This document is an Exhibit K Bid Schedule for ITB 24-022, the Low Water Drain CIPP Rehabilitation project for the Murphey Candler Lake Dam in the City of Brookhaven, Georgia. The project involves the cured-in-place pipe (CIPP) rehabilitation of a corrugated metal pipe (CMP) low water drain, as well as related site work such as mud mats, mulching, seeding, silt fencing, tree protection, a construction entrance, flowable fill, sidewalk replacement, guardrail, rip rap, grading, and other miscellaneous items. The bid schedule lists 27 line items with various quantities and a total bid price to be provided by the contractor. The overall project is being managed by the City of Brookhaven Department of Public Works.
The bid schedule does not provide pricing details, but notes that unit prices should be provided for items without specified quantities. An allowance of $10,000 is included for repair, removal, or lowering of an abandoned standpipe. The project will be funded through the City of Brookhaven, and no set-asides or incumbent information is provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questionaire 2_Addendum 3.docx | DOCX document | |
| ITB No_ 24_022_Addendum 3.pdf | ||
| ITB No_ 24_022_Addendum 4.pdf | ||
| RFP No_ 24_022_Addendum 2.pdf | ||
| Questionaire 1 _Addendum 2.pdf | ||
| ITB No_ 24_022_Addendum 2.pdf | ||
| L2_Technical Specifications for MCD CIPP Reha.pdf | ||
| Document Takers_2024_11_12_planholders list.xlsx | XLSX spreadsheet | |
| 24_022_Exhibit K_rev1.pdf | ||
| Questionaire _11_06_2024.docx | DOCX document | |
| ITB No_ 24_022_Addendum 1.pdf | ||
| 24_022 2024 Low Water Drain Rehab Murphey Can.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT K
BID SCHEDULE
ITB 24-022, Low Water Drain CIPP Rehabilitation, Murphey Candler Lake Dam
Item Description Qty Unit Unit Price Total Price
1 Mobilization 1 LS
2 Mud Mats 375 SY
3 Mulch Complete 850 SY
4 Sodding and Permanent Seeding Complete 850 SY
5 Temporary Seeding Complete 850 SY
6 Silt Fence Complete, Type C 800 LF
7 Tree Protection Fence Complete 100 LF
8 Construction Entrance Complete 1 EA
9-A Cured In Place Pipe Rehabilitation, 30-IN CMP 165 LF
9-B Point Repairs, 30-IN CMP 1 EA
10 Flowable Fill 5 CY
11-A Control of Water (Dewatering and Construction) 130 DAY
11-B Control of Water (Reservoir Refilling) 90 DAY
12 Sidewalk Replacement 35 SY
13 W-Beam Guardrail 55 LF
14 Rip Rap, Type 3, 24-IN Thickness 65 SY
15 Riser Modifications 1 LS
16 Grading Complete 1 LS
17 Plastic Filter Fabric 75 SY
18 Removal of Existing Storm Drain Pipe 5 LF
19 Traffic Control 1 LS
Sluice Gate Structure System Installation, Complete
(City to provide Hoist Head, Stem Guides, Pedestal, Gate, Operating Stem)
1 LS
Stem Guides Complete - Sluice Gate Structure
Component System
1 EA N/A -
Pedestal Complete – Sluice Gate Structure
Component System
1 EA N/A -
Operating Stem Complete – Sluice Gate Structure
Component System
1 EA N/A -
Gate Complete – Sluice Gate Structure Component
System
1 EA N/A -
25 Compost Filter Sock 2000 LF
Allowance – Repair/Remove/Lower Abandoned
Standpipe
1 LS $10,000.00 $10,000.00
27 LiDAR Survey – Dewatered Lake Bed (Area = 40 Ac) 1 LS
Low Water Drain CIPP Rehabilitation - Total Bid Price
* Please provide a unit price for items listed in the table above that do not have quantities.
*** Include completed bid schedule with your bid.
File details come from the government source that posted it. Updated .