R-7274 Belmont Pool Bid Tab.pdf

PDF 204 KB Posted

Attached to
R-7274 Belmont Plaza Pool
Solicitation number
PW-25-657
Issued by
California

About this file

This is a Tabulation of Bids document for the Belmont Plaza Pool project in Long Beach, California, issued by the Department of Industrial Relations (DIR) and Contractors State License Board (CSLB). The project, identified as R-7274 / PW-25-657, involves construction and renovation work at the pool facility. Bids were opened on October 23, 2025, with three responsive bidders submitting proposals: Bernards Bros., Inc. (San Fernando, CA), S J Amoroso Construction Co., LLC (Costa Mesa, CA), and Milender White Construction Co. (Newport Beach, CA). The project includes a base bid for all work except items specified separately, allowances for dewatering, shoring, related work, testing and permitting, and a market volatility allowance. A bid additive (A1) is available for spectator bleachers, shade structures, and expansion of the West Support Building with additional restrooms.

The base bid totals (including allowances) were $52,923,900 for Bernards Bros., Inc., $61,307,000 for S J Amoroso Construction Co., LLC, and $64,023,242 for Milender White Construction Co. With the inclusion of Bid Additive A-1, the total bids are $54,384,700, $63,317,000, and $66,351,725 respectively. The delta between the lowest and second-lowest bidder is $8,932,300. All three bids were deemed responsive. Bernards Bros., Inc. submitted the lowest bid with 77.51% subcontracted work and 22.49% self-performance, while S J Amoroso Construction Co., LLC proposed 56.59% subcontracted work and 43.41% self-performance, and Milender White Construction Co. proposed 72.71% subcontracted work and 27.29% self-performance. The basis for award is the total amount of the base bid plus Bid Alternate A-1.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIR / CSLB 1000002911 / 302007 1000000202 / 331024 2000003577 / 938970

TABULATION OF BIDS OPENED OCTOBER 23, 2025 FOR THE BELMONT Bernards Bros., Inc. S J Amoroso Construction Co., LLC Milender White Construction Co.

PLAZA POOL IN LONG BEACH, CALIFORNIA IN ACCORDANCE WITH 555 First Street 275 E. Baker St. Suite B 1401 Dove St,Ste 500 PLANS AND SPECIFICATIONS NO. R-7274 / PW-25-657 San Fernando, CA 91340 Costa Mesa, CA Newport Beach, CA 92660

Ph 818-898-1521 Ph 714-433-2326 Ph 949-724-9531

BASE BID ITEMS QTY UOM UNIT COST ITEM TOTAL UNIT COST ITEM TOTAL UNIT COST ITEM TOTAL

1 All, except as included for other bid items: Base Bid 1 LS $49,923,900 $49,923,900 $58,307,000 $58,307,000 $61,023,242 $61,023,242

Plan Sheet C1.32/Appendices C & H: Allowance--Dewatering, Shoring and Related Work, Testing and Permitting

1 AL $2,500,000 $2,500,000 $2,500,000 $2,500,000 $2,500,000 $2,500,000

3 Division D: Allowance--Market Volatility 1 AL $500,000 $500,000 $500,000 $500,000 $500,000 $500,000

BASE BID TOTAL (INCLUDING ALLOWANCES) $52,923,900 $61,307,000 $64,023,242

BID ADDITIVES

A1: Plan Sheet Nos: G-000, AA001, AA002, AA101, AA201, AA301, AA401, AA402:

Spectator Bleachers, Shade Structure and Expansion of West Support Building with Additional Restrooms

1 LS $1,460,800 $1,460,800 $2,010,000 $2,010,000 $2,328,483 $2,328,483

$54,384,700 $63,317,000 $66,351,725

Delta between 1st and 2nd Lowest bidder $8,932,300

Subcontracted $42,153,392 $35,828,616 $48,243,161 % Subcontracted 77.51% 56.59% 72.71%

% Self Performance -No Minimum 22.49% 43.41% 27.29% Responsive Bid: YES YES YES

BASIS FOR AWARD: TOTAL AMOUNT BASE BID + BID ALTERNATE NO. A-1 (TOTAL BID)