Q1_2025_-_Business_Case_-_CVG_Centre_Roof_Replacements.pdf

PDF 267 KB Posted

Attached to
CVG Centre Roof Replacement & Fall Protection
Solicitation number
25-053-ITB
Issued by
Bell County, Kentucky

About this file

This is a business case document and related state and local contract opportunity from the Kenton County Airport Board (KCAB) in Kentucky for the CVG Centre Roof Replacement & Fall Protection project. The project involves the replacement of four identified roof sections at the CVG Centre that have exceeded their useful life and are in poor condition. A pre-bid meeting and site visit are scheduled for Thursday, August 21, 2025 at 10:00 am at CVG Centre, Admin. Offices, 77 Comair Blvd., Erlanger, KY 41018. Written questions must be submitted by 11:59 pm on Tuesday, August 26, 2025, with answers posted no later than Thursday, August 28, 2025 at 11:59 pm. Bids are due by Thursday, September 4, 2025 at 2:00 pm, with no late submissions accepted unless extended by addendum. The project is scheduled for execution between March 2025 and June 2025, pending weather conditions.

The total project cost is estimated at $2,033,484, consisting of design costs of $194,748, construction and installation costs of $1,593,396, a minimum 10 percent contingency of $159,340, force labor of $85,000, and miscellaneous costs of $1,000. The project is funded through capital expenditure (CapEx) funding. The business case was approved by multiple stakeholders including Candace McGraw, Dilwyn Gruffydd, Bill Siemer, Tim Haizlip, and Tim Dodson between January 27 and January 29, 2025. The project aligns with sustainability and master plan objectives and addresses the need to replace aging roof sections before age-related failures occur, as an alternative to continued monitoring and reactive repairs.

View the file

Other files

File Type Posted
CVG_Centre_Roof_Replacement_&_Fall_Protection_(Addendum_#3_Revision).pdf PDF
Photo_Binder_-_Addendum_2_08.26.2025.pdf PDF
Technical_Specifications_-_Addendum_2_08.26.2025.pdf PDF
25-053-ITB_Pre-Bid_Sign_In_Sheets.pdf PDF
25-053-ITB_Pre-Bid_Meeting_Agenda.pdf PDF
25-053-ITB_CVG_Centre_Roof_Fall_Protect_Anticipated_Solutions.pdf PDF
25-053-ITB_CVG_Centre_Roof_Replacement_&_Fall_Protection_-_Exhibit_B_-_Contract_&_Bonds.pdf PDF
25-053-ITB_CVG_Centre_Roof_Replacement_&_Fall_Protection_-_Exhibit_A_-_Proposal_Forms.pdf PDF
CVG_Center_9.30.24_Roof_Assessment.pdf PDF
25-053-ITB_CVG_Centre_Roof_Replacement_&_Fall_Protection_-_Ad.pdf PDF
Original_Building_Plans_T2001-0205_-_COMAIR_General_Office_Building_-_CVG_Centre.pdf PDF
Fall_Protection_Assessment_0116304-CVG_Centre.pdf PDF
Q1_2025_-_Business_Case_-_CVG_Centre_Roof_Replacements.pdf PDF
Affirmative_Action_Certification.docx DOCX document
Disclosure_of_Lobbying_Activities_Certification.docx DOCX document
NonSegregated_Facilities_Certification.docx DOCX document
EEO_Certification.docx DOCX document
Certification_of_Offeror-Bidder_Regarding_Tax_Delinquency_and_Felony_Convictions.docx DOCX document
Non_Debarment_or_Suspension_Certification.docx DOCX document
Buy_American_Certification-Equipment-Building_Projects.docx DOCX document
Buy_American_Certification-Construction_Projects.docx DOCX document
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CVG Centre Roof Replacement

Current Situation/Background Information

The roof sections on the CVG Centre, excluding one section, were installed in 1999 and have exceeded their anticipated life expectancy. Through routine maintenance and inspections, the majority of sections are identified as being in poor condition and recommended for replacement.

Project Definition

Project Information: Replacement of 4 identified sections of the CVG Roof that are at or past their useful life.

The business objectives: Replace the roof of the CVG Centre before the development of age and condition related failures.

Project Approach

Obtain quotes to remove the existing roofing material, perform any needed deck repairs, and install new roofing per scope specifications.

Alternatives

As an alternative we could continue to monitor, and assess the roof on a bi-annual basis and perform repairs as needed. This may require fast tracking replacements of large sections of the roof as age related failures occur.

Recommendation

Solicit bids to replace 4 of the roof sections identified as past their useful life to avoid age related failures.

Cost

Design: $194,748

Construction/Installation: $1,593,396

Contingency (min 10%): $159,340

Force Labor: $85,000

Miscellaneous: $1,000

Total Cost: $2,033,484

Project Funding

CapEx

Project Schedule

March 2025 - June 2025 weather dependent

Known Risks & Limitations

N/A

Approvals:

Candace McGraw

Dil Gruffydd

Concurrence Leader: Bill Siemer

Executive Sponsor: Tim Haizlip

Business Unit Leader: Tim Dodson

Sponsor/Originator: Tim Dodson

Strategic Plan Fit Sustainability FitMaster Plan Fit

Tim Dodson (Jan 27, 2025 09:57 EST)

Tim Haizlip (Jan 27, 2025 16:55 EST)

Dilwyn Gruffydd (Jan 28, 2025 18:05 EST)

Candace McGraw (Jan 29, 2025 18:04 GMT+1) Candace McGraw https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAjWn6QCU3Te880yKixp0quaWc3UKxXhWU https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAjWn6QCU3Te880yKixp0quaWc3UKxXhWU https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAjWn6QCU3Te880yKixp0quaWc3UKxXhWU https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAjWn6QCU3Te880yKixp0quaWc3UKxXhWU https://cvgairport.na2.adobesign.com/verifier?tx=CBJCHBCAABAAjWn6QCU3Te880yKixp0quaWc3UKxXhWU

2025-07-18T20:47:15+0000
Certified by Adobe Acrobat Sign

File details come from the government source that posted it. Updated .