Attachment 2 Statement of Work.pdf

PDF 264 KB Posted

Attached to
Moyer Bridge Installation - Salmon-Challis National Forest Federal contract opportunity
Solicitation number
1282B123R0077
Issued by
Department of Agriculture Forest Service

About this file

This statement of work outlines the technical requirements for a bridge installation project on the Salmon-Challis National Forest. The selected contractor will be responsible for mobilizing to the job site, dewatering and rewatering the stream, fabricating and installing timber abutments, installing a government-furnished bridge, constructing approach roads using government-provided aggregate sources, recontouring and revegetating the stream channel, and designating an on-site representative experienced in bridge and earthwork projects. Key deliverables include proposed project plans and schedules, material certifications, and testing results. Work must be completed between July 15th and August 15th to accommodate fish species protections. The government will provide the bridge, aggregate sources, and fish and sediment monitoring services.

View the file

Other files for this federal contract opportunity

Other files attached to Moyer Bridge Installation - Salmon-Challis National Forest, newest first.
File Type Posted
Attachment 9 Appendix D Past Performance Questionnaire.pdf PDF
Attachment 7 MOYER MATERIALS VICINITY MAP.pdf PDF
Attachment 5 Project Design Features.pdf PDF
Attachment 3 PRELIM MOYER CREEK FSSS.pdf PDF
Attachment 10 Moyer Creek Bridge Shop Drawings APPROVED.pdf PDF
1282B123R0077.pdf PDF
Attachment 4 G-074 MOYER CREEK FINAL Drawings.pdf PDF
Q_As Moyer Site Visit_6.28.23_sk.pdf PDF
Attachment 8 DBWage Determination ID20220087_5.12.23.pdf PDF
Attachment 6 MOYER ACCESS MAP.pdf PDF
Attachment 1 Schedule of Items.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards Attachment

Project

MOYER BRIDGE INSTALLATION

General Information

1.0 Scope of Work

This project is an Aquatic Organism Passage project to replace an existing ford with a bridge. Work includes channel restoration, installation of a government furnished bridge on contractor provided abutments and the construction of bridge approach roadways. Rock and aggregate materials are available from government sources. Alternate (Commercial) sources proposed by the contractor will need to be approved for material suitability and weed free nature of the source. The contractor is responsible for the acquisition of the abutment materials per the attached plans and specifications along with the erection of the abutments. Government furnished materials are located at 3 locations in the vicinity of the project. Material removed from the Opal Pit and Moyer Pit will need to be quarried and hauled to the project. Opal pit material placed as road surfacing may need to be screened prior to placement. Riprap and Channel Rock may be obtained from the Musgrove Staging site. This material will have been stockpiled prior to the commencement of the project. Streambed material is expected to be salvaged from the excavation of the abutments and other channel restoration work including the placement of grade control structures and channel alignment work.

The prefabricated bridge will be staged in Salmon, Idaho. The contractor is responsible for transporting the bridge to the work site. An instream work window of 7/15 to 8/15 has been established. All work within the ordinary high-water mark including de-watering, excavation and backfill, channel restoration and re-watering of the channel shall occur within this window.

2.0 Background

The project is part of a larger habitat restoration project to improve habitat quality and remove barriers for ESA listed and native species. This specific project aims to remove a ford, re-establish channel complexity to a near natural condition and re-establish riparian function in the affected reach by replacing the ford with a bridge and naturalizing the stream channel and banks previously degraded by the development and use of the ford.

Contractor Requirements

3.0 Technical Requirements / Tasks

Mobilization:

• Transport the government supplied bridge from Salmon, Idaho to the Jobsite.

• Comply with weed prevention requirements through equipment cleaning and inspection prior to mobilization.

• Mobilize equipment/materials and supplies to the job-site or approved lay-down areas.

• Submit required plans, materials specifications, bonds and shop drawings prior to commencement of work.

Dewatering and Rewatering

• The contractor shall submit for approval a dewatering and rewatering plan prior to dewatering. Monitor and maintain effective dewatering for the duration of instream work. Rewatering shall be conducted in a controlled manner to minimize sediment mobilization including washing down placed material prior to reintroduction of water. Coordinate with COR to schedule dewatering and rewatering in order to facilitate fish salvage during dewatering and sediment monitoring during the reintroduction of flow to the constructed channel.

Abutment Fabrication and Installation

• The contractor shall procure and install timber abutments according to the attached plans and specifications. Shop drawings for the fabrication of the abutments shall be submitted and approved prior to the commencement of fabrication.

Bridge installation

• Install bridge on abutments per manufacture’s specifications and attached plans. Wear surface will be aggregate as shown on the drawings.

Approach Construction

• Construct approaches as shown on the drawings, material sources provided by the government are considered acceptable. Surfacing material may need to be screened to meet gradation requirements. Crushed aggregate is not required.

Revegetation

• The Forest Service will retain responsibility for seeding and mulching on this project. The contractor will be responsible for final grading and willow placement.

Channel Reconstruction

• Construct channel and structures as shown on the plans, minor modifications and adjustments to locations, geometry and final elevations are expected (field fit) but no significant deviations in quantities are expected. Contractor is expected to salvage suitable material for streambed construction from planned excavation and channel realignment.

4.0 Government Furnished

The government will furnish to this project the prefabricated steel bridge and provide access to rock and aggregate sources shown on the attached map. The government will also perform fish salvage and sediment monitoring for this project.

5.0 Deliverables / Schedule

Example 1 Key Deliverables

Item No. Deliverable Objective Due 1 Proposed Project Plan and schedules Provide a schedule that provides a timeline for coordination of government and contractor responsibilities and demonstrates ability to comply with project performance periods and restrictions.

No later than five (5) business days after contract award

2 Required submittals and requests for inspection of equipment or materials

Submit for approval all required submittals in a timely manner to allow for review, approval and acceptance that will not cause delays in the performance of the project.

See specific requirements in project specifications for each approval or request.

3 Material Certifications Where required, submit certifications for material properties, grade or in the case of treated timber treatment certification

Prior to incorporating into work

4 Sampling and Testing Results

Where contractor is required to sample or test work provide copies of the test results. Acceptance of work is contingent on delivery of the results.

Results to be available to inspector on request. All results must be submitted prior to invoicing the work.

6.0 Travel

N/A

7.0 Contractor’s Key Personnel

Contractor shall have on site anytime work is being conducted one person designated as the contractor’s representative who is able to take notices and act in response to any notices of non-conforming work. The designated person should be experience in bridge construction and associated earthwork including dewatering, channel construction and overall project management.

8.0 Security Requirements

N/A

9.0 Data Rights

N/A

10.0 Section 508 – Electronic and Information Technology Standards N/A

Attachment See attached Project Design Features-These features are incorporated in the ESA consultation for the project. ESA consultation is a legal requirement for the project and conformance to the design features is included in the requirements for the project.

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights