Preliminary Results~59.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- Ona Beach Maintenance Station Improvements
- Solicitation number
- S-73000-00008954
- Issued by
- Klamath County, Oregon
About this file
This document is a bid tabulation sheet for the Ona Beach Maintenance Station Repairs project, a state and local contract opportunity in Lincoln County, Oregon. The project involves upgrading the District Office 201 siding, windows and exterior doors, new personnel doors and miscellaneous exterior repairs to Maintenance Building 202, as well as exterior overhead sectional and personnel doors in Storage Building 205 and the addition of overhead doors to Storage Building 207. The bid closing date is 01/24/2024 at 1:00 PM. Four bidders submitted proposals, including Buck Canyon Construction LLC, CMH Remodeling LLC, Ordell Custom LLC, and Z Terrell & Son.
The bid tabulation sheet provides the unit prices and total prices for the base bid and two additive alternates. The base bid covers all the work excluding the additive alternates, while the additive alternates address the storage building improvements. The total bid amounts range from $418,144 to $706,863. This bid tabulation is not an indicator of award, but rather a compilation of the bids submitted for consideration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 35877 ITB_Final.docx | DOCX document | |
| Attachment A (Plans)~2.pdf | ||
| Attachment B (Specifications)~1.pdf | ||
| Attachment D (Description of Base Bid and Alternates)~1.docx | DOCX document | |
| Attachment C (Bid Pricing Form)~3.xlsx | XLSX spreadsheet | |
| ITB_Addendum 3.docx | DOCX document | |
| ITB_Addendum 1.docx | DOCX document | |
| ITB_Addendum 2.docx | DOCX document | |
| Intent To Award~3.xlsx | XLSX spreadsheet | |
| Notice of Intent to Award-All bidders~4.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 1/24/24 | |||||
| ITB No. | S-73000-00008954 | BIDDER | ||||
| NAME: | Buck Canyon Construction LLC | CMH Remodeling LLC | Ordell Custom LLC | Z Terrell & Son | ||
| Bid Closing: | 01/24/2024 @ 1:00 PM | |||||
| Description: | Ona Beach Maintenance Station Repairs | |||||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | BASE BID (All work excluding additive alternates). | 1 | LS | $ 302,419.00 | $ 302,419.00 | $ 393,434.00 | $ 393,434.00 | $ 335,131.00 | $ 335,131.00 | $ 581,656.00 | $ 581,656.00 |
| 2 | Additive Alternate #1 Storage Building 205. Furnish and install (4) 14’-0” X 15’-0” Overhead Sectional Doors (103A, 103B, 103C, 103D AND SIX (6) 14’-0” X 14’-0” Overhead Sectional Doors (102B, 102C, 102D, 102E, 102F, 102G) | 1 | $ 78,875.00 | $ 78,875.00 | $ 132,839.00 | $ 132,839.00 | $ 192,598.00 | $ 192,598.00 | $ 88,511.00 | $ 88,511.00 | |
| 3 | Additive Alternate #2 Storage Building 207. Furnish and install (4) 16'-0" X 16'-0" Overhead Sectional Doors (100A, 100B, 100C, 100D) | 1 | LS | $ 36,850.00 | $ 36,850.00 | $ 73,727.00 | $ 73,727.00 | $ 86,218.00 | $ 86,218.00 | $ 36,696.00 | $ 36,696.00 |
| TOTAL | $ 418,144.00 | $ 600,000.00 | $ 613,947.00 | $ 706,863.00 |
File details come from the government source that posted it. Updated .