Project Manual and Specifications Keller Hall Part 2.pdf
PDF 11 MB Posted
- Attached to
- WVSDB Keller Hall Updates
- Solicitation number
- CRFQ 0403 DBS2600000008 2
- Issued by
- Hampshire County, West Virginia
About this file
This is a Project Manual and Specifications document for the West Virginia Schools for the Deaf and Blind (WVSDB) Keller Hall Renovations project located in Romney, West Virginia, prepared by The Thrasher Group architecture firm. The project involves comprehensive renovations including replacement of all windows, upgrades to portico ceiling and columns, repointing of window well brick, installation of new stone caps, interior improvements to create a secure school entrance, and plumbing work including waste piping replacement, new faucets, shower inserts, mop sinks, shower valves, access doors, and water heater replacement with thermostatic mixing valves. The contract is structured as a single prime contract with the contractor responsible for furnishing and installing all materials, equipment, and labor necessary for project completion. Key administrative requirements include submission of a CPM (Critical Path Method) schedule within 14 days of the Notice to Proceed, a Schedule of Values coordinated with the construction schedule, submittal schedules for all materials and equipment, and comprehensive shop drawings for doors, frames, hardware, windows, and specialty items. The project includes allowances for 60 linear feet of brick repointing and 100 linear feet of cast stone repair or replacement, with unit prices to be established for these items. A preconstruction conference must be conducted no later than 15 days after execution of the Agreement, and progress meetings are scheduled monthly.
Pricing will be established through competitive bidding on the lump-sum contract amount with adjustments for change orders, unit price work, and allowance adjustments as construction progresses. The contract includes a five percent (5%) retainage throughout the construction period with ninety-five percent (95%) payment of work completed. The contractor must maintain performance and payment bonds as required by West Virginia state regulations and must comply with supplementary general conditions modifying the AIA Document A201-2017 standard form, including overhead and profit limitations for change order work (15% for contractor's own forces, 8% for subcontractor work). All door hardware is specified from scheduled manufacturers with no substitutions permitted for certain items, and the contractor must furnish complete key control systems and coordinate with the owner's existing Master Key System. The project requires compliance with West Virginia prevailing wage requirements, certificates of insurance naming the state as additional insured, and final closeout documentation including as-built schedules, warranties, operation and maintenance manuals, and record drawings. Substantial Completion procedures require submission of a punch list at least 10 days prior to inspection, with all closeout requirements including final cleaning, demonstration and training of owner's personnel, and submission of all warranties and Project Record Documents completed before final payment authorization.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SGC -1
Supplementary General Conditions to the
AIA Document A201-2017 General Conditions of the Contract for Construction
The following supplements shall modify AIA Document A201-2017, "General Conditions of the Contract for Construction". Where a portion of the General Conditions is modified or deleted by these Supplementary Conditions, the unaltered portions of the General Conditions shall remain in effect.
GENERAL
A. Whenever any provision of the Contract Documents requires the giving of written notice it shall be deemed to have been validly given if delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended, or if delivered at or sent by registered or certified mail, postage prepaid, to the last business address known of the giver of the notice.
B. The duties and obligations imposed by these General Conditions and Supplementary General Conditions and the rights and remedies available hereunder to the parties hereto, and, in particular but without limitation, the warranties, guarantees and obligations imposed upon CONTRACTOR and all of the rights and remedies available to OWNER and ARCHITECT thereunder, shall be in addition to, and shall not be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by law or contract, by special warranty or guarantee or by other provisions of the Contract Documents. The provisions of this paragraph shall be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right and remedy to which they apply. All representations and warranties and guarantees made in the Contract Documents shall survive final payment and termination or completion of this Agreement.
ARTICLE 2 OWNER
§2.2 delete section 2.2.6 and substitute the following:
“§2.2.6 The Owner will furnish the Contractor an electronic copy of the Contract Documents.”
ARTICLE 3 CONTRACTOR
§3.2 add following:
“§3.2.5 The Owner is entitled to reimbursement from the Contractor for amounts paid to the Architect for evaluation and responding to the Contractor’s requests for information that are not prepared in accordance with the Contract Documents or where the requested information is available to the Contractor from a careful study and comparison of the Contract Documents, field conditions, other Owner-provided information, Contractor-prepared coordination drawings, or prior Project correspondence or documentation.”
§3.4 LABOR AND MATERIALS
3.4.2 add the following:
“§3.4.2.1 After the Contract has been executed, the Owner and Architect will consider requests for the substitution of products in place of those specified only under the conditions set forth in the General Requirements (Division 1 of the Specifications).
§3.4.2.2 The Owner shall be entitled to reimbursement from the Contractor for amounts paid to the Architect for reviewing the Contractor’s proposed substitutions and making agreed-upon changes in the Drawings and Specifications resulting from such substitutions.”
SGC -2
§3.12 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES
3.12 add the following:
“§3.12.11 The Architect’s review of Contractor’s submittals will be limited to examination of an initial submittal and two (2) resubmittals. The Owner is entitled to obtain reimbursement from the Contractor for amounts paid to the Architect for evaluation of additional resubmittals.”
ARTICLE 4 ARCHITECTS
§4.2 add the following:
“§4.2.2.1 The Owner is entitled to reimbursement from the Contractor for amounts paid to the Architect for site visits made necessary by the fault of the Contractor or by defects and deficiencies in the Work.”
ARTICLE 7 CHANGES IN THE WORK
§7.1 GENERAL add the following:
“§7.1.4 The combined overhead and profit included in the total cost to the Owner for a change in the Work shall be based on the following schedule:
.1 For the Contractor, for Work performed by the Contractor’s own forces, fifteen percent (15%) of the cost.
.2 For the Contractor, for Work performed by the Contractor’s Subcontractors, eight percent (8%) of the amount due the Subcontractors.
.3 For each Subcontractor involved, for Work performed by that Subcontractor’s won forces, fifteen percent (15%) of the cost.
.4 For each Subcontractor involved, for Work performed by the Subcontractor’s Subcontractors, eight percent (8%) of the amount due the Sub-subcontractor.
.5 Cost to which overhead and profit is to be applied shall be determined in accordance with Section 7.3.7.
.6 In order to facilitate checking of quotations for extras or credits, all proposals, except those so minor that their propriety can be seen by inspection, shall be accompanied by a complete itemization of costs including labor, materials and Subcontracts. Labor and materials shall be itemized in the manner prescribed above. Where major cost items are Subcontracts, they shall be itemized also.”
ARTICLE 9 PAYMENTS AND COMPLETION
§9.3 APPLICATIONS FOR PAYMENT add the following sentence to Section 9.3.1:
“The form of Application for Payment, duly notarized, shall be a current authorized edition of AIA Document G702- 1992, Application and Certificate for Payment, supported by a current authorized edition of AIA Document G703- 1992, Continuation Sheet.”
§9.8 SUBSTANTIAL COMPLETION add the following to section 9.8.3:
“§9.8.3.1 The Architect will perform no more than two (2) inspections to determine whether the Work or a designated portion thereof has attained Substantial Completion in accordance with the Contract Documents. The Owner is entitled to reimbursement from the Contractor for amounts paid to the Architect for any additional inspections.”
§9.10 FINAL COMPLETION AND FINAL PAYMENT add the following to section 9.10.1:
“§9.10.1.1 The Architect will perform no more than one (1) inspections to determine whether the Work or a designated portion thereof has attained Final Completion in accordance with the Contract Documents. The Owner is entitled to reimbursement from the Contractor for amounts paid to the Architect for any additional inspections.”
AIA A201-2017 Supplementary Conditions to Standard form of Agreement Between Owner and Contractor State of West Virginia
Any provisions of the Contract Documents that conflict with these Supplementary Conditions shall be null and void unless they have been approved in writing by the applicable State purchasing officer and the Attorney General, and are clearly identified as such in the bid documents.
The Owner and Contractor hereby agree to the full performance of the covenants contained herein.
IN WITNESS WHEREOF, the Owner and Contractor have entered into this Agreement as of the effective date as stated in the A101-2017 (when utilized) or other Contract Documents.
Owner: Contractor:
By: By:
Title: Title:
Date: Date:
This �ntary C()Dd,itions to AIA Document A201-2017, General Conditions of the Contract for Construction, has been approved as to form on this • ay of \.tbni.D.f � . 2019, by the West Virginia Attorney General's office as indicated in the signature line below.
Any modification of this document is vd1tl unless expressly approved in writing by the West Virginia Attorney General's Office.
PATRICK MORRISEY, ATTORNEY GENERAL
BY1nQIT��
Effective Date: October 1, 2018 Page 12
TECHNICAL
SPECIFICATIONS
THIS PAGE INTENTIONALLY LEFT BLANK
WV Schools for the Deaf and Blind T60-11386 Keller Hall Renovations
SUMMARY 011000 - 1
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Access to site
4. Work restrictions.
5. Specification and Drawing conventions.
B. Related Requirements:
1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.2 PROJECT INFORMATION
A. Project Identification: WV Schools for the Deaf and Blind Keller Hall Renovations
1. Project Location: Romney, WV 26757.
B. Owner: WV Schools for the Deaf and Blind, 301 East Main Street, Romney, WV 26757
C. Architect: The Thrasher Group, 1000 Corporate Landing, Charleston, WV 25311.
D. Web-Based Project Software: Project software will be used for purposes of managing communication and documents during the construction stage.
1. See Section 013100 "Project Management and Coordination." for requirements for using web-based Project software.
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. The replacement of all windows, upgrades to portico ceiling and columns, repointing of window well brick, and installation of new stone caps. Interior improvements will provide a secure school entrance. Plumbing work will involve replacing waste piping, faucets, installing new shower inserts, mop sink, shower valves, and access doors, removing the existing water heater, and adding new water heaters equipped with thermostatic mixing valves.
WV Schools for the Deaf and Blind T60-11386
SUMMARY 011000 - 2
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.4 ACCESS TO SITE
A. General: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project.
B. Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine construction operations to within designated Limits of Disturbance (LOD) as defined on the Drawings.
2. Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times.
Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
1.5 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 6:00 p.m., Monday through Saturday, unless otherwise indicated.
1. Work hours shall comply with local ordinances.
C. Controlled Substances: Use of tobacco products is not permitted within the building after the building is enclosed, or after any finish work has commenced, or after any permanent HVAC system is in use.
D. Noise, Vibration, Dust, and Odors: Noise and vibration to be limited during work hours. Dust to be controlled by wetting to control air born dust leaving the site.
1.6 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
WV Schools for the Deaf and Blind T60-11386
SUMMARY 011000 - 3
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.
3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.
4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 00 Contracting Requirements: General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications.
C. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
WV Schools for the Deaf and Blind T60-11386
SUMMARY 011000 - 4
This page intentionally left blank.
WV Schools for the Deaf and Blind T80-11386
ALLOWANCES 012100 - 1
SECTION 012100 - ALLOWANCES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements governing allowances.
B. Types of allowances include the following:
1. Quantity allowances.
C. Related Requirements:
1. Section 012200 "Unit Prices" for procedures for using unit prices, including adjustment of quantity allowances when applicable.
1.2 SELECTION AND PURCHASE
A. At the earliest practical date after award of the Contract, advise Architect of the date when final selection, or purchase and delivery, of each product or system described by an allowance must be completed by the Owner to avoid delaying the Work.
B. At Architect's request, obtain proposals for each allowance for use in making final selections.
Include recommendations that are relevant to performing the Work.
C. Purchase products and systems selected by Architect from the designated supplier.
1.3 ACTION SUBMITTALS
A. Submit proposals for purchase of products or systems included in allowances in the form specified for Change Orders.
1.4 INFORMATIONAL SUBMITTALS
A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.
B. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance.
C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
WV Schools for the Deaf and Blind T80-11386
ALLOWANCES 012100 - 2
1.5 LUMP-SUM ALLOWANCES
A. Allowance shall include cost to Contractor of specific products and materials ordered by Owner or selected by Architect under allowance and shall include taxes, freight, and delivery to Project site.
B. Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials ordered by
Owner or selected by Architect under allowance shall be included as part of the Contract Sum and not part of the allowance.
1.6 QUANTITY ALLOWANCES
A. Allowance shall include cost to Contractor of specific products and materials ordered by Owner or selected by Architect under allowance and shall include taxes, freight, and delivery to Project site.
B. Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials ordered by
Owner or selected by Architect under allowance shall be included as part of the Contract Sum and not part of the allowance.
1.7 ADJUSTMENT OF ALLOWANCES
A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place where applicable. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins.
1. Include installation costs in purchase amount only where indicated as part of the allowance.
2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other markups.
3. Submit substantiation of a change in scope of Work, if any, claimed in Change Orders related to unit-cost allowances.
4. Owner reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.
B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit.
1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of Work has changed from what could have been foreseen from information in the Contract Documents.
2. No change to Contractor's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated.
WV Schools for the Deaf and Blind T80-11386
ALLOWANCES 012100 - 3
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
3.3 SCHEDULE OF ALLOWANCES
A. Allowance No. 1: Quantity Allowance: Include 60 linear feet of brick repointing.
1. Coordinate quantity allowance adjustment with unit-price requirements in
Section 012200 "Unit Prices."
B. Allowance No. 2: Quantity Allowance: Include 100 linear feet of cast stone repair or replacement.
1. Coordinate quantity allowance adjustment with unit-price requirements in
Section 012200 "Unit Prices."
END OF SECTION 012100
WV Schools for the Deaf and Blind T80-11386
UNIT PRICES 012200 - 1
SECTION 012200 - UNIT PRICES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for unit prices.
1.2 DEFINITIONS
A. Unit price is an amount incorporated into the Agreement, applicable during the duration of the
Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased.
B. Contractor provided Unit Prices indicated on the Bid Form are not considered by the Owner when determining the lowest qualified bidder. For additional information refer to the
Instructions to Bidders.
1.3 PROCEDURES
A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.
B. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.
C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.
D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SCHEDULE OF UNIT PRICES
A. Unit Price No. 1: Brick repointing.
1. Unit of Measurement: Linear foot.
WV Schools for the Deaf and Blind T80-11386
UNIT PRICES 012200 - 2
2. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in
Section 012100 "Allowances."
B. Unit Price No. 2: Cast stone.
1. Unit of Measurement: Linear foot.
2. Quantity Allowance: Coordinate unit price with allowance adjustment requirements in
Section 012100 "Allowances."
END OF SECTION 012200
WV Schools for the Deaf and Blind T80-11386
SUBSTITUTION PROCEDURES 012500 - 1
SECTION 012500 - SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
B. Related Requirements:
1. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.
2. Section 013100 “Project Management and Coordination” for requirements for coordination drawings.
1.2 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer an advantage to
Contractor or Owner.
1.3 ACTION SUBMITTALS
A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Substitution Request Form: Use form at the end of this Section.
2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
a. Statement indicating why specified product or fabrication or installation method cannot be provided, if applicable.
b. Coordination of information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable Specification Section.
Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific
WV Schools for the Deaf and Blind T80-11386
SUBSTITUTION PROCEDURES 012500 - 2
features and requirements indicated. Indicate deviations, if any, from the Work specified.
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested.
g. List of similar installations for completed projects, with project names and addresses as well as names and addresses of architects and owners.
h. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated.
i. Research reports evidencing compliance with applicable building codes in effect for Project.
j. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall
Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
k. Cost information, including a proposal of change, if any, in the Contract Sum.
l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents, except as indicated in substitution request, is compatible with related materials and is appropriate for applications indicated.
m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution.
Architect will notify Contractor of acceptance or rejection of proposed substitution within
15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.
a. Forms of Acceptance: Change Order, Construction Change Directive, or
Architect's Supplemental Instructions for minor changes in the Work.
b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.
1.4 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
1.5 PROCEDURES
A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.
WV Schools for the Deaf and Blind T80-11386
SUBSTITUTION PROCEDURES 012500 - 3
1.6 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 30-days prior to time required for preparation and review of related submittals.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. Substitution request is fully documented and properly submitted.
c. Requested substitution will not adversely affect Contractor's construction schedule.
d. Requested substitution has received necessary approvals of authorities having jurisdiction.
e. Requested substitution is compatible with other portions of the Work.
f. Requested substitution has been coordinated with other portions of the Work.
g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
B. Substitutions for Convenience: Architect will consider requests for substitution if received within 30-days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of Architect.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities
Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.
b. Requested substitution does not require extensive revisions to the Contract
Documents.
c. Requested substitution is consistent with the Contract Documents and will produce indicated results.
d. Substitution request is fully documented and properly submitted.
e. Requested substitution will not adversely affect Contractor's construction schedule.
f. Requested substitution has received necessary approvals of authorities having jurisdiction.
g. Requested substitution is compatible with other portions of the Work.
h. Requested substitution has been coordinated with other portions of the Work.
i. Requested substitution provides specified warranty.
WV Schools for the Deaf and Blind T80-11386
SUBSTITUTION PROCEDURES 012500 - 4
j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
WV Schools for the Deaf and Blind T80-11386
SUBSTITUTION PROCEDURES 012500 - 5
WV Schools for the Deaf and Blind T80-11386
SUBSTITUTION PROCEDURES 012500 - 6
END OF SECTION 012500
WV Schools for the Deaf and Blind T80-11386
CONTRACT MODIFICATION PROCEDURES 012600 - 1
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing
Contract modifications.
1.2 MINOR CHANGES IN THE WORK
A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710.
1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change.
1.3 PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change.
2. Within time specified in Proposal Request or 20 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the
Contract Sum and the Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include all subcontractor proposals, with labor and material costs listed separately.
e. Include all material supplier proposals.
f. Include a revised CPM Baseline Schedule for review, that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
g. Include a revised Schedule of Values for review.
B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the
Contract, Contractor may initiate a claim by submitting a request for a change to Architect.
1. Include a statement outlining reasons for the change and the effect of the change on the
Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
WV Schools for the Deaf and Blind T80-11386
CONTRACT MODIFICATION PROCEDURES 012600 - 2
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include all subcontractor proposals, with labor and material costs listed separately.
6. Include all material supplier proposals.
7. Include a revised CPM Baseline Schedule for review, that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the
Contract Time.
8. Include a revised Schedule of Values for review.
9. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.
10. Claims shall be made within 20 days of the discovery of need for Change. Claims made after that time are not considered valid.
1.4 CHANGE ORDER PROCEDURES
A. Owner's approval of a Work Change Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on AIA Document G701.
1.5 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: Architect may issue a Construction Change Directive on
AIA Document G714. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the
Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the
Construction Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
PART 2 - PRODUCTS (Not Used)
PART 4 - END OF SECTION 012600
WV Schools for the Deaf and Blind T80-11386
PAYMENT PROCEDURES 012900 - 1
SECTION 012900 - PAYMENT PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process
Applications for Payment.
1.2 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the Schedule of Values with preparation of
Contractor's construction schedule.
1. Coordinate line items in the schedule of values with items required to be indicated as separate activities in Contractor's construction schedule.
2. Submit the Schedule of Values to Architect at earliest possible date, but no later than seven days before the date scheduled for submittal of initial Applications for Payment.
B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section.
1. Arrange Schedule of Values consistent with format of AIA Document G703.
2. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Provide multiple line items for principal subcontract amounts in excess of five percent of the Contract Sum.
3. Provide a separate line item in the Schedule of Values for each part of the Work where
Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.
a. Differentiate between items stored on-site and items stored off-site.
4. Allowances: Provide a separate line item in the Schedule of Values for each allowance.
Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities.
5. Overhead Costs: Include total cost and proportionate share of general overhead and profit for each line item.
6. Overhead Costs: Show cost of temporary facilities and other major cost items that are not direct cost of actual work-in-place as separate line items.
7. Closeout Costs. Include separate line items under Contractor and principal subcontracts for Project closeout requirements in an amount totaling five percent of the Contract Sum and subcontract amount.
8. Schedule of Values Revisions: Revise the Schedule of Values when Change Orders or
Construction Change Directives result in a change in the Contract Sum. Include at least one separate line item for each Change Order and Construction Change Directive.
WV Schools for the Deaf and Blind T80-11386
PAYMENT PROCEDURES 012900 - 2
1.3 APPLICATIONS FOR PAYMENT
A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Architect and paid for by Owner.
B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.
1. Submit draft copy of Application for Payment seven days prior to due date for review by
Architect.
C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 as form for Applications for Payment.
D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.
1. Entries shall match data on the Schedule of Values and Contractor's construction schedule. Use updated schedules if revisions were made.
2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.
3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
E. Retainage: A five percent (5%) retainage will be maintained throughout the construction period.
The Owner will pay ninety-five percent (95%) of the portion of the Contract Sum allocable to labor, material and equipment incorporated in the Work, and of materials, and equipment suitably stored at the site or at some other location agreed upon in writing by the Owner, for a period covered by the most current submitted Application for Payment, less the aggregate of previous payments.
F. Transmittal: Submit three signed and notarized original copies of each Application for Payment to Architect by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.
1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.
G. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from subcontractors, sub-subcontractors, and suppliers for construction period covered by the previous application.
1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.
2. When an application shows completion of an item, submit conditional final or full waivers.
3. Owner reserves the right to designate which entities involved in the Work must submit waivers.
WV Schools for the Deaf and Blind T80-11386
PAYMENT PROCEDURES 012900 - 3
4. Submit final Application for Payment with or preceded by conditional final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.
5. Waiver Forms: Submit executed waivers of lien on forms acceptable to Owner.
H. Initial Application for Payment: Administrative actions and submittals that must precede the submittal of first Application for Payment include the following:
1. Projected Schedule of Values.
2. Projected Construction Schedule. With approved CPM Baseline.
3. Copies of building permits.
4. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.
5. Report of preconstruction conference.
6. Certificates of insurance and insurance policies.
7. Performance and payment bonds.
8. Data needed to acquire Owner's insurance.
I. Applications for Payment during Construction: Administrative actions and submittals that must be provided with each Application for Payment includes the following:
1. Updated CPM Schedule showing Baseline and progress.
2. Updated Schedule of Values.
3. Updated Submittal Schedule.
J. Application for Payment at Substantial Completion: After Architect issues the Certificate of
Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work.
K. Final Payment Application: After completing Project closeout requirements, submit final
Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.
3. Updated final statement, accounting for final changes to the Contract Sum.
4. AIA Document G706.
5. AIA Document G706A.
6. AIA Document G707.
7. Evidence that claims have been settled.
8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.
9. Final liquidated damages settlement statement.
WV Schools for the Deaf and Blind T80-11386
PAYMENT PROCEDURES 012900 - 4
END OF SECTION 012900
WV Schools for the Deaf and Blind T80-11386
PROJECT MANAGEMENT AND COORDINATION 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. RFIs.
4. Digital project management procedures.
5. Project meetings.
B. Related Requirements:
1. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
1.2 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
1.3 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
WV Schools for the Deaf and Blind T80-11386
PROJECT MANAGEMENT AND COORDINATION 013100 - 2
B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation, maintenance and updating of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
1.4 COORDINATION DRAWINGS
A. Coordination Drawings, General: Prepare coordination drawings as required to verify compatibility with associated systems and adjacent Work, installation requirements for components, and where installation is not completely indicated on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.
1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements.
Provide alternative sketches to Architect indicating proposed resolution of such conflicts. Required dimensional changes and difficult installations will not be considered changes to the Contract.
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Plenum Space: Indicate sub-framing for support of ceiling, and wall systems, fire suppression, mechanical and electrical equipment, and related Work. Locate components within plenums to accommodate layout of light fixtures and other components indicated on Drawings. Indicate areas of conflict between light fixtures and other components.
3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.
4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door
WV Schools for the Deaf and Blind T80-11386
PROJECT MANAGEMENT AND COORDINATION 013100 - 3
floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.
6. Coordination Drawings may need to include existing conditions exposed by demolition activities and relationship to new systems and components.
7. Review: Architect may review coordination drawings to confirm that, in general, the
Work is being coordinated, but not for the details of the coordination, which are
Contractor's responsibility. If Architect determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Architect may inform Contractor, who shall make suitable modifications and resubmit.
8. Conflicts arising from the Contractor’s failure to complete and provide Coordination
Drawings shall not constitute valid grounds for additional compensation.
C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Submittal Format: Submit or post coordination drawing files using PDF format.
2. BIM File Incorporation: Contractor may develop and incorporate coordination drawing files into BIM established for Project.
3. Upon request the Architect will furnish Contractor one set of digital data files of
Drawings for use in preparing coordination digital data files.
a. The Architect makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings of existing conditions or new construction.
b. Digital Data Software Program: Drawings are available in Revit 2021.
c. The Contractor, subcontractors and material suppliers that will use the digital data files for purposes of coordination drawings shall execute a data licensing agreement in the form of the Electronic Files Documents Release Form included in this Project Manual.
1.5 REQUEST FOR INFORMATION (RFI)
A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Architect will return without response those RFIs submitted to Architect by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
3. Submit RFI Forms using PDF format with a unique RFI number. Example; “AES-RFI-4” and as an example for a follow-up to that RFI, “AES-RFI-4A”.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Owner name.
2. Name of Architect.
3. Architect's Project number.
4. Date.
5. Name of Contractor.
WV Schools for the Deaf and Blind T80-11386
PROJECT MANAGEMENT AND COORDINATION 013100 - 4
6. RFI number, numbered sequentially.
7. RFI subject.
8. Specification Section number and title and related paragraphs, as appropriate.
9. Drawing number and detail references, as appropriate.
10. Field dimensions and conditions, as appropriate.
11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
12. Contractor's signature.
13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
C. RFI Forms: AIA Document G716 or form with substantially the same content as indicated above, acceptable to Architect.
D. Architect's Action: Architect will review each RFI, determine action required, and respond.
Allow seven days for Architect's response for each RFI. RFIs received by Architect after 12:00 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e.