states that “The Contractor shall complete cleanup pass dredging at the toe of slope a minimum of one week after achieving the required dredge depth, as necessary, to address sloughed material.” Understanding that the Owner is trying to achieve a template that will remain clear as long as possible, will the Owner please consider removing the requirement to wait a minimum of one week? Including this language is costly as it requires the Contractor to keep their equipment mobilized and unproductive for a week. Typical dredge operations utilize daily hydrographic surveys to monitor the progress of the channel and would allow for productive clean-up during the normal course of dredging by setting the dredge back to remove any high spots.

Response 19: Evaluation of slope development following completion of dredged units can be assessed during progress surveys. Please submit requests for variance from contract drawings or specifications during the course of construction.

Question 20: Paragraph 3.04 C. of Section 35 20 23 states that “The Contractor shall be responsible for all means and methods required for controlling and maintaining water quality standards during dredging and placement operations. The Contractor shall minimize turbidity and loss of resuspended sediments during dredging and transport operations and adhere to the Section 401 Water Quality Certification requirements and USACE permit requirements, subject to monitoring by the Owner.” However, Paragraph 4.02 B. of Section 01 57 23 states that “Environmental controls must also include associated quality control, reports, submittals, monitoring (by the Contractor), and all other incidental items required to maintain water quality.” Is the Owner or the Contractor responsible for water quality monitoring?

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383

Response 20: The City will perform water quality monitoring and reporting required by the Section 401 Water Quality Certification and USACE permit.

Question 20: Paragraph 3.04 C. of Section 35 20 23 states that “The Contractor shall be responsible for all means and methods required for controlling and maintaining water quality standards during dredging and placement operations. The Contractor shall minimize turbidity and loss of resuspended sediments during dredging and transport operations and adhere to the Section 401 Water Quality Certification requirements and USACE permit requirements, subject to monitoring by the Owner.” However, Paragraph 4.02 B. of Section 01 57 23 states that “Environmental controls must also include associated quality control, reports, submittals, monitoring (by the Contractor), and all other incidental items required to maintain water quality.” Is the Owner or the Contractor responsible for water quality monitoring?

Response 20: The City will perform water quality monitoring and reporting required by the Section 401 Water Quality Certification and USACE permit.

Question 21: Paragraph 3.01 A. 6. of Section 35 20 23 indicates that the Contractor should obtain Owner approval to use anchors to control the position of its equipment as opposed to spuds. Please confirm that, if a Contractor has proven experience of safely and efficiently working on anchors in navigation channels, Owner approval will be granted to use anchors.

Response 21: The City will review the Contractor's work plan and proposed anchor system and the Contractor may provide examples of experience successfully using anchors in navigation channels.

Question 22: Please provide the latest full resolution survey datasets for the full dredge area and the full beach renourishment area in XYZ file format.

Response 22: The 2023 survey data are provided for planning purposes only. The pre-construction survey will be the basis for the contract. Dropbox LINK to access the files https://bit.ly/4sDepT9.

Question 23: "Regarding the insurance requirements, if the contractor has primary Marine General Liability limits of $1M per Occurrence / $2M aggregate, but the contract requires a primary $2M Per occurrence / $4M aggregate, and the contractor has plenty of limit available in the umbrella (the contract requires $3M), will the City/POLB accept what the contractor has?"

Response 23: The Contractor shall comply with DIVISION H Section 7-3-1 Minimum Insurance Requirements. (This is not a POLB project.)

Question 24: Regarding the insurance requirements, will the City/POLB be amenable to amending the insurance requirement language in the contract with the awarded contractor, and if not is the City able to provide acknowledgepment that the coverage the contractor has is acceptable?

Response 24: The Contractor shall comply with DIVISION H Section 7-3-1 Minimum Insurance Requirements. (This is not a POLB project.)

Question 25: "Paragraph 4.01 A. of Section 35 20 23 states the following regarding the Beach Nourishment Area: “The Contractor shall meet the specified grades and tolerances defined in the Contract Documents for the Beach Nourishment Area as measured by the post-construction topographic surveys. The Contractor shall perform the grading and https://bit.ly/4sDepT9 https://bit.ly/4sDepT9

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383 earthwork to meet these requirements at no additional cost to the Owner, prior to Owner acceptance of a dredging subsection or final acceptance.” Because beach erosion will occur over the duration of the project, would the Owner please consider accepting 200 to 300 ft sections at a time?"

Response 25: Bid line items will be paid according to volume of material removed by dredging. The plans have a target slope of 20H:1V, if beach nourishment material is lost due to currents, work plan may be adjusted to restore areas with remaining dredged material to the contractor’s best ability with approval from the Engineer.

Question 26: Paragraph 4.01 B. of Section 35 20 23 indicates that Bid Item 6 “will be measured on a per ton basis based on certified weight tickets from the approved upland off-site disposal facility.” Considering that debris removal may require the mobilization and demobilization of different equipment and the additional logistics that could be required for debris removal, is it the Owner’s intention for this item to be measured per ton? If not, please revise the measurement language for Bid Item 6.

Response 26: Mobilization and demobilization of debris removal equipment will be approved by the Owner prior to mobilization of equipment to the site. Debris removal within Bid Item 6 will be measured on a per ton basis based on certified weight tickets from the approved upland off-site disposal facility.

Question 27: If debris removal causes a delay to dredging operations, will dredging delays be covered under the Bid Item 6 allowance?

Response 27: "Dredging delays shall not be compensated under the Bid Item 6 allowance.

Reference is made to DIVISION H Section 6 for any schedule related matters."

Question 28: If the language of Paragraph 3.06 A. of Section 01 57 23 is to remain in the Contract Documents, requiring that the Contractor propose and enact actions to minimize hydrogen sulfide odors coming from material placed on the beach, please provide information regarding what type of remediation would be acceptable to minimize such odors.

Response 28: See RFI response to item 10 above.

Question 29: The last sentence of Paragraph 3.10 D. of Section 35 20 23 states that “The cost to the Owner for verifying completion of the work after the initial inspection will be deducted from payments due to the Contractor.” Please clarify what cost would be deducted from the Contractor payment.

Response 29: See Paragraph 3.10 D. of Section 35 20 23. Any additional inspections due to unsatisfactory completion of the work will be deducted from the Contractor's payment.

Question 30: The Contract Documents state that Contractor must coordinate and cooperate in a manner to minimize impacts to others working in the area. Please confirm whether any such work is scheduled or anticipated during this Project.

Response 30: Per Spec. 01 11 00, access to the lifeguard station and parking lots are to remain open as shown in Sheet C07. There are no other known projects.

Question 31: Please confirm that if access is restricted by any party other than Contractor, such restrictions to access shall be considered an Excusable Compensable Delay. Owner agrees to pay Contractor's Standby Rates during any Excusable Compensable Delay.

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383

Response 31: Reference is made to DIVISION H Section 6 for any schedule related matters.

Question 32: Please confirm in the event of changes in laws or regulations (including applicable tariffs or duties) taking effect after submission of Contractor's bid, Contractor shall be entitled to an equitable adjustment to the extent such change impacts Contractor's cost and/or time of performance.

Response 32: The City is unable to confirm adjustments to the Contract in the event of changes in law or regulations after bid award.

Question 33: Since liquidated damages are assessed not as a penalty but as a reasonable pre estimate of probable damages when actual/direct damages are difficult to calculate, please confirm and update the contract documents to reflect that in the event of delayed performance, liquidated damages will be assessed in lieu of actual (direct and indirect/consequential) damages.

Response 33: For requirements associated with Liquidated Damages, please refer to DIVISION D Performance Bond, DIVISION C Equal Benefits Ordinance Disclosure Compliance, DIVISION H Section 6-9.

Question 34: "To reduce contingencies in Contractor bids, please include the following waiver of consequential damages: “Notwithstanding anything herein to the contrary, Contractor shall not be responsible or liable for and Owner hereby waives, any indirect, consequential or special damages of any type or nature whatsoever and howsoever arising, including, without limitation, loss of profits, loss of income, loss of business opportunity, business interruption, loss of use and/or loss of ability to use undamaged component or system parts, whether resulting from negligence, breach of contract or otherwise, and regardless of whether such damages may have been foreseeable.”" Response 34: Reference is made to DIVISION H Section 7-16 Indemnification.

Question 35: Please confirm that Contractor shall be entitled to an equitable adjustment in the Contract Time and/or Contract Price for delays caused by the acts or omissions of the Owner, other contractors of Owner, or anyone for whom Owner is responsible. The Contractor should not be required to bear the costs associated with such delays.

Response 35: Reference is made to DIVISION H Section 6 for any schedule related matters.

Question 36: Will this project receive Federal financial assistance (it is funded in whole or in part by the U.S. Government), yes or no?

Response 36: There is no federal funding on this project.

Question 37: Please provide the full name of the Federal agency providing financial assistance for this project.

Response 37: See response to RFI # 36 above.

Question 38: Please provide the date (day, month, and year) the Federal financial assistance grant or loan for this Project was awarded.

Response 38: See response to RFI # 36 above.

Question 39: If this project will receive Federal financial assistance and 2 CFR part 184 does not apply, please provide complete documentation from the Federal funding agency about

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383 the applicable domestic project preference requirements, and conform the contract documents.

Response 39: See response to RFI # 36 above.

Question 40: Please confirm Contractor shall be entitled to an equitable adjustment in the Contract Price and/or time for completion of the Work associated with any delays in the issuance of the permit(s) or any unanticipated impacts/changes to the Work required by such permit(s).

Response 40: Reference is made to DIVISION H Section 3 for changes related matters, and Section 6 for any schedule related matters.

Question 41: Please confirm in accordance with Section 1.06.A.4. of DIV J, SEC. 35 20 23, that Contractor is responsible only for hazardous materials brought to the Project site and/or generated by the Contractor, and will not be responsible for any pre-existing materials containing substances classified as hazardous, potentially hazardous, infectious, toxic or dangerous under applicable law, which shall be disposed of in strict compliance with all regulations as directed by Owner. With respect to any such pre-existing materials, Owner is the generator. Please modify Section 7-16.1.d. of the General Requirements accordingly.

Response 41: DIVISION H Section 7-16.1.d is not relevant to DIVISION J Section 1.06A.4, and therefore remains as is.

Question 42: In the event of an Owner suspension, please confirm that an equitable adjustment to the Contract Time, Price, or both will be granted commensurate with the suspension.

Response 42: Reference is made to DIVISION H Section 3 for changes related matters, and Section 6 for any schedule related matters.

Question 43: Please also consider limiting the potential period of suspension to allow bidders to make contingency plans (no limitations on the duration of suspensions could result in unnecessarily high bid prices).

Response 43: Reference is made to DIVISION H Section 3 for changes related matters, and Section 6 for any schedule related matters.

Question 44: "Please confirm Contractor is solely responsible for damage to known utilities and will not be responsible for damage to utilities not shown on the plans and specifications or identified by the utility locator service.

Contractor should not be responsible for damage to unknown, unidentified utilities located on the Owner's project site that cannot reasonably be discovered."

Response 44: Reference is made to DIVISION J Section 35 20 23 for several references on utilities.

Question 45: "Unlike land-based construction, completed dredging activities are subject to natural forces that are entirely outside the control of the Contractor. To clarify the intent of the warranty, please include the following warranty provision: "Upon Contractor’s advising Owner that the dredging has been completed, Owner shall inspect the Work and, if acceptable, shall advise Contractor of Owner’s acceptance thereof. Contractor in no way represents, guarantees or warrants that

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383 any dredging or excavation will stay open, dredged or excavated for any period of time whatsoever.”

Response 45: See response to RFI # 25 above.

Question 46: Section 6-4.3 (b) of the Greenbook allows Owner to use any materials, equipment, tools, or other facilities furnished by the Contractor to secure and maintain the Work Site. It is unacceptable for any third party to take possession of Contractor's highly specialized marine tools and equipment. Please remove "equipment, tools, or other facilities" from Section 6-4.3 (b) of the Greenbook for purposes of this contract or add clarifying language to Division H stating that under no circumstances will Owner attempt to use and/or take possession of Contractor's equipment, tools, or other facilities.

Response 46: The City will not remove Section 6-4.3(b) of the Greenbook. However, the City clarifies that any use of the Contractor-furnished materials, equipment, tools or facilities following termination for default will be limited to that which is reasonably necessary to secure and maintain the Work site. The City will not operate or utilize specialized equipment requiring unique training, certification, or proprietary knowledge, except to the extend necessary to address imminent risk to public safety or property.

Question 47: If a contractor has a dredge that meets California Air Resource Board statewide requirements, will that suffice, or will all engines still be required to be “Tier 4 standard?”

Response 47: Strike requirement for Tier 4 standards for marine vessels. Reference: 01 40 00 1.04C.3.a.3 For marine vessel equipment, USEPA Tier 4 standard or equivalent, using conventional diesel.

Question 48: If “Tier 4 standard” engines are required on the dredge, does Tier 4 Interim and Tier 4 Final diesel engines meet the requirement of “Tier 4 standard?”

Response 48: Strike requirement for Tier 4 standards for marine vessels. Reference: 01 40 00 1.04C.3.a.3 For marine vessel equipment, USEPA Tier 4 standard or equivalent, using conventional diesel.

Question 49: Pre-Construction Environmental Survey & Report – please elaborate on the requirements for the pre-construction environmental survey and report, and if a third party environmental firm or biologist will need to be utilized by the contractor.

Response 49: The Contractor shall review environmental surveys provided by the City, including the pre-construction eelgrass survey, and note environmental conditions that differ from those reflected on the Drawings.

Question 50: Independent Survey Firm – Please advise if an Independent Survey Firm is required for all hydrographic and topographic surveying regarding surveys for payment and acceptance; and does these surveys for payment and acceptance need to be stamped by a PLS in the State of California, employed by the Independent Survey Firm?

Response 50: See Technical Specification SECTION 01 71 23 CONSTRUCTION

SURVEYING.

Question 51: Dragging – the spec notes knockdown dredging projects not to exceed 2,000 cubic yards, and not in the same area more than once per year. Please advise if

Department of Public Works 411 West Ocean Boulevard, 5th Floor Long Beach, CA 90802

(562) 570-6383 dragging/knockdown dredging will be allowed on this project for cleanup purposes post-dredging to achieve final grade?

Response 51: Reference Clean Water Act Section 401 Water Quality Certification File No.

23-052 dated January 8, 2024. Knockdown dredging is allowed if it is performed in compliance with the terms and conditions of the project permits.

CONTACT: Before the Bid opening, prospective Bidders shall direct any communications regarding this Work to:

City of Long Beach, Department of Public Works Project Management Bureau 5th Floor, City Hall 411 W. Ocean Boulevard Long Beach, CA 90802 Attention: Alma Wagner / TidelandsCIP E-mail: Alma.Wagner@longbeach.gov / TidelandsCIP@longbeach.gov

Communications may be written or oral, but the City is not bound by any oral interpretation of the Contract Documents made by any City employee, nor does the City guarantee the accurate transcription of oral questions.

PREPARED BY: Alma Wagner

ACKNOWLEDGED BY:

Company Name

Print Name Title

Signature Date

Attachments:

Division A Notice Inviting Bids Division B Instructions To Bidders

Division F Permits and Attachments - 1. Coastal Development Permit, dated July 25, 2025 (Permit Application Number: 5-24-0845) and 2. Department of The Army Permit, date of Issuance, August 15, 2025 (Permit Number SPL-2023-00708-SME)

Division J CSI Technical Specifications - Section 01 71 23 Construction Surveying Sheet G-02 Existing Conditions mailto:Alma.Wagner@longbeach.gov mailto:TidelandsCIP@longbeach.gov

Department of Public Works A-1 Specification R-7291

City of Long Beach Rebid Addendum No. 2 Division A – Notice Inviting Bids

DIVISION A

NOTICE INVITING BIDS

FOR R-7291

ALAMITOS BAY ENTRANCE CHANNEL DREDGING

RECEIPT OF BIDS: Bids will be accepted on behalf of the City, Owner of the work, until 3:00 p.m. on April 23, 2026 April 29, 2026, for ALAMITOS BAY ENTRANCE CHANNEL DREDGING, via the City’s online portal https://longbeachbuys.buyspeed.com/ keyword Project R-7291.

MANDATORY PRE-BID CONFERENCE AND OPTIONAL JOB-SITE WALK-

THROUGH: The City will conduct a mandatory pre-bid conference to review bidding processes, Project Labor Agreement (PLA), at 10:00 a.m. on April 2, 2026. Prospective Bidders must attend this meeting. Failure to attend the pre-bid conference and follow procedures to confirm your attendance shall be cause for rejecting the bid.

The pre-bid conference will be conducted via Microsoft Teams. Prospective Bidders must attend this meeting. The meeting can be accessed online via the following link or by phone:

MANDATORY PRE-BID CONFERENCE

Microsoft Teams Join the meeting now https://teams.microsoft.com/meet/24268552448900?p=IygIoziYENcVG1Lr6C

Meeting ID: 242 685 524 489 00 Passcode: nL9Sb2ad

Dial in by phone +1 213-279-1690,,154126068# United States, Los Angeles Phone conference ID: 154 126 068#

OPTIONAL JOB-SITE WALK-THROUGH

The City will also conduct an optional Job-Site Walk-Through meeting at the below location:

Alamitos Bay 72nd Place Parking Lot 7203 E Ocean Boulevard Long Beach, CA 90803

Time: 11:30 a.m.

Date: April 2, 2026

DESCRIPTION OF WORK: The work to be done consists primarily of dredging the Alamitos Bay Entrance Channel under Drawings B-4852 to maintain navigable vessel draft depths and to replenish the nearby Beach Nourishment Area on Peninsula Beach.

https://longbeachbuys.buyspeed.com/ https://teams.microsoft.com/meet/24268552448900?p=IygIoziYENcVG1Lr6C https://teams.microsoft.com/meet/24268552448900?p=IygIoziYENcVG1Lr6C tel:+12132791690,,154126068

Department of Public Works A-2 Specification R-7291

City of Long Beach Rebid Addendum No. 2 Division A – Notice Inviting Bids

Bids are required for the entire Work. Selection of “NO BID” for any bid item will render the bid-non-responsive. Work is subject to regular and special conditions from regulatory agencies, including but not limited to the Regional Water Quality Control Board, US Army Corps of Engineers, and California Coastal Commission.

PROJECT LABOR AGREEMENT: This work is covered by a Citywide Project Labor Agreement (PLA) entered into by the City of Long Beach with the Los Angeles/Orange Counties Building and Construction Trades Council and the signatory Craft Unions. The PLA establishes the labor relations Policies and Procedures for the City, the Contractor and subcontractors awarded contracts for the Work and for the craft persons employed by the Contractor or subcontractor while engaged in the work. See Division E of the Specifications for the applicable PLA.

CONTRACTOR'S LICENSE: The Contractor shall possess a valid California Class A Contractor license at the time of contract award. The City may deem any Bidder who fails to possess the required license to be non-responsive.

MINIMUM QUALIFICATIONS: Please note that for this work, minimum qualifications apply. Information concerning these requirements can be found in Division C of the specifications.

PLANS AND SPECIFICATIONS: Plans and specifications are posted on the City’s website at the URL http://www.longbeach.gov/finance/business-info/purchasing-division/ on the “Bids/RFPs” tab and available for free download, however, you must be registered (registration is free and may be accomplished at the same URL) and logged in to view or download the documents.

BID SECURITY: Bidders must scan and upload with their bid documents, a certified check or bank draft payable to the City of Long Beach, drawn on a solvent bank in the United States of America, or a satisfactory bond in an amount not less than 10 percent of the bid. The original of the above instrument shall be submitted to the City Clerk in a sealed envelope and must be received and time/date stamped by the City Clerk’s Office no later than the time and date stated for receipt of bids. The outside of the envelope shall clearly state “Bid Security for Specification R- 7291 Project ALAMITOS BAY ENTRANCE CHANNEL DREDGING. DO NOT OPEN WITH REGULAR MAIL.” The City Clerk’s Office is located at 411 W. Ocean Blvd, 1st Floor, Long Beach, CA 90802.

The bid security may be submitted through certified mail or in-person. Bidders may proceed directly to Window 12 without pulling a service ticket.

The bid security shall serve as a guarantee that the Bidder, if awarded the Contract, will execute, and deliver to the City, no later than fifteen (15) calendar days after the date shown on the “Notice of Award,” the following items:

1. The Contract for doing the work, and http://www.longbeach.gov/finance/business-info/purchasing-division/

Department of Public Works A-3 Specification R-7291

City of Long Beach Rebid Addendum No. 2 Division A – Notice Inviting Bids

2. A corporate surety bond in favor of the City of Long Beach in an amount not less than 100 percent of the Contract price for the faithful performance of the Contract, and

3. A corporate surety bond in an amount not less than 100 percent of the Contract price for the payment of all labor and material claims, and

4. Evidence of required insurance coverage as written in Division H of the Bid Specifications.

Failure to submit the items noted above when specified may result in the City, in its sole discretion, declaring the bid security forfeited and depositing the same into the City Treasury.

The City will retain the bid security accompanying all bids until it awards the Contract.

The City will retain the bid security submitted with the bid of the Bidder to whom an award of Contract is made, and the bid security of the next higher bid, until the Contract between the Bidder to whom award of the Contract is made and the City has been executed.

RETENTION: In the event the contract to be awarded hereunder, including Bid Specifications and other documents incorporated therein by reference, provides for the withholding of monies by the City to ensure performance of such contract, the Contractor may: a) deposit with the City as a substitute for said monies, securities listed in Section 16430 of the California Government Code or bank or savings and loan certificates of deposit, or both, equivalent to the amount withheld; or, b) request payment of retentions earned directly to the escrow agent at the expense of the Contractor, provided Contractor requests, in writing, to make such substitution within five (5) days of the date of the Notice of Award of the Contract and bears all expenses in connection therewith. Either option shall be in accordance with Public Contract Code Section 22300.

CALIFORNIA WAGE RATE REQUIREMENTS: This project is a public work under Labor Code § 1720 et seq. Pursuant to Division 2, Part 7, Chapter 1 of the Labor Code of the State of California, the Director of Public Works of the City by and on behalf of the City Council has obtained from the Director of the Department of Industrial Relations of the State of California the general prevailing rate of per diem wages, and the general prevailing rate of holiday and overtime work in the locality in which the public work is to be performed for each craft, classification or type of workers needed to perform the work.

Copies of the prevailing rate of per diem wages are on file in the office of the City Engineer, 5th Floor, City Hall, 411 West Ocean Boulevard, Long Beach, California 90802. The Contractor to whom the Contract is awarded, and its subcontractors, shall pay to all workers in the performance of the work not less than the prevailing rate of wages needed to execute the contract. Copies of schedules of prevailing wage rates may be obtained on the California Department of Industrial Relations website http://www.dir.ca.gov/dlsr. This project will be subject to the 2026-1 prevailing wage rate, as determined by the Director of the Department of Industrial Relations for the State of California. Bidders are directed to Section 7-2, “Labor,” of the Standard Specifications, and to Division H, Subsection 7-2.2, “Prevailing Wages,” for requirements concerning payment of prevailing wages, payroll records, and hours of labor.

http://www.dir.ca.gov/dlsr

Department of Public Works A-4 Specification R-7291

City of Long Beach Rebid Addendum No. 2 Division A – Notice Inviting Bids

DEPARTMENT OF INDUSTRIAL RELATIONS (DIR) COMPLIANCE: This project is subject to the following: No contractor or subcontractor may be listed on a bid proposal for a public works project (submitted on or after March 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)]. No contractor or subcontractor may be awarded a contract for public work on a public works project (awarded on or after April 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. Contractors are further cautioned that certified payrolls shall be submitted electronically directly to the Department of Industrial Relations.

CERTIFIED PAYROLL SUBMISSION TO THE CITY OF LONG BEACH: Pursuant to the provisions of Labor Code Section 1776, Contractor shall keep and shall cause each subcontractor performing any portion of the work under this Contract to keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by Contractor or subcontractor in connection with the work. Such payroll records for Contractor and all subcontractors shall be certified and shall be available for inspection at all reasonable hours at the principal office of Contractor pursuant to the provisions of Section 1776 of the Labor Code. Contractor's failure to furnish such records to City or City’s authorized Labor Compliance representative in the manner provided herein for notices shall entitle City to withhold the penalty prescribed by law from progress payments due to Contractor.

Each contractor and every subcontractor and supplier shall be required to submit certified payrolls and labor compliance documentation electronically at the discretion of and the manner specified by the City of Long Beach. Electronic submittal will be a web-based system, accessed on the World Wide Web by a web browser. Each contractor and subcontractor will be given a Log On identification and password to access the City of Long Beach reporting system. The foregoing is in addition to, and not in lieu of, any other requirements or obligations established and imposed by any department of the City with regard to submission and retention of certified payroll records for Contractor and subcontractors.

APPRENTICESHIP EMPLOYMENT (CONTRACTS OVER $30,000 ONLY): The

Contractor shall comply with Section 1777.5 of the Labor Code concerning the employment of apprentices by the Contractor or any subcontractor under the Contractor and, by submitting a Bid and executing the Contract, the Contractor stipulates that it shall so comply. Contractors employing apprentices or trainees under approved programs shall maintain written evidence of the registration of apprenticeship programs and certification of trainee programs, the registration of the apprentices and trainees, and the ratios and wage rates prescribed in the applicable programs.

Department of Public Works A-5 Specification R-7291

City of Long Beach Rebid Addendum No. 2 Division A – Notice Inviting Bids

PENALTIES: Contractor and subcontractors are subject to penalties, including, but not limited to, under Labor Code §§ 1775, 1776, 1777.7 and 1813, for failure to comply with

Labor Code § 1720 et seq. The Awarded Consultant expressly agrees to comply with the penalty provisions of California Labor Code section 1776.

(SEAL) /s/ MONIQUE DE LA GARZA

CITY CLERK, CITY OF LONG BEACH, CALIFORNIA

_____________ /s/ THOMAS B. MODICA

DATE CITY MANAGER

End of Division A – Notice Inviting Bids

Department of Public Works B-1 Specification R-7291 City of Long Beach Rebid Addendum No. 2 Division B – Instruction to Bidders

DIVISION B

INSTRUCTIONS TO BIDDERS

Please read these instructions carefully. If you do not submit a complete bid, the City may determine that your bid is non-responsive, in which case the City will reject your bid.

ATTENDANCE AT MANDATORY PRE-BID CONFERENCE: Entry of bid amounts will be accomplished electronically. Bid prices submitted on a paper bid form will not be accepted. Bidders are strongly encouraged to send an individual who is responsible for the bid, and not a runner. Bid submission processes and how to access the bidding system will be discussed at the pre-bid conference. Attendance at the pre-bid conference is mandatory. Failure to attend the pre-bid conference and follow procedures to confirm attendance shall be cause for rejection of the bid. See Division A of the Specifications for the date and time of the Pre-Bid Conference.

SUBMISSION OF BID: The bid shall be submitted online at https://longbeachbuys.buyspeed.com/bso/ keyword R-7291. Bidders must be registered on the City’s portal to access the bidding page and to download the plans and specifications. All documents to be submitted with the bid are contained in Division C of this Specification and the issued Addenda found under the online bid portal. These documents shall be scanned and uploaded with the bid. The originals of the Bidder’s Bond, and any other document which may require notarization, must be placed in a sealed envelope, clearly marked on the outside with “Specification R-7291 ALAMITOS BAY ENTRANCE CHANNEL DREDGING, DO NOT OPEN WITH REGULAR MAIL,” and these originals must be received by the City Clerk at the address shown in the Notice Inviting Bids by the time and date stated therein. These originals may be mailed or sent via package delivery service to City of Long Beach, 411 W. Ocean Blvd, Attn: City Clerk, Long Beach, CA 90802, but the City is not responsible for lost or misdirected mail. The City Clerk’s time-stamp clock is the official time for receipt of documents.

PROJECT LABOR AGREEMENT: This work is covered by a Citywide Project Labor Agreement (PLA) entered into by the City of Long Beach with the Los Angeles/Orange Counties Building and Construction Trades Council and the signatory Craft Unions.