This is a Quality Assurance Surveillance Plan (QASP) for the FCDAS Boilers Replacement Construction project at the Fairbanks Command and Data Acquisition Station. The document establishes the Government's standard surveillance methodology for monitoring contractor performance and ensuring compliance with contract requirements.

The QASP identifies three primary performance objectives: (1) replacement of commercial boilers in the Facilities Building and Powerhouse, plus re-orientation of an existing boiler; (2) boiler start-up, commissioning, training, and preparation of Operations and Maintenance manuals; and (3) integration of boilers with the Building Automation System (BAS) including lead-lag configuration. All performance objectives reference PWS Section I-02 and require compliance with applicable specifications and industry standards. Surveillance methods include review of submittals for boilers, burners, and accessories; verification of startup and commissioning plans; review of training materials and O&M manuals; and physical verification of boiler installation and BAS integration with lead-lag setup demonstration. The QA personnel will conduct periodic assessments at critical project stages, develop a checklist with evaluation procedures, document all submittals and reports in a log, provide Government comments to the contractor for revisions, and determine whether contractor performance is acceptable or sub-par. The QA is responsible for accepting or declaring services as sub-par and determining payment amounts due to the contractor.

View the file

Other files for this federal contract opportunity

Other files attached to NOAA/FCDAS Replacement of Two (2) Non-Operational Boilers, newest first.
File Type Posted
FCDAS Boilers Replacement QA_Amendment Ver 3.pdf PDF
FCDAS Boilers Replacement QA_Amendment Ver 2.docx.pdf PDF
FCDAS_Facilities Building_Amendment 0001.pdf PDF
FCDAS_Power House_Amendment 0001.pdf PDF
DBA Wage Determination.pdf PDF
RFQ_1332KP26Q0033 Boilers Replacement.pdf PDF
PWS FCDAS Boilers Replacement.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY ASSURANCE SURVEILLANCE PLAN

FCDAS Boilers Replacement Construction

Fairbanks Command and Data Acquisition Station (FCDAS)

PURPOSE

This Quality Assurance Surveillance Plan (QASP) provides a standard of surveillance for monitoring the requirements of the above listed contract and a systematic approach for conducting surveillance over the performance aspects of the effort. The QASP is for the use of Government Quality Assurance (QA) personnel to insure standards of the contract are being met.

The QASP provides a systematic method to evaluate the services the Contractor is required to furnish, but not the details of how the Contractor accomplishes the work. This plan uses inspections and customer feedback as the primary evaluation criteria. This surveillance assures the Government that the Contractor’s performance is acceptable.

Any noncompliance with contract performance requirements is deemed ―sub-par. The term ―sub-par refers to a support service that does not meet the standard of performance specified in the contract. The QASP is based upon the premise that the Contractor, not the Government, is responsible for management and quality control actions to meet the terms and conditions of the contract. The methods of surveillance recognize that unforeseen and uncontrollable problems do occur however the Contractor shall employ adequate resources to identify and correct these problems. Effective management and use of a quality control plan will allow the Contractor to operate within the specified surveillance requirements.

Government’s quality assurance methods are expected to be objective, fair, and consistent in evaluating Contractor performance against the standards.

PROCEDURE

Quality Assurance Schedule The QA will develop a checklist with evaluation procedures to use when conducting surveillance of the Contractor’s performance as identified in the QASP.

Surveillance

The QA will assess Contractor’s completion of the tasks outlined in the Performance Work Statement (PWS) from review of product submittals and datasheets and verifying that the equipment and materials installed are in accordance with contract drawings and specifications. Functionality and proper operation of the installed equipment, servers, workstations, sensors, wiring, system notifications and alarms etc.

shall be verified through testing and physical verification. The QA will develop an opinion of the task completion and the quality of the work completed based on thorough review of submittals, testing reports, pictures, monitoring and control of sensors, controllers and equipment utilizing Building Management System (BMS) through software and Human Machine Interface (HMI). The QA will determine whether or not the performance meets the standards contained in the contract.

First, the submittals, test reports, shop drawings and installed equipment, sensors, wiring and controllers shall be compared to contract specifications and drawings. Then the review will focus on completeness of work, in individual buildings, as well as the quality of the completed work. A log will be developed to document review of all reports and submittals. Government comments on the submittals shall be provided to the Contractor asking him to revise reports and other submittals to address provided comments or provide clarification to the Government regarding the comments.

The QA is required to accept or declare as sub-par Contractor services and determine amount of payment due to the Contractor.

METHODS OF SURVEILLANCE

Assessments

Periodic assessments will occur on a pre-determined basis to interact with the Contractor at critical stages of the project such as after field surveys and submission of product submittals as well as installation and integration of Building Management System (BMS) components into the new BMS system. The results of periodic assessments will be used to covey to the Contractor that their performance is sub-par and to improve quality of produced deliverables.

The QA is the point of contact for the QASP and shall collect all customer feedback and comments. All comments and resultant resolutions shall be documented and become a permanent part of the QA surveillance records. Valid, documented negative feedback may be used as the basis for asking the Contractor to improve their performance and positive feedback may be used to encourage the Contractor to continue performing above expectations.

Surveillance Guide

The QASP Guide defines the performance objective and shows the pertinent portion of the statement of work, performance metric and the method of surveillance.

Performance Objective PWS

Reference Performance Standard Method of Surveillance

Replacement of Commercial Boilers in the Facilities Building and the Powerhouse plus Re-Orient an Existing Boiler.

I-02

Applicable Specifications and Industry Standards

Review of Submittals for Boilers, Burners and other Accessories. On-site Physical Verification of Installation.

Boilers Start-Up, Commissioning, Training and Operations and Maintenance (O&M) Manuals

Applicable Specifications and Industry Standards

Review of Submittals for Start-up and Commissioning Plan as well as Training Materials and O&M Manuals.

Integration of Boilers with Building Automation System (BAS) plus Lead- Lag Configuration.

Applicable industry standards

Physical Verification of Boilers in the BAS and Demonstration of Lead-Lag Set-Up.

QUALITY ASSURANCE SURVEILLANCE PLAN
FCDAS Boilers Replacement Construction
Fairbanks Command and Data Acquisition Station (FCDAS)
PROCEDURE
Surveillance
METHODS OF SURVEILLANCE
Surveillance Guide