Q_As Moyer Site Visit_6.28.23_sk.pdf

PDF 241 KB Posted

Attached to
Moyer Bridge Installation - Salmon-Challis National Forest Federal contract opportunity
Solicitation number
1282B123R0077
Issued by
Department of Agriculture Forest Service

About this file

This document contains questions and answers from a pre-bid meeting for the Moyer Bridge Installation project on the Salmon-Challis National Forest. The project involves constructing a bridge over a stream located in Salmon, Idaho, with instream work dates of July 15 to August 15, 2024. Key details include clarification that contractors can conduct their own survey work and are responsible for fish screening on any pumps used outside the dewatered area. The document also notes the approximate round trip mileage to the material staging area, confirms an area is available for equipment staging, and discusses requirements for containment of fuels and coordination for fish salvage and sediment monitoring during dewatering and rewatering activities.

View the file

Other files for this federal contract opportunity

Other files attached to Moyer Bridge Installation - Salmon-Challis National Forest, newest first.
File Type Posted
Attachment 9 Appendix D Past Performance Questionnaire.pdf PDF
Attachment 7 MOYER MATERIALS VICINITY MAP.pdf PDF
Attachment 5 Project Design Features.pdf PDF
Attachment 3 PRELIM MOYER CREEK FSSS.pdf PDF
Attachment 2 Statement of Work.pdf PDF
Attachment 10 Moyer Creek Bridge Shop Drawings APPROVED.pdf PDF
1282B123R0077.pdf PDF
Attachment 4 G-074 MOYER CREEK FINAL Drawings.pdf PDF
Attachment 8 DBWage Determination ID20220087_5.12.23.pdf PDF
Attachment 6 MOYER ACCESS MAP.pdf PDF
Attachment 1 Schedule of Items.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Moyer Pre-Bid Mee�ng 06/28/2023

Ques�ons and Answers:

Bridge Loca�on: The bridge is located in Salmon and will require delivery by the contractor, although the abutments need to be constructed as part of this contract package.

Ques�ons and inquiries from the Contractors during the pre-bid mee�ng.

1. Are the instream work dates correct?

a. A: Yes, July 15 to August 15 2024 are the correct dates for the instream work. Work not within the channel may be performed outside the instream window.

2. What are the an�cipated flows for implementa�on?

a. A: Approximately < 10 cubic feet per second

3. Are contractors required to have addi�onal fire suppression equipment like water wagons during the implementa�on given it is in a drier �me of year?

a. A: No, basic requirements for fire ex�nguishers, shovels, and spark arrestors required in the contract are sufficient.

4. Are there control points located in proximity to the site for survey purposes?

a. A: Yes, they will be flagged prior to implementa�on by the Forest Service

5. Can contractors conduct their own survey to ensure eleva�ons are consistent?

a. A: Yes, they can and are expected to conduct their own survey.

6. Do we have to have a fish screen for pumps?

a. A: Yes, for dra�ing associated with road compac�on if dra�ing occurs outside of the dewatered area. Sump pumps within the dewatered area may not require screens if there is no chance that fish can move into the sump.

7. What is the round trip mileage from the bridge site to the Opal Pit?

a. A: It is approximately 14.1 miles from the pit to the site, round trip is es�mated as 28.2 miles.

8. Can we close the road to the bridge?

a. Yes, we may need to make minor accommoda�on to allow access to a couple of private parcels but the landowners have indicated that they are willing to forego access during construc�on with the excep�on of an emergency.

9. What area is available for staging materials and equipment.

a. The flat area on the east side of the site is available for these purposes.

10. It was noted that a sample dewatering plan was not included in the drawings, is there a sample plan?

a. We didn’t include a sample dewatering plan; the contractor is s�ll required to submit for approval their own plan which gives addi�onal flexibility in designing their workspace. It was noted in the field that we expected the most likely diversion would be on the east side of the channel

Discussion items at the site visit:

Containment of fuels and motorized equipment- Pumps and other motorized and fuel stored adjacent to the stream and having the poten�al to discharge petroleum products into the stream need to be contained in a manner that will capture spills or overfills.

Coordina�on of fish salvage and sediment monitoring associated with dewatering and rewatering of the channel- Contractor will need to communicate �ming of these opera�ons in advance of performance to ensure required monitoring and salvage occur. FS is commited to providing these services in a manner that minimizes delay to the contractor.