Questionaire _11_06_2024.docx
DOCX document 54 KB Posted
- Solicitation number
- PE-64496-NONST-2025-000000030
- Issued by
- Dekalb County, Brooklet City, Georgia
About this file
The document is a pre-bid conference Q&A for a state and local government contract opportunity for the cured-in-place pipe (CIPP) rehabilitation of the corrugated metal pipe (CMP) Low Water Drain (LWD) at Murphey Candler Lake Dam in Brookhaven, Georgia. The project is being solicited by the City of Brookhaven's Department of Public Works. Key details include a mandatory/optional pre-bid conference on October 21, 2024, a 150-day substantial completion timeline that may be extended for material lead times, requirements for maintaining minimum downstream flow, dewatering plans and discharge points, and procedures for addressing existing sluice gates and pipes. The contractor will be responsible for providing backup pumps, conducting 24/7 monitoring, and completing various repair and vegetation removal work.
The contract documents include drawings, technical specifications, standard details, and pay items. Pricing terms are not provided, but the document indicates there may be set-aside requirements or preferences. Funding information is not included, but the project appears to be a local government initiative without any direct state or federal involvement noted.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Public Q&A Pre-Bid Conference IHC Construction Companies, LLC, Oct 21, 2024 7:58 AM EDT, Not Public - Pending
Invitation to Bid, page 1 of 36 states "***Mandatory/Optional Pre-Bid Conference***". Please confirm the pre-bid conference is mandatory.
· Updated with Addendum: Optional – Procurement
Exhibit A - General Conditions IHC Construction Companies, LLC, Oct 21, 2024 7:59 AM EDT, Not Public - Pending
In the Invitation to Bid, page 6 of 36 states "Placeholder for Exhibit A - General Conditions". Please provide Exhibit A - General Conditions.
· Exhibit A – revised with Addendum 1 – Procurement
Dewatering IHC Construction Companies, LLC, Oct 21, 2024 1:58 PM EDT, Not Public - Pending
There is no information regarding anticipated flow rates to size the cofferdam or dewatering/bypassing scope. Please provide all information available on the inflow rates and discharge rates at various levels (drought, “normal”, 1” storm event, 2” storm event, 3” storm event, lake volume, lake bottom topography, etc).
The estimated mean annual flow and two-year peak inflow into the reservoir is 3 cfs and 264 cfs, respectively, per the USGS StreamStats application. Please note that this information is for planning purposes only and the actual flow conditions may vary.
The selection of the appropriate inflow event to size the cofferdam and/or dewatering/bypassing pumping is the responsibility of the Contractor. The Contractor is responsible for submitting a Dewatering Plan to the City/Engineer. Additional information is as follows and has been provided for planning purposes only.
Drainage Area – 2.38 Sq. miles Normal Pool Volume: 276 ac-ft A figure is included in Exhibit L providing approximate lake depths from a bathymetricscan conducted following dredging operations in 2020.
Dewatering - Minimum Flow Rate IHC Construction Companies, LLC, Oct 21, 2024 1:59 PM EDT, Not Public - Pending
Specification 31 23 19, 1.2, A., 1. states “It is essential to the operation of the existing stream that there be no interruption in the flow of water throughout the duration of the Project.”. What is the minimum flow that must be maintained?
The Contractor shall maintain the mean annual 7-day 10-year low (7Q10) flow (0.12 cfs) as the minimum flow in the stream downstream of the dam.
Dewatering Discharge Pipeline IHC Construction Companies, LLC, Oct 21, 2024 2:00 PM EDT, Not Public - Pending
Specification 31 23 19, 3.1, C., 3. states “Confine the bypass discharge pipeline to the area within the temporary construction area and construction easement, for construction of the pipeline.”. The limits of construction are constrained to two separate areas (one within the lake and another around the existing CMP). This is not currently any area within the construction limits that allows the bypass discharge piping from the lake to a discharge point outside the lake.
Please clarify the intended discharge point, and expand Construction Limits as necessary. One option maybe to place discharge piping across the concrete spillway (under the bridge), and shift piping as necessary during construction to allow crack repair.
Bypass piping will need to be laid out outside of the construction limits. The proposed approach is acceptable to the City. The intended discharge point will be slightly downstream of the spillway.
Backup Pumps IHC Construction Companies, LLC, Oct 21, 2024 2:03 PM EDT, Not Public - Pending
Specification 31 23 19 mentions back ups (1.4, 7. Standby power generator; and 2.3, C. back-up pumps). What capacity of backup is required (100%, 50%, etc.)? Paragraph 1.7 B. doesn’t imply spare pumps/generators are required as it allows for spares (backups) to available within 24 hours. Please clarify if backup pumps are required to be onsite, or available within 24 hours.
Backup Pumps should be sized to be capable of bypassing flow as necessary to perform the Work.
Dewatering 24/7 Monitoring IHC Construction Companies, LLC, Oct 21, 2024 2:03 PM EDT, Not Public - Pending
Specification 31 23 19, 1.7, A. requires an operator on hand at all times when the pumps are operating (extra project cost). Is a remote monitoring system that notifies the contractor/operator (and other people/parties as deemed necessary by the Engineer and/or City) acceptable instead of having an operator on site 24/7 for several months when pumps are running?
Yes.
Sluice Gate Release for Schedule IHC Construction Companies, LLC, Oct 21, 2024 2:04 PM EDT, Not Public - Pending
Drawing S-102 calls for the existing 24”x24” Sluice Gate to remain, however the bid form calls for a new gate which matches spec 33 01 30.72, 2.2 (calls to replace if damaged or inoperable). Please confirm the City will direct/authorize the contractor to purchase the gate and appurtenances as one of the first actionable items on the project (due to lead times), and then if the gate is determined not needing to be replaced, the contractor will not install the gate and supply the gate to the City instead. Note only replacing parts of the gate won’t provide the City with a warranty of the complete gate assembly.
Confirmed.
Project Schedule - Gate Lead Time IHC Construction Companies, LLC, Oct 21, 2024 2:12 PM EDT, Not Public - Pending
The project schedule is only 150 days to substantial completion, however Heyward (Rodney Hunt sluice gate manufacturer’s rep.) says currently 22 weeks is the approximate current lead time for a gate. If we can use the existing gate submittal to expedite (and not generate a new submittal) and assume 1 week for engineer review and approval, and release same day of approval then 22 weeks for fabrication, then the gates would deliver ~161 days after NPT which is 11 days after substantial completion. Note that if the existing submittal cannot be used (unknown at this time if existing materials match new material specs – would add up to 8 weeks for Rodney Hunt to prepare a new submittal). Please add additional time to the substantial completion period (revise to 210 days), or add an administrative period to allow procurement of the gate (60 days or more). Ideally we would like to have the gate delivering to site when the lake is being drained so it could possibly be utilized as a means (or backup means) to control lake water elevation.
Time extensions due to fabrication lead times for specific products as indicated in the Contract Documents will be considered.
Existing JB Sluice Gates IHC Construction Companies, LLC, Oct 21, 2024 2:16 PM EDT, Not Public - Pending
On drawing CP-101, JB (2498) has two existing sluice gates (6” or 8”?) inside of it that will interfere with the CIPP work.
a. These two gates will need to be removed during the CIPP work. Please confirm this is acceptable.
This is acceptable.
b. Do these gates need to be reinstalled after CIPP work is complete?
Yes
c. Are there any existing drawings on the gates or pipes their connected to/isolating? If not please provide information available on the two pipes (description/ size/ service/ intended function, etc).
We do not have record drawings. These gates are closures to block off toe drains when the low water drain is operated to prevent pressurized flow in the toe drain to the dam embankment.
d. During the period the gates are remove, can these two pipes be plugged to ensure no water enters the JB?
These should be plugged as needed to complete the work.
9-B Point Repairs 30-in CMP IHC Construction Companies, LLC, Oct 21, 2024 2:21 PM EDT, Not Public - Pending
Specification 33 01 30.72, 3.1, F. states “If inspection reveals an obstruction that cannot be removed by conventional cleaning equipment, the Contractor shall make a point repair excavation to uncover and remove or repair the obstruction prior to rehabilitation.” On drawing CP-101 there is a note stating “Clean and Point Repair existing 30” CMP per specification 33 01 30.52 and 33 01 30.72 prior to CIPP lining” and points to two locations.
a. Bid Item 9-B Pint Repairs, 30-IN CMP has a quantity of 1 EA. Is there one location expected? Is this the same specification and drawing mentioned earlier?
These callouts were specifically requested by GASDP, but they do no indicate any identified sections that need repair. They are general to indicate that the contractor should confirm if any point repairs are necessary based on CCTV inspection prior to lining.
Bid Item #14 Rip Rap Type 3, 24 IN IHC Construction Companies, LLC, Oct 21, 2024 2:23 PM EDT, Not Public - Pending
Bid Item #14 Rip Rap Type 3, 24 IN. The measurement and payment lists a significant amount of work to be included which appears to be included in other bid items already (dewatering, bypass pumping, support of sewers, etc.). Please confirm the only scope of work to be included is related to the last sentence “access the work area around the riser by placing additional rip rap along the upstream slope within the limits of construction to the height of the existing retaining wall “. Which is primarily install and removal of rip rap, removal and restoration of features associated with accessing from the road including but not limited to road guard rail, grassing, concrete sidewalk, retaining wall rail, etc. Please consider revising the language of the item to be clear on its use.
Confirmed. This item is specifically pertaining to installing additional Rip Rap in order to access the work area around the riser from the upstream slope. The incidentals listed are specific to that work only and do not include items considered incidental to other Unit Prices.
Pay Item 300 - Remove All Vegetation on Upstream Slope IHC Construction Companies, LLC, Oct 21, 2024 2:25 PM EDT, Not Public - Pending
Pay Item 300 - Remove All Vegetation on Upstream Slope, Sheet C-001. No work is called out on C-001 related to this scope. Please clarify.
This maintenance activity is essentially clearing and grubbing along the wave protection on the upstream slope of the dam above the water line along the length of the dam to facilitate inspections and prevent future maintenance issues. This will include hand pulling small woody vegetation and backfilling holes as necessary. From previous inspections, trees/shrubs present are small caliper (i.e., ≤ 3” dia.).
Pay Item 800 - Repair Broken Concrete IHC Construction Companies, LLC, Oct 21, 2024 2:25 PM EDT, Not Public - Pending
Pay Item 800 – Please clarify what “Repair Broken Concrete” scope is included in this item. The joint and crack repair/sealant is defined, but what scope and quantity should be assumed for the repair broken concrete.
Repair of broken concrete will consist of sealing cracks to prevent widening, grouting and patching holes as needed. Prevalent pages from the most recent inspection report detailing the extent of this work have been provided in Exhibit L.
Pay Item 900 – Rip Rap IHC Construction Companies, LLC, Oct 21, 2024 2:26 PM EDT, Not Public - Pending
Pay Item 900 – Rip Rap. Is this exclusively the work shown on C-002 (NW side of spillway at lake) and detailed on C-003 (excavation and disposal, fabric, #3 Stone, Rip Rap Type 1)? If not please clarify what bid item is used for.
This would be for the work shown on the NW Side of the Spillway (See annotation Sheet C-002). Rip Rap used/needed for repairs on the NE Side of the Spillway (see annotation Sheet C-002) should be included with the Lump Sum price under Item 600.
Pay Item 1000 - Install and Maintain Orange Tree Barrier Fencing IHC Construction Companies, LLC, Oct 21, 2024 2:26 PM EDT, Not Public - Pending
Pay Item 1000 - Install and Maintain Orange Tree Barrier Fencing Around Work Areas. Since unit is lump sum please confirm the intent is to be used to define/limit access by the public to the work areas of the maintenance.
Confirmed.
Remove all trees within 3’ of spillway walls IHC Construction Companies, LLC, Oct 21, 2024 2:29 PM EDT, Not Public - Pending
Drawing C-001 calls to remove all trees within 3’ of spillway walls. Is this just cutting the tree off a few inches above the ground and treating with herbicide? What all is involved in the scope? It appears from a site visit there are several decent size trees with roots that have grown in and under existing features (sidewalks, retaining walls etc.) and removing the roots would be fairly extensive amount of work and cost.
Trees and stumps should be removed and ground as close to the ground surface as possible (1”-2”) where roots have grown in under existing hardscape. Cut stumps should be treated with 50% solution of glyphosate or triclopyr. All herbicides shall be applied by hand applicator and in accordance with label instructions, state and federal laws and shall be conducted by or under the supervision of experienced, licensed applicators.
CP-101 construction limits IHC Construction Companies, LLC, Oct 21, 2024 2:31 PM EDT, Not Public - Pending
Drawing CP-101 construction limits are fairly tight against the mud matting and drain structure. Please consider adding additional area to the limits as currently there is not enough space to install the lake drain/dewatering pumps or install a cofferdam.
The City will consider minor adjustments to the limits shown on the plans as necessary for access and dewatering operations.
Overnight lane closure IHC Construction Companies, LLC, Oct 21, 2024 2:32 PM EDT, Not Public - Pending
Specification 34 41 16.10, 3.1, A. states “All roadwork and lane closures shall be limited to between the hours of 7:00 am and 4:00 pm, Monday through Friday.”
However drawing CD-101, note 7 could imply the lane closure can last overnight without a flagman. Please confirm if the lane closure is limited to 7am to 4pm in most cases (please note special cases may require longer hours when doing CIPP work).
Confirmed. Where Flagmen are not available, an off-duty officer should be retained to assist traffic control during overnight operations.
Use of Police Officer(s) IHC Construction Companies, LLC, Oct 21, 2024 2:32 PM EDT, Not Public - Pending
Specification 34 41 16.10, 3.2, E. states “Use of Police Officer(s) shall be used when safety necessary, in areas of high traffic volume, installation in roadways, road closures and lane closures, or in areas of low visibility.” Please confirm a police officer will be required during a single lane closure.
See response above. It is not anticipated that a Police officer will be required to supplement the traffic control plan for single lane closure when flagging operations are active.