Project Risk Assessment Replace Roof and HVAC building 3.pdf
PDF 4 MB Posted
- Solicitation number
- 36C25621R0112
About this file
This notice announces a federal contract opportunity to replace the roof and HVAC system in Building 3 at the Alexandria VA Health Care System in Pineville, Louisiana. The contract is valued between $5-10 million and has a North American Industry Classification System code of 236220 for commercial and institutional building construction. The solicitation will be open only to verified Service-Disabled Veteran-Owned Small Businesses and issued on or after June 15, 2021 via the System for Award Management. Offerors must meet limitations on subcontracting and be registered in both the Vendor Information Pages database and System for Award Management to be considered. The single site visit is scheduled for June 22 and questions must be submitted by the cutoff stated in the forthcoming solicitation. The Department of Veterans Affairs is the contracting agency and Jennings Herbst is the point of contact.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25621R0112 0001.docx | DOCX document | |
| BLDG 3 Site Visit Information.pdf | ||
| WDLA202110051 04302021.txt | TXT text file | |
| 36C25621R0112.docx | DOCX document | |
| EXHIBIT F REQUEST FOR INFORMATION FORM.docx | DOCX document | |
| Vol 2-Specs.pdf | ||
| ACM and LeadReports.pdf | ||
| Drawings volume 2.pdf | ||
| Drawings Volume 1.pdf | ||
| EXHIBIT D CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY.docx | DOCX document | |
| EXHIBIT B PAST AND PRESENT PERFORMANCE QUESTIONNAIRE.docx | DOCX document | |
| EXHIBIT E SURETY FORM.docx | DOCX document | |
| J_A 502-19-102 (BC Signed) v1_Redacted.pdf | ||
| EXHIBIT A PERFORMANCE RELEVANCY SURVEY.docx | DOCX document | |
| EXHIBIT G RETURNABLES.docx | DOCX document | |
| Vendor Request Form.xlsx | XLSX spreadsheet | |
| Vol 1-Specs v2.pdf | ||
| EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT.docx | DOCX document | |
| VA10091 FMS Vendor Request Form EFT.pdf | ||
| SOW-04052021.docx | DOCX document |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pro ect Risk & Impact Assessment Date of Print Review: Demolition Start Date: TBD
Estimated Project Length: 365 Days Areas Effected by the Project:
Required OSHA Training: (10hr, 30hr) Scope of Project: Project 502-16-102 system Building 3 I
Building 2 Attic and various floors
Services Render Inoperative:
Overall EOC Effect to Which Areas: Building
High Interest Assessment Construction Specific
Items _ Operational Impact Team
Involvement Noise Type:
Equipment
Drilling 0 Blasting Pounding 0 Heavy El Motors 0 Other
X Asbestos High
Severity: 0 Low 0 Mild El Moderate 0 High 0 Severe Duration: 0 Short El Brief 0 Intermittent El Frequent 0 Prolonged 0 Continuous
X Vibration Type: El Primary Secondary 0 Other:
Access and Waiting Areas X Medium
Severity: 0 Low Mild 0 Moderate El High 0 Severe Duration:fa Short 0 Brief 0 Intermittent 0 Frequent 0 Prolonged 0 Continuous ILSM X Infection Control Hazards Low
X Air Quality Issues Type: a Fumes Severity: i Low Duration: Short Prolonged 0 Continuous
I Dust El Mold 0 Smoke 0 Chemicals 0 Mild 0 Moderate 0 High 0 Severe
El Brief 0 Intermittent 0 Frequent 0
Security Systems Impaired
X Utility Type:I Impact:
Duration:
Prolongedl
Issues I HVAC 0 Med Gas 0 Power 0 Water 0 Suction El Modified Operational a Shut Down
0 Short 0 Brief El Intermittent El Frequent D Continuous
Overcrowding/Patient Flow
Impaired Access to Facility Patient Care Effected Comments Trenching/Shoring/Holes Heat or Flames
X Electrical Work Limit Access to Care All employee X Overhead Hazards/Crain Operation Clinical Alarms Impairment notification on X Hot Work Permits Generator Power ISLM issued during X Fire Plan Required Equipment Modifications the construction of
Fall Protection • Air/Oxygen/Suction (AOV) this project
Lighting X Smoke Producing Operations
Portable Heaters X Weekly Inspections required Access to IT closets Access to IT data systems
X Fire Wall Penetrations VISN Notifications
Other Special Needs or Considerations Recommendations:
Chief Engineering Service: Date:
Facilities Safety Manager: , ic.....-.; Date: , 40 Patient Safety Manager: --794..-.e.4"-- Date:
AFGE Safety Representative: ,--• ---- _ Date: Arm Infection Control Nurse: /4,7„4-4,— 7-,-1-ii,--- ----_, Date: LAMM Green Environmental Manager: ' Date: it -11— 2.4.-L.-4
Emergency Managementa , / Date: 7
Employee Health:
Police Service:
Project C.O.R.:
Revised: 04/14
502-19-102
ALEXANDRIA VA HEALTH CARE SYSTEM
CONSTRUCTION PROJECT BLUE PRINT AND IN FIELD
SAFETY AND HEALTH ASSESSMENT RISie 'AS FP CRITERIA
CLASS
-Ik
CONSTRUCTION
f v R1 / l' misi6 r : O''- f 0 H
ACTIVITY RISK AUTIONS REQUIRED
CLASS
I
Type A: Inspection and Non-Invasive Activities.
Includes, but is not limited to:
1. Small scale removal of ceiling tiles for visual inspection or minor installation.
2. Painting (but not sanding).
3. Wall covering, electrical trim work, minor plumbing, and activities that do not generate dust or require cutting of walls.
Low or Moderate
Risk Patients Only
High Risk Requires Class II
Precautions
1. Execute work by methods to minimize raising dust from construction operations.
2. Immediately replace a ceiling tile displaced for visual inspection.
CLASS
II
Type B: Small scale, short duration activities that create minimal dust.
Includes, but is not limited to:
1. Access to chase spaces.
2. Cutting of walls or ceiling where dust migration can be controlled.
3. Installation of telephone and computer cabling
Low or Moderate
Risk Patients Only
High Risk Requires Class III
Precautions
1. Notify staff in the immediate area.
2. Provide active means to prevent airborne dust from dispersing into air.
3. Water mist work surfaces while cutting.
4. Seal unused doors with duct tape.
5. Block off and seal air vents.
6. Place dust mat at entrance/exit of area.
7. Contain construction waste before transport in tightly covered containers.
8. Upon completion, wipe work surfaces with disinfectant, wet mop and/or vacuum and remove isolation of HVAC system.
Administrative Lobbies Public Corridors Elevators Day Rooms Canteen
Type C: Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components and assemblies or new construction.
Includes, but is not limited to:
1. Sanding of walls for painting or wall covering,
2. Removal of floor coverings, ceiling tiles, and casework.
3. New wall construction.
4. Uncontained duct, HVAC or electrical work above ceiling.
5. Major cabling activities,
6. Any other project where high levels of dust are generated.
Moderate or High Risk Patients
Only Low Risk Requires Class ll
Precautions
In addition to Class II Precautions above,
1. Obtain IC concurrence before construction begins.
2. Complete all critical barriers, i.e., sheetrock, plywood, plastic, to seal from non-work area or implement control cube method (cart with plastic covering/sealed connection to work site with vacuuming prior to exit) before construction begins.
3. Isolate HVAC system in area and maintain negative air pressure within work site.
4. Cover transport receptacles or carts.
5. Seal holes, pipes, conduits, and punctures.
6. Personnel required ensuring shoes are not tracking when leaving the work site.
7. Upon completion, do not remove barriers until inspected by Safety and IC and thoroughly cleaned by EMS. Remove barrier materials carefully to minimize spreading of dirt and debris.
Offices
Retail Store
PATIENT
Medium
Outpatient, Urgent Care Laboratory Radiology and Nuclear Physical Therapy Respiratory Therapy Pharmacy Food Services Interim Care and Medical
RISK GROUP
Ri5!-.: Gmup and Primary Care Clinics
Medicine
Units
SPD Storage/Sterilization .
TB Negative Pressure isolation rooms Operating Room Urgent Care Morgue
ALEXANDRIA VA HEALTH CARE SYSTEM
CONSTRUCTION PROJECT BLUE PRINT AND IN FIELD
SAFETY AND HEALTH ASSESSMENT RISK BASED CRITERIA
Project Start Date: TBD Location of Construction: Building 3
Contractor Performing Work:
Low Risk
Estimated Duration:
X
365 Days
:, f
Type A: Inspection, non-invasive, minor X Low Risk
Type B: Small scale, short duration, moderate levels. Medium Risk Medium Risk
Type C: Major activity generates moderate to high levels of dust.
High Risk High Risk
INFECTION CONTROL PRECAUTIONS
-t
Base upon CDC Guidelines for preventing
.,k Assessment the transmission of TB in Health-Care Setting 2005
X Low Risk <3 TB Patients/year Inpatient & Outpatient
Medium Risk >3 TB Patients/year Inpatient & Outpatient
Potential on Going Transmission Evidence of ongoing M. Tubercubsis
Transmission regardless of setting.
Construction Site Location Low Risk: Administrative Offices, Lobbies, Public Corridors, Elevators, Day Rooms, Canteen Retail Store, Pharmacy and Food Services
Medium Risk: Outpatient, Urgent Care and Primary Care Clinics, Laboratory, Radiology and Nuclear Medicine, Physical Therapy, and Respiratory Therapy
High Risk: SPD Storage/Sterilization, Intensive Care Units, TB Negative Pressure isolation rooms, Operating Room, Emergency Room, Morgue, Laboratory TB testing room
PatientPo iiiation
Low risk: 0 - 37 Medium Risk: 38 - 75 High Risk: 76 — 111+
Hospital Layout Low risk:
Office Areas Lobbies/Corridors Mechanical Rooms And any other area with exceptions listed in the Medium or High risk
Medium Risk:
Building 7- Yellow team, Green team, Blue team, Dental, Radiology, Gold Team, Short Stay, Surgery, Women's Health, Rehabilitation Medicine, Cardiology Patient Services, Respiratory Therapy, Patient rooms Building 45 Building 9- Mental Health
High Risk:
Urgent care Rm Endoscopy Rm Morgue Outpatient Surgery Pharmacy Recovery Surgical units Negative pressure rooms
Overall Risk Assessment x Low risk: No TB test required for this project. Medium Risk: Annual TB test is required by all construction workers for this project.
High Risk: TB test within 90 days prior to construction is required by all construction workers for this project. , CLASS
1. Execute work by methods to minimize raising dust from construction operations.
2. Immediately replace any ceiling tile displaced for visual inspection.
CLASS
II
1. Provides active means to prevent air-borne dust from 5. Place dust mat at entrance and exit of work area.
dispersing into atmosphere. 6. Contain construction waste before transport in tightly
2. Water mist work surfaces to control dust while cutting. covered containers.
3. Seal unused doors with duct tape. 7. Upon completion, wipe work surfaces with disinfectant,
4. Block off and seal air vents, wet mop and/or vacuum and remove isolation of HVAC system.
CLASS
III
In addition to Class II Precautions above, 5. Seal holes, pipes, conduits, and punctures
1. Obtain IC concurrence before construction begins. appropriately
2. Complete all critical barriers or implement control cube 6. Personnel are required to ensure shoes are not method before construction begins, tracking dust and soil when leaving the work site.
3. Control airflow: Isolate HVAC system in areas where 7. Upon completion, do not remove barriers until work is being performed and maintain negative air inspected by Safety and Infection Control and thoroughly pressure within work, site, cleaned by EMS. Remove barrier materials carefully to
4. Cover transport receptacles or carts. minimize spreading of dirt and debris.
r"TPPW ! !FE C' .."-'711 ''F C" '9PS
NI I , CLASS ACTIVITY ILSM PRECAUTIONS
.CLASS
I
Minor: No breech of fire detection, alarm or fighting systems. No egress or access blockage.
None required beyond routine general safety precautions.
Ensure egress. Ensure access for Emergency forces.
Ensure operational Life Safety Systems.
Prohibit smoking.
CLASS
ii
Moderate: Short-term breech of fire detection, alarm or fighting systems < a single work shift. Blockage of egress or access but second means available.
In addition to Class I ILSMs, apply at-the-site measures.
Notify staff in the immediate area.
Control combustible loads.
Repair/construction staff immediately available at the site.
Compensate for compartmentalization deficiencies?
Each single breech of fire barrier immediately replaced.
CLASS
III
Major: Multiple or continuous breech of fire detection, alarm or fighting systems.
Blockage of egress or access. Work > a single shift.
In addition to Class I and II ILSMs, obtain Safety Manager concurrence before construction begins.
Construct temporary smoke tight barriers of non-combustible materials.
Provide additional fire fighting equipment.
Designate alternative exit/access routes.
Increase Hazard Surveillance.
Provide additional education to applicable Medical Center Staff/Incident Response Team Conduct 2 fire drills per shift in local areas vs. all areas.
Notify Emergency Forces.
INTERIM LIFE SAFETY MEASURE
LOCATION: I REASON:
ESTIMATED COMPLETION:
ILSM Start Date:
ILSM Implemented: POC:
ILSM Problems/Issue(s):
ILSM Action(s) Taken:
MANDATORY ILSM SURVEY ITEMS STATUS
Item Yes Yes No Comments
1. Exits free and unobstructed egress
2. Free and unobstructed emergency vehicle access
3. Fire alarm systems not impaired or equivalent
4. Temporary partition are smoke tight
5. Additional fire fighting equipment
6. Prohibit smoking
7. Ensure housekeeping standards
8. Two drills qtr where ILSM are evident
9. Increased hazard surveillance's 0.Training personnel of changes in procedures
11.0rganizational wide awareness of ILSM
ILSM Action Items from Above
Target Date Comp etion Date Problems Noted
Dates of Drills
COMMENTS:
Fire Plan Worksheet
Project Title & Project No:
Type of Project: 0 In-House 0 Purchase and Hire • Construction Contract
This worksheet completed by: The Risk Assessment Team
Date Completed: * Be sure to clearly mark/date addendum comments Updated #1: 4/27/2020 under Section 2 where updates are made Updated #2:
Updated #3:
SECTION 1
1. Will this project affect any of the following: If so details shall be provided for the corresponding numbered paragraph addressing the interim life safety measures that will be taken in Section 2
Item Yes No N/A
a. Exits or exit passageways. X
b. Stairwells. X
c. Storage space for construction materials. X
d. Heating devices shall be needed. X
e. Temporary partitions shall be needed. X
f. Fire extinguishing systems will be modified. X
g. Fire/smoke partitions will be affected. X
h. Fire/smoke detection systems shall be modified. X
.. Fire/smoke detection or extinguishing systems shall be down periodically. X
j. Fire/smoke doors and/or frames will be affected including automatic devices. X
k. Access to the building from any entrance shall be periodically blocked. X
I. Exterior distribution systems will be periodically shut down interrupting the building's service or backup sources.
X
m. Shall passageways for the physically handicapped be affected? X
n. Shall emergency power to any of the following areas be affected? X
1) Alarm systems. X
2) Blood/bone and tissue storage units. X
3) Egress illumination. X
4) Elevators. X
5) Emergency care areas. X
6) Emergency communication systems. X
7) Exit sign illumination. X
8) Medical air compressors. X
9) Medical/surgical vacuum systems. X
10) Operating rooms. X
11) Postoperative recovery rooms. X
12) Special care units (CCU, MICU, SICU). X
o. Shall emergency shutoff valves or isolation valve of any system be affected. X
1) Inside work area only. X
2) Adjacent occupied areas. X
p. Shall modifications/additions require updating existing policies for emergency response/reporting actual procedures?
X
q. Will there be any work performed within "confined workspaces?" X
r. Shall HVAC systems be shut down during the construction work? X
s. If an "Engineered Smoke Control System" exists, will it be affected? X
t. Shall the work require readying other space to relocate existing functions? X
u. If other areas are needed for domino moves, has each area been analyzed separately via attaching a completed work sheet to this plan for the other area(s)?
X
v. Shall any "Hot Work" activities be required during construction? X
w. Shall exterior excavation/trenching be performed during construction? X
x. Are any hazardous chemicals within the existing space? X
y. Are any flammable storage areas within existing space? X
z. Will asbestos or asbestos containing materials be associated with this work? X
FORM DISPOSITION: RETURN TO THE SAFETY STAFF FOR EVALUATION.
SECTION 2- SAFETY STAFF USE ONLY
(The following discussion for each item marked "Y" shall state interim measures to be taken or initiated).
Chief Engineering Service: . i\ vi — Date: I q Facilities Safety Manager Date:
Patient Safety Manager: Date:
AFGE Safety Representative: ,_,........- Date:
Infection Control Nurse: ) iL--,-- /4-4-2,--4._ Date:,51 7 /2 e c, Green Environmental Manager: 84.‘,.,. PA":3 Date: 14- 1.1-1--1..b Emergency Manag men c": ‘.-.. Date:9/77/2204 Employee Health: `1 LA S, ik-Q'' 4 Date: L( ?1f2 Police Service: , Date: LI r,- 2 0,2 et-t Project C.O.R.: -----,,,-r''4--- ,----- -=---- 1 Date: ,;//-2.,,/2,:. 7 c
DEPARTMENT OF VETERANS AFFAIRS MEDICAL CENTER
Alexandria, Louisiana
NE DESIGN SCOPE OF WORK
Replace Roof & HVAC System for Building 3
I. DEFINITION AND ACRONYMS:
I . Pre-Construction Risk Assessment (PCRA), Interim Life Safety Measures (ILSM), Request for Proposal (RFP). Certified Independent Third-Party Safety Professional (CITP) National Fire Protection Association (NFPA), The Joint Commission (TJC), Facilities Condition Assessment (FCA). Competent Person (CP). Contracting Officer's Representative (COR), Central Energy Plant (CEP)
II. GENERAL REQUIREMENTS
1 The Architectural/Engineering Consultant (ALE) shall provide all architectural and engineering services necessary to prepare complete contract documents consisting of specifications, drawings, and any other documents for bidding purpose and A/E construction period services for preparation of construction documents, cost estimates and other items as indicated to accomplish the replacement of the roof and air handler for building 3.
2. Work shall include, but is not limited to, the above detailed requirements which are to be considered a basic part/minimum requirement of this project and shall be fully developed by the ALE, discussed and resolved with Alexandria VA Health Care System staff.
3. The A/E shall schedule and conduct an initial pre-design meeting and field visit with the VA personnel consisting of: Engineering personnel, Safety Officer and other VA personnel as necessary. The purpose of this meeting/field visit is for all parties involved to fully define and understand the Scope of Work necessary for the A/E to design and prepare contract documents consisting of plans and VA specifications for the replacement of the building 3 roof and air handler. Design shall not relay on Boiler Plant Steam; alternative methods are to be considered.
4. The ALE shall perform any other necessary investigative work, i.e, meet with or communicate with VA staff regarding design layout.
5. The design and resulting construction must, as a minimum, be in accordance with all applicable codes, (NFPA, JCAHO, NEC, UPC, UMC, ASME, ASHRAE.
EPA), Controlled Environment Testing Association (CETA) and Department of
Veterans Affairs (VA) publications, Master Construction Specifications, Construction Standards, Design Guides and Standards.
6. All design and work will conform to the current edition of the VA Master Specifications and VA Design Standards as published at the following site:
www.cfm.va.gov; ASME, ASHRAE, OSHA, IBC 2009, IPC 2009, IMC 2009, NFPA, ABA, ABAAS, ADAAG and NEC building codes and standards.
III. INVESTIGATIVE WORK:
The NE, with the aid of VA staff is to perform all necessary testing and investigative work required to adequately design the project. Utilizing "as-built" drawings provided by the VA and design staff site visits, the NE will investigate scope of required new construction. The NE shall develop, execute and demonstrate that the project plans and specifications have gone through a rigorous review and coordination effort. The NE shall provide an outline of the actions that the firm will take during the design process to ensure a quality finished design is achieved.
IV. DESIGN CONSIDERATION:
Design shall include, but is not limited to, the following:
a. VA specification guidelines.
b. Construction drawings
c. Construction cost estimate
d. ASHRAE design considerations
e. Other necessary design considerations.
V. DESIGN REQUIREMENTS:
The Architectural/Engineering Consultant (NE) shall provide all Architectural and Engineering Services necessary to prepare complete contract documents consisting of specifications, drawings, and any other documents for bidding purposes and NE construction period services to upgrade the HVAC in Bldg 3 and replace the roof at VAMC, Alexandria, La. The project includes general re-design and removal of existing roof and HVAC system and replacing with Variable Air Volume (VAV) HVAC system including all associated components including but not limited to resized air handling unit and duct work and all associated controls for a complete working system. Replacement of these systems will also result in substantial revisions to their supporting electrical systems, as well as ceiling removal and replacement or reinstallation. The existing air-handler is located in the attic. This unit will remain on-line until a new unit can be installed, then removed in some fashion through roof.
Bldg 3 was built in 1929, and has approximately 27,500 gross Sq. Ft. The design will include replacing induction units, steam convectors and associated piping, controls and electrical equipment on the 1st, 2"d, & 3rd floor of Building #3. The scope of the project is to include removing all induction units on the 181, 2nd & 3rd floors and associated controls and electrical work in building #3 :and inStall'. Nlarfable'Air Volume (VAV) HVAC system including ,all associated compOnents inclucling but not limited to esized airhandling:Unit and duct work and all associated controls for a complete working system,. Existing baseboard stream heating convectors shall be removed including their supports, valves, and connecting piping. The existing air handling unit and some chilled water units and hot water piping scheduled for demolition are insulated with asbestos insulation. Asbestos abatement shall be part of the project. Floors in the facility are typically VCT with areas of carpet. Walls are either plaster or gypsum board assemblies for the newer areas. Ceilings are a combination of drywall, plaster, and ACT, varying by location and ducting needs.
This is an occupied office and medical building; this project will require phasing the construction to minimize the disruptions to the VA Medical Center. The NE will evaluate the entire project and make recommendations how to phase the AHU installation and roof replacement. This contract will provide for complete site investigation, design (construction documents), construction period services (CPS) and construction site visits.
will ,identify the construction time periods for shutdowns and lengths on the phasing drawings. Also, identify construction that will be required to occur outside of normal operational hours (Monday -Friday, 8:00 a.m.-4:30 p.m.).
Schedule and conduct an initial pre-design meeting and field visit with the VA personnel consisting of: Engineering personnel, Safety Officer, Maintenance and Operations, and other VA personnel as necessary. The purpose of this meeting/field visit is for all parties involved to fully define and understand the Scope of Work necessary for the NE to design and prepare contract documents consisting of plans and VA specifications to upgrade the HVAC system in building 3 and replace the building 3 roof.
PERIOD OF PERFORMANCE
The delivery date for this contract shall be 200 days from Notice to Proceed.
QUALITY ASSURANCE/QUALITY CONTROL (QA/QC)
The Design Offeror or NE shall develop, execute and demonstrate that the project plans and specifications have gone through a rigorous review and coordination effort. The NE shall provide an outline of the actions that the firm will take during the design process to ensure a quality finished design is achieved.
COST ESTIMATE
A detailed estimate of construction cost (using RS Means, Cost Works) and Market Study/Survey shall be provided with each design submission.
DRAWINGS
This project will utilize AutoCad, version 2017. All VA design guides and requirements can be found online at: http://www.cfm.va.gov/TIU. Where conflicts occur between VA standards and model codes, the most stringent requirement shall govern. All drawings must be bundled using the "e-transmit" function.
UTILITY SURVEY
During the design phase, the NE will coordinate with Alexandria VA Health Care System Staff to obtain utility information to facilitate the design. Otherwise, what is not obtained shall be surveyed to extent necessary by the NE.
HAZARDOUS MATERIAL ABATEMENT SURVEY
During the design phase, the NE will coordinate with Alexandria VA Health Care System Staff to perform a hazardous material abatement survey to facilitate the design. The NE shall survey the areas of conflict in question to incorporate into the design documents accordingly.
FIRE PROTECTION ENGINEER REVIEW & CERTIFICATION
The NE shall have the design plans and specifications reviewed by a registered Fire Protection Engineer (FPE) to ensure the design proceeds in accordance with Life Safety Code (LSC) and applicable National Fire Protection Association (NFPA) codes. The FPE's review comments shall be provided along with each design submittal starting with the 50% Design Development drawings. With the Final 100% Construction Documents submittal, provide a FINAL certification letter from a registered FPE stating that the FINAL plans and specifications are in compliance with the current LSC and NFPA codes.
PHYSICAL SECURITY & BLAST DESIGN
The design shall be in accordance with the latest edition of the Physical Security Design Manual for VA Facilities, Life-Safety Protected/Mission Critical Facilities as applicable.
HANDICAP ACCESSIBILITY
The design will be required to comply with the Uniform Federal Accessibility Standards (UFAS), ABAAS (Architectural Barriers Act Accessibility Standards) and PG-18-13 (Barrier Free Design Guide) in all areas.
COMMISSIONING
The construction and intended use does require commissioning. The NE shall incorporate the VA's commissioning specification into the design and complete set of construction documents as applicable. The Construction contractor shall procure the 3rd party Commissioning Agent to oversee and execute the contract required commissioning activities during Construction.
GOVERNMENT FURNISHED INFORMATION
The following is a list of government furnished information found on the VA's Technical Information Library website (http://www.cfm.va.gov/TIL/) to be used for this project, as applicable:
PG-18-1 Master Construction Specifications PG-18-3 Design and Construction Procedures PG-18-4 Standard Details and CAD Standards PG-18-10 Design Manuals (by discipline) PG-18-12 Design Guides (graphical, by function) PG-18-13 Barrier Free Design Guides
Uniform Federal Accessibility Standards (UFAS) ABAAS (Architectural Barriers Act Accessibility Standards) Physical Security Design Manual for VA Facilities, Life-Safety Protected
NOTE: Utilize the latest version of guidance at time of design award.
VI. SUBMISSION OF DOCUMENTS:
the VA staff shall have a minimum number of calendar days .to review and coordinate each NE design submissions broken down as follows: 25% -fifteen days (15), 75% - thirty days (30), 100% - fifteen days (15). If the VA workload does not allow for a thorough review within this timeframe, the A/E shall not proceed to the next design phase until comments have been received from the VA. The AE will be entitled to a time only contract extension for the number of ,VA review days beyond what is specified, above.
2. The following specifies the documents, etc., required to be submitted by the consultant to the Contracting Officer for distribution for each scheduled review and the due dates for each submission. Dates indicated must be strictly adhered to.
3. Working Drawings:
General
a. The Architect/Engineer shall design and estimate so that all applicable codes are met. The NE and their design teams will be required to attend a 0% pre-design meeting with the Alexandria VA Health Care System personnel to outline the scope of the design project. The NE should be prepared to walk through the work site, take pictures, ask questions, take measurements, review as-built drawings and VA specifications and gather any other pertinent information necessary to fully understand the scope of the design task. The A/E will also be required to make a formal presentation at the 50% and 100% reviews in person.
b. The NE shall take written minutes of the pre-design meeting and all design reviews, in which he is in attendance, and provide the Alexandria VA Health Care System with them within two (2) working days.
c. The NE shall establish a construction schedule.
d. The NE shall prepare a list of equipment and material submittals required by this project as separate specification section in the contract package.
e. In each submission, the NE shall incorporate all materials, procedures, etc., specified and all revisions according to comments made by either the Health Care System, Regional Safety & Fire Protection Engineer or VA Central Office where applicable.
4. 25% — 25% design submission required within sixty (6Q) calendar days after conclusion of the 0% design meeting.
a. Submittal Letter — Consultant shall provide a submittal letter addressed to the Contracting Officer stating documents submitted for 25% Review.
b. Specifications — Consultant shall provide (2) sets of edited, assembled and technical Project Specifications to the Project Engineer to be used on this project. Marked up standard specifications are acceptable. The most current VA Master Specifications shall be used on this project and are available on internet: htto://www.cfm.va.gov/TiUspec.asp
c. Drawings — Consultant shall provide a (2) full set of project drawings showing the Basic Plan for each discipline involved. This shall include:
(1) All drawings developed for the previous reviews shall be detailed showing all utilities, services and sizes as well as other required construction detail.
(2) Show complete plan views, elevation views, photographs, legends and other schedule information.
(3) Also show complete details, notes, sections and locations.
d. Cost Estimate — Consultant shall provide a cost estimate to both the Contracting Officer and the COR/engineer and ensure that the following items are included:
(a) Certification that the quantities have been checked and found to be correct.
(2) All estiMates shall be based on the most up-to-date working drawings availaOle and shall be current as of the date of submission.
(3) Materials are priced at the contractor's buying level. Sales taxes, whp,p7appligabtegkwilkbp a.citded into material egsts,.
(4) Cost totals should reflect 1?bor and materials separatdhotjid be formatted as follows:
(a) Totals — Labor and materials for all branches of work.
(b) Contingencies — None.
(c)Overhead and Profit — A nominal percentage to reflect variatioh-of trades, project size, competition, etc.
(d) Total Estimated Cost.
e. This submission will be reviewed and one (1) copy of the plans and specifications returned to the Consultant. This design will be reviewed for functional purposes only. Technical accuracy and detail will be the responsibility of the NE firm.
5. 50% — 50% design submission is not required due to time constraints- of the project. This will facilitate expediting the project.
6. 75% — 75% Design is required within forty (40) calendar days after- notice to continue is issued by Contracting Officer or the COR.
a. Submittal Letter — Consultant shall provide a submittal letter addressed to the Contracting Officer stating documents submitted for 75% Review.
b. Specifications — Consultant shall provide (2) sets of edited, assembled and technical Project Specifications to the Project Engineer to be used on this project. Marked up standard specifications are acceptable. The most current VA Master Specifications shall be used on this project and are available on internet:
c. Drawings — Consultant shall provide a (2) full set of project drawings showing the Basic Plan for each discipline involved. This shall include:
(1) All drawings developed for the previous reviews shall be detailed showing all utilities, services and sizes as well as other required construction detail.
(2) Show complete plan views, elevation views, photographs, legends and other schedule information.
(3) Also show complete details, notes, sections and locations.
d. Cost Estimate — Consultant shall provide a cost estimate to both the Contracting Officer and the COR/engineer and ensure that the fonowrob items are included:
(1) Certification that the quantities have been checked and found to be correct.
(2) All estimates shall be based on the most up-to-date working drawings available and shall be current as of the date of submission.
(3) Materials are priced at the contractor's buying level. Sales taxes, when applicable, will be added into material costs.
(4) Cost totals should reflect labor and materials separately and should be formatted as follows:
(a) Totals — Labor and materials for all branches of work.
(b) Contingencies — None.
•(c) Overhead and Profit — A nominal percentage to reflect variation of trades, project size, competition, etc.
(d) Total Estimated Cost.
e. This submission will be reviewed and one (1) copy returned to the Consultant. This design will be reviewed for functional purposes only.
Technical accuracy and detail will be the responsibility of the A/E firm.
7. 100%-100% Design two (2) sets of specifications, drawings and cost estimates are required within twenty (20) calendar days after notice to continue is issued by Contracting Officer or the COR.
a. Submittal Letter — Consultant shall provide a submittal letter addressed to the Contracting Officer stating documents submitted for 100% Review.
b. Specifications — Consultant shall provide (2) sets of edited, assembled and technical Project Specifications to the Project Engineer to be used on this project. Marked up standard specifications are acceptable. The most current VA Master Specifications shall be used on this project and are available on internet: .v cfm.va.ciov/TILispec.
c. Drawings -- Consultant shall provide a (2) full set of project drawings showing the Basic Plan for each discipline involved. This shall include:
(1) All drawings developed for the previous reviews shall be detailed showing all utilities, services and sizes as well as other required construction detail.
_(?) Show complete plan views, pleygtioR views, phplpgraphs, legends and other schedule information.
(3) Also show complete details, notes, seCtiOns and locations.
d. Cost Estimate — Consultant shall provide a cost estimate to both the Contracting Officer and the COR/engineer and ensure that the folloyving items are included:
(1) Certification that the quantities have been checkedf and found to be correct,
(2) All estimates shall be based on the most up-to-date working drawings available and shall be current as of the date of submission.
(3) Materials are priced at the contractor's buying level. Sales taxes, when applicable, will be added into material costs.
(4) Cost totals should reflect labor and materials separately and should be formatted as follows:
(a) Totals — Labor and materials for all branches of work.
(b) Contingencies — None.
(c)Overhead and Profit — A nominal percentage to reflect variation of trades, project size, competition, etc.
(d) Total Estimated Cost.
e. This submission will be reviewed and one (1) copy of the plans and specifications returned to the Consultant. This design will be reviewed for functional purposes only. Technical accuracy and detail will be the responsibility of the A/E firm.
f. In accordance with the previous review requirements, with all review Specification — consultant shall provide to the COR/engineer specifications, complete comments accounted for and ready for use as final Contract documents. Specifications shall include scope of work and phasing schedule requirements assembled with the general construction sections.
8. Final submission — after completion of all the 100% review comments and corrections, the final contact documents shall be prepared, and submitted within ten (10) calendar days after notice to continue is issued by Contracting Officer or the COR.
a. Submittal letter — consultant shall provide a submittal letter stating that the changes and corrections noted on the previous review have all been evaluated and incorporated in the documents submitted for the final submission. List these documents:
(1) Provide as a minimum a 700mb recordable disk containing digital drawings and technical specifications and two hard copies.
(a) Drawings to be in AutoCAD and PDF format
(b) The Combined Specifications to be in Word and PDF Format
(i) The most current VA Master Specifications shall be used on this final documentation submission and are available on internet:
http ://ww w. cfm va. g o v 1-IL/spec. a sp
(2) A final cost estimate based on revisions made at 100% review and cost estimate of bid items if required.
(a) Totals — Labor and materials for all branches of work.
(b) Contingencies — None.
(c) Overhead and Profit — A nominal percentage to reflect variation of trades, project size, competition, etc.
(d) Total Estimated Cost.
(3) A final set of design calculations (where applicable).
(4) A&E Design and AS-BUILTS only:
(a) The CD case shall have the full name of the firm, address, contact phone numbers, Project number (station number, year, the number of the project) and Set 1 of CDs if more the one CD is required, on the inside of the CD case only there shall be an index of drawings with page numbers and drawing numbers.
(b) The CD face shall contain the same information as the CD case except "the index". The CD shall not have anything to unbalance it.
(c) All information shall be neatly typed and legible without the aid if any type of magnifying devises.
(d) All CAD data and project specifications shall be delivered on Compact Disk(s) (CD) 650MB or greater. All data files shall be organized using the directory structure (path) as outlined in the CAD Standards, Naming Conventions section of this document. All files shall be free of corrupted or unusable data.
(e) All CAD data shall be supplied in the latest version of the translation format, DWG. The contractor will be responsible for phsuriv - that all files shall tra, sla 'System, AutoCAD oeisfc1 nA nto t: ' 'tc)L 4.
) The „A&E shall ensure, a separate layer' identified as SQUARE FOOTAGE, with the length, width, and square footage of all mechanical: office, ,and patient area, corridors, etc this la-y.cr shall havE the total of existing' renovated space, total of new oonstructiQn d the total square foQtage of the entire renovated area.
VII. PRE-BID CONFERENCE — the NE is required to attend the pre-bid conference, which will be scheduled by the Alexandria VA Health Care System, contracting and procurement section, prior to the bid opening date for the purpose of answering questions and clarifying the project specifications and drawings with prospective bidders. The project site will also be visited to verify existing field conditions and dimensions.
VIII. PRE-CONSTRUCTION MEETING — the A/E is required to attend the pre-construction meeting for the project which will be scheduled by the Alexandria VA Health Care System for the purpose of answering questions and clarifying the bid documents, etc., with the contractor. The A/E is to provide five (5) complete sets of contract drawings and specifications to the construction contractor at this meeting. The A/E shall take written minutes of the pre-construction meeting and provide the Alexandria VA Health Care System with them within five (5) working days.
IX. CONSTRUCTION PERIOD SERVICE REQUIREMENTS
1. Review of submittals — Consultant shall review all material submittals, shop drawings and test reports. Reviews shall be completed and submittals returned to the COR/ engineer with fifteen (15) calendar days from receipt of request.
2. Review analysis of change order and costs — consultant shall provide prompt response when contacted by resident engineer to review and provide analysis of change orders and costs.
3. Site visits — Consultant shall provide weekly site visits throughout the duration of construction activities and one (1) final inspection for the project. (Please include price for additional site visits should they be desired by resident engineer.) The architect/engineer will also make a written inspection report within two (2) working days after each site inspection.
4. Weekly Construction Phase Meeting --- Consultant shall be required to attend all weekly construction phase meeting in person or via tele-conferencing to discuss any issues or concerns the VA staff or contractor may have.
5. One set of drawings / Markup Drawings shall be on site or in Job shack with all documented changes to the project. Must be legible and ready at any time for the COR to review while in the area. Once completion of construction this set of drawing will be turned into the COR so it can be given to the A&E to make all changes and create the final set of "AS- BUILT"drawings. In accordance with Alexandria VA Healthcare Systems Computer Aided and Drafting Standards.
6. The A&E shall be responsible for obtaining a certified Test and Balance Agency that is capable of performing a system balance as per VA Specification Section 23 05 93 Testing, Adjusting and Balancing for HVAC that is non-affiliated to any contractor, architect, engineer or manufacturer. Test and Balance Agency shall be either a certified member of Associated Air Balance Council (AABC) or certified by the National Environmental Balancing Bureau (NEBB) to perform Testing, Adjusting and Balancing (TAB) service for HVAC. A submittal with the name of the selected Test and Balance Agency, plus the name and registration number of the certified Test and Balance Engineer, shall be submitted to the CO/COR for approval within thirty (30) days after award of the construction contract.
X. MISCELLANEOUS:
1. Following approval of the final (100%) review material, the NE will provide the government with electronic sets of the approved contract, drawings and specifications. Drawings shall be furnished in AutoCad® 2015 electronic format and one set of drawings in .pdf for distribution. The specifications shall include those sections prepared and edited by the Contracting Officer and shall be furnished in MS Word format. Specifications shall be of the most recent version on the VA Master Specifications TIL
2. NE will provide additional services as outlined in Special Provisions (Architect- Engineer Contract) including construction period services, site surveys, as-built drawings, etc.
3. Design to be in accordance with applicable federal, state, and local codes (ASCE, ASME, ASHRAE, NFPA, JCAHO, OSHA, VA design guides and Master Specifications, etc.).
4. Design shall be in accordance with Program Guide, PG-18-15, and Volume C of the TIL.
Building 1 Hoer Miscellaneous Materials Ceiling Materials TS! Materials _ 1:41061411K00111$
Basement NO ACM NO ACM HMA-1-B-TS!
Steam Pipes
HMA-1-B-FT&M
Various Floor Tile and Mastic
First i
NO ACM NO ACM HMA-1-1-TSI
HVAC Pipes
HMA-1-1-FT&M
Various Floor Tile and Mastic
1 Seculd
I
NO ACM NO ACM NO ACM HMA-1-2-FT&M
Various Floor Tile and Mastic
Attic NO ACM NO ACM NO ACM NO ACM
Building 2 Floor Miscellaneous Materials Ceiling Materials TSUMOtnials
Basement Hi ) Ai M NO ACM NO ACM NO ACM
First HMA-01 Fire Doors
NO ACM HMA-2-1-TSI
Pipe Insulation (3) Vertical pipes
HMA-2-1-FT&M
Various Floor Tile and Mastic
Second HMA-01 Fire Doors
NO ACM HMA-2-2-TSI
Pipe Insulation (1) Vertical Pipe
HMA-2-2-FT&M
Various Floor Tile and Mastic
' "Third HMA-01 Fire Doors
NO ACM HMA-2-3-TSI
Pipe Insulation - (1) Vertical Pipes
HMA-2-3-FT&M
Various Floor Tile and Mastic
I 0(111110(11111 NO
HMA-01
Fire Doors ACM
HMA-2-4-TSI
Air Handlers Ductwork
Pipe Insulation & Fittings- (3) Vertical
HMA-2-4-FT&M
Various Floor Tile and Mastic
Attic
HMA-2-A-M
Black Mastic on Ductwork
NO ACM
HMA-2-A-TSI
Insulation on Air Handler and Ducts Insulated
Elbows Exhaust Blower
Pipe Insulation & Fittings - (7) Vertical Vibration Isolators
NO ACM
Building 3 Floor Miscellaneous Materials Ceiling Materials TS! Materials
Basement NO ACM NO ACM NO ACM NO ACM First HMA-01
Fire Doors
NO ACM NO ACM HMA-3-1-FT&M
Various Floor Tile and Mastic
Second HMA-0 1 Fire Doors
HMA-3-2-CT
Black Glue Dots Under 12X12"
NO ACM HMA-3-2-FT&M
Various Floor Tile and Mastic
Third HMA-01 Fire Doors
HMA-3-3-CT
Black Glue Dots Under 12X12" Ceiling
Tile
NO ACM HMA-3-3-FT&M
Various Floor Tile and Mastic
Attic NO ACM NO ACM NO ACM NO ACM
KOH GAR1.1.1 HI ALI( MAWR: FOUNn Fl NOUN 116 A0 111. 2,113 IHINSINOTTUN
NOTE • Ft 00111NO 11.6 CHANtiFO TO CERAMIC TILE
IN ROOMS 121 4 110 05 OF 2013 PLINSPECTION.
No Ant At, 00 NO1 CONTAIN
21: NT AND REMOVED FROM MIA •
AS OF 2013 REINOPECTION.
1.711 I ARM- 1 21ACt I) LA20 FL .13R TE
10 1101./.1 II:. A. 02 2513 112201.1.12. HON \
_NO7 E : BROWN PEEL a sncR TILE FOUND
IN ROOM 102 DURING 2013 REINSPECDON.
FLOOR TILE a MASTIC HAVE LIEF 5 ABATED a REPIACED will NoN.Acifi i
FLOORING. (2007 PER OWNER)
PEN 2013 REINIIPEclION. NO ABATEMENT RECORDS WERE AVAIL KALE.
PER 2013 REINSPEC DON. NO ABATEMENT
-RECORDS WERE ATTAR AR) E
NOTE: FLOORING la NOW WOOD LAASTATE
W HALLWAYS AS OP 2013 REINS PECHON.
-"O
RUE 21100 3. WHO 10,02)0
FLOORING APIRESTDS
HomODELIECnia AREAS
0E TER11100 AFFAIRs TWITICAL CENTER At eXANDRIA.1 AYMARA
2017 ASSFATOS ftPINSPPOInN
ItrA44.1.FT 41-2100/1 Till;
12,2.,0 AMOR MASTIC • ana FT
Fga ABATED AREAS r "3: :A? UPDATED OF p
NCOMUMBNIS
CREAM tr 0 12' ENDER CARPET MAROON 12" 0 ir
1.10447 GREEN ir 0 12' UNDER CARPET
YELLOW 1 ORANGE ir x ir ORAV OWEN r WRITE ir Di CoNcRETE OREEN, WIRTZ W GREEN sPEcKs IOU V • PINK W: GREEN MOM 12" X Tr TRUK MISS DC GREEN W. III GE SPECKS 1r X IrBLACK MA% IP'
CERAMIC
GREEN /WHITE ir Si
INIIITE W BLACK VEERS 12" X 12"
LIGHT GREEN ar X /2" BLACK MASTIC
UNDER CARPET
CARPET
i
9" X r FLOOR IRE , BLUE , BROWN /WOE troll' swimmer/iv/WE 12" 012' BLACK 5155 11::
UNDER CARPET
GREEN I WHITE r X 9" BLACKS" X r
SLACK MASTIC ON CONCRETE
CARPET
ElAcK MASTIC BROWN 12" X Tr POOLE STICK
WOOD LAMINATE
Fin
MIR MU RAT FLOOR
PRAM lANE01/5 AMIE 31'33 flOPDATNEDLIS ARM
VETERANS AFFAIRS Pear.m. crlinft
ALEXANDRIA LOUISIANA
2011 AARE S RFIt44PIIC I ION
Ell IISI4•01 FIRE DOORS
111* FLOOR TOTAL -3 DODRE
1:1T=g,":."
113 I 121A 121
I tiN
;! ilea MD 1,
• I i
P - .
120 11;2AA."."
t r
_71:f 77:7 1150
104 les
ELEV. I Li110
-j
112 -
NOTC. 1100 000110 FOUND 000P4I3
2513 REINSPFCTION
Fin
Mb. 400.
113 112A
NOTE. FLOORING IN ROOM 25215 NOW BROWN
-PEEL A STICK AS OF 2013 REINSPEC DON.
FLOOR TILE a MASTIC HAVE BEEN ABATED S REPT ACED WITH
-NONACM FLOOR (IF. (JULY 2007 PER OWNER)
PER 2013 REINSPECTION. NO ABATEMENT RECORDS WERE AVAILABI
ii4A4.3.2.FT M • FkOOR TEE Kral ANA'OR MASTIC • 1.165 SO FT
MA ORATE)) AREAS
E '114,0"47,°51.7:",,tt,OF
NOTE ROOM 202 CHANGED TO MOWN
PEEL S STICK Al) OF 2013 NE HISPEC TION.
NO II Hoots 223A nsx-stmo FOUND 70 SF NON ACM T4 2013 RFINSPECnoN AND REMOvEU FROM 1114A
NOTE. FLOORING IN ROOM 214 IS NOW CARPET OVER
GREEN LINOLEUM AS OF 2013 REINSPECTION.
6111MILKEIBUNIMMIIMIMININIMITZE
IS'
BUILDING 3 .11ECO5n 40E41
21. DORM ASBESTOS
ituV.OGINEttus ATIVAS
VC1ENA1S AFrAIIIS SIIINCAL C.1:111) Al FUSON/A. LOUISIANA
7111. ASSFRSIS 04I0A(N,11011
4.2Me
CREAM T BROWN tr x 12" BLACK ir it tr LIMIT GREEN r X r
CERAMIC
GRAY / GREEN WHITE Ir X 12"
CONCRETE
CARPET Cu SLACK MASTIc BROWN :sROwN a WHITE 12 3 ir STAT.% T.T1'.ir.
E 21 WM SLACK MASTIC
BRIGHT GREEN tr x ir BLAcK mayo.
cAREETAN r X 1- CHU1EN r X I' SLACK MAsTic LIGHT GREEN ir X 12. SLACK MASTIC
UNDER CARPET
BROWN 12- X IS' PEELS STICK
GREEN tr x sr PEEL a STICK cAREEr ovER GREEN LINOLEUM
CARPET
r-- —01
FLOOR IRE a MASTIC HAS BEEN ABATED. (2062 PER OWNER)
PER 2013 REINSPECTION. NO ABATEMENT RECORDS WERE AVAILABLE.
NOTE CARPET NOW COVERS FLOOR TILE IN
ROOMS 206 211 AS OF 2013 REINSPECTION.
la a am I u Imo INE los a mu;
202 203
1.61 224,11
UDE]
221 li 222 223 rAC
21R L- 216
2211 217 217A
16.1rEl Effl
11'1- =T.:AA
ELEV.
I
22stottil 29I
WM RPM 3 .1192:0411 El opp CPR WO Asovuot'•
77a1013113E000 AREAS
111111111111111•1111111111111111111/111111111111111MVAN
1/176RA71S ASFAIRD MODICAL CEA Oh
ALE 04400RIA, 1.031676140
2617 A614611700 Fa 60161,1116121
PR HAM 9447 8IAGN GLUE ROTS k
. 12- 0 12" DRAM TA 6 • 1,62C 61.1 F
IMMINIIIMIIIIIMMIRMEREInene
1 1 24- 143' WHITE DER IOU 17 1, am 714.".l I) iEI
PERM k i
DEIRDRE*.
„, 12- 012' MUIR& TAR iNini WAX Po% Ario21.
DROP CEILING
III 24' 034' WI1176 Coma 111.6 WM IRAS s 047 P AUER CEILING 01101/9 *Mr 01611E3, 17907
1110131.111.11.111111111111WWW1
I " 11 20 ' ff-n.22"
17.7— TL
I [1] r
9-f
0 2'4 0
0 7;
F
220 217
RUDOIND 3 • s mow rtwm MISCRI.I.AWDUS AIWA? On
INISOCIEWOUS ARIAS
tERAns An' APIs ISEDICAL et N Al EXANDRIA LOUISIANA
A2RFSTOR1121142POCTION
NM 1112241 FIRE DOORS
2ND FLOOR TOTAL - I tle9R
A A n R n A I
N V I
NOTE: FIRE DOORS POUND OURINO
2113 REINSPECIION.
Fin 17611 r° IS
4, !J., I: It 11(1k) (1 MAlt RIM. IS CREI A 1.:1, Al. of IX, 111.10SPI ..11110
0.CIL I LOORINO IS CONCRETE AND HAS BEEN
RE MOVF.D FROM HMS AS OF 2013 RFINSPF.C7100..
319 [19
. 1117&q1=-_---A7PA4-q-
..NOTE FLOORING MATERIAL HAS CHANGED
IN THIS WING AS OF 2013 RONSPEC 1100.
IJ,
FLOOR ME It MASTIC HAVE BEEN ABATED S. REPLACED 151TII
100)1-ACM FLOOR TILE. (JULY 2007 PER OWNER)
PER 2013 REINSPECTION NO ABATEMENT RECORDS WERE AVAILABLE.
NOTE • FLOORING CHANGED TO GRAY
i
LINOLEUM AS OF 2013 REINSPECIION.
_NOTE. FLOORING COVERED WITH
CARPET AS OF 2013 NFINSPECTION
RIM DINO 3 • moan ft ow, FIG OKING Asevann.
ocklooLNEEAES NEAR drsa271
VETERANS AFFAIRS ARChIVAL ern 0 E At FORMA. i OWEIANA
201? ASIIFSTOs REPESPECTION
111.1A44•FT & Et • Ka* Itt- ANWOR MASTIC • IOW 012 El
IRM AOAT CO AREAS
AREA UPDATED AS OE
2012 RFINSPECTION
1IO
LOUT GI10EN WITH DARK BLUE SPECKS Er • 2 Er ceilAINC LNTPINK wale MIEN sPECKs 12'S IT
GRAY LINOLEUM
CARPET OVER CERAMIC
OFF WRITE? BROWN IV x w UNDER CANN, OW PORTS i DROWN 12. X 12" UNDER LPN: E LU1 IJORT GREEN WI DARK BLUE SPECKS 12'S la" UNDER Off METE I DROWN 12'S fr
141 CARPET
GREEN tIr A Sr PEEL a STICK
CONCROP
imonuommummummemonwma
CFin Imamsnommeauesummenoel
RILEDIVO 3 • 011111114.0011
BEANO AMITE MS
0021110ENTOUS ARTAI
VETERANS ATTAINS 1.1E1/1CAL 0E1E0 11
ALEXANVILIA. LOUISIANA
21113 ASHES TON ifiINAPICTION
VTO 11114444CT BLACK (RUE DOM UND•
12. X 12" BEANO TILE • IVO SO I 1
I2" X 12" CEILING The VA 011101.1:9 UN 10
OWE DOTS
Eqj 24. X 44. WHITE CEILING TILE IMO 1101 Es
24" X 24. METE CEILING TICE WITH HINTS
ABOVE LA Y4I4 TILE
E01 Tax W CEN.1111011lE WITH HOt ES ON 1111 LI, tI IV 1301S ABOVE 04101 CEREAL
111 321 320A
-MALL -Of
3E3
323A 0
317A 317 j1 1:3,4, -11111 312
31413
Id- IT" :AAIrla 1-171AAT7,- :
III/FANO • TIRO Fl CO" LIR.EELLAIVOIES ASHES oS
'MR00E11E0116 AREA,
VETERANS AFFAIRS MCIACAL GLOM.
ALEXANDRIA, LOUISIANA
211? ASRFS70111whearcenrIN
IIMA•01 FIRE DOORS
3RD FLOOR 'MM.., 7130011,
171 :573"::=5"."
ROTA FIRE DOORS FOUND 1101120
2513 RESISPEO7101.
kt5STI
14/
| Page 1 |
| Page 2 |
| Page 3 |
| Page 4 |
| Page 5 |
| Page 6 |
| Page 7 |
| Page 8 |
| Page 9 |
| Page 10 |
| Page 11 |
| Page 12 |
| Page 13 |
| Page 14 |
| Page 15 |
| Page 16 |
| Page 17 |
| Page 18 |
| Page 19 |
| Page 20 |
| Page 21 |
| Page 22 |
| Page 23 |
| Page 24 |
| Page 25 |
| Page 26 |
| Page 27 |
| Page 28 |
| Page 29 |
| Page 30 |
| Page 31 |
| Page 32 |
| Page 33 |
| Page 34 |
| Page 35 |
| Page 36 |
| Page 37 |
| Page 38 |
| Page 39 |
| Page 40 |
File details come from the government source that posted it. Updated .