QA_#4_9-30-2024_(1)_FENCE.pdf

PDF 362 KB Posted

Attached to
Grayton Beach Community Center
Solicitation number
ITB 24-35
Issued by
Walton County, Florida

About this file

This is a Question and Answer document from Walton County, Florida regarding Invitation to Bid (ITB 24-35) for the Grayton Beach Community Center construction project. The document addresses a bidder inquiry concerning item #3 on the bid sheet, which involves the removal and relocation of 225 linear feet of Cedar Split Rail Fence. The response clarifies the fence type and provides an image identifying the existing fence location and the new relocation site marked in red. The project encompasses construction of a 2,000-square-foot restroom facility, roadway improvements to Hotz Avenue, beach vehicle entrance enhancements at DeFuniak Street, and a 6-foot-wide beach access timber/composite decking boardwalk. A non-mandatory pre-bid conference was held on September 19, 2024, with bid submissions due by October 14, 2024, at 3:00 pm. The contract duration is 300 days for substantial completion, with an additional 30 days for punch list completion.

The project requires a licensed General Contractor in accordance with Walton County Ordinance 2009-01, with the contractor responsible for obtaining a Walton County Building Permit. The work will be performed on county-owned property identified by parcel ID #08-3S-19-25030-003-0011 in Grayton Beach, Florida. Liquidated damages penalties of $6,204 per calendar day apply for delays in substantial completion and $3,102 per calendar day for punch list completion delays. Bidders must provide a bid bond, proof of licenses, and compliance certifications. The contract includes an alternate bid option for DeFuniak Street resurfacing and striping, with the county reserving the right to reject any or all submissions based on a lump sum bid evaluation methodology.

View the file

Other files

File Type Posted
Grayton_Beach_Community_Center_(Addendum_#1_Revision).pdf PDF
Grayton_Beach_Community_Center_(Addendum_#1_Revision).pdf PDF
QA_#4_9-30-2024_(1)_FENCE.pdf PDF
50150591_Bid_Schedule_8-21-2024.pdf PDF
50150591_Bid_Schedule_8-21-2024.pdf PDF
Contract_No._24-35.pdf PDF
Contract_No._24-35.pdf PDF
Public_Construction_Bond.pdf PDF
Public_Construction_Bond.pdf PDF
STRUCTURAL_BID_TDC_GRAYTON_BEACH.pdf PDF
Landscape_Plan_For_Bid.pdf PDF
Landscape_Plan_For_Bid.pdf PDF
STRUCTURAL_BID_TDC_GRAYTON_BEACH.pdf PDF
24019_PLUMBING_BID.pdf PDF
240724_GRAYTON_BEACH_PAVILION_RELEASE_FOR_BID.pdf PDF
2215-GRAYTON_BEACH_BID_240822.pdf PDF
Alternate_Bid_Item_DEFUNIAK_ST_DRAFT_PLANS.pdf PDF
50150591_ALTERNATE-Bid_Schedule_8-21-2024.pdf PDF
24019_MECHANICAL_BID.pdf PDF
50150591_Grayton_Beach_RR_2024-8-21_Civil_Bid_Set.pdf PDF
24019_MECHANICAL_BID.pdf PDF
50150591_Grayton_Beach_Restroom_Specs_8-21-2024.pdf PDF
Alternate_Bid_Item_DEFUNIAK_ST_DRAFT_PLANS.pdf PDF
2215-GRAYTON_BEACH_BID_240822.pdf PDF
24019_PLUMBING_BID.pdf PDF
240724_GRAYTON_BEACH_PAVILION_RELEASE_FOR_BID.pdf PDF
50150591_Grayton_Beach_Restroom_Specs_8-21-2024.pdf PDF
50150591_Grayton_Beach_RR_2024-8-21_Civil_Bid_Set.pdf PDF
50150591_ALTERNATE-Bid_Schedule_8-21-2024.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

4. Fence Sep 25 2024 at 10:01 AM

Question: #3 on the bid sheet . What type of fence has to be removed and relocated. 225 LF. And where is this being relocated too.

RESPONSE: Please see below image of existing fence (Cedar Split Rail Fence).

Below is location of relocated fence (see in red).